Professional Documents
Culture Documents
uide 4th Edition, and the PMI Practice Standard for Earned Value Management (2005)
You need to fill in at least the data in the blue table "Basic data points". (Duration in months is optional) v2.1 - 02 June 2011 - If you find an error or have a suggestion, you can contact me: xavier@lescalier.eu
Status:
Earned Value (EV) € 6,700.00 Monetary BAC * percentage completed Budgeted Cost of Work Performed (BCWP)
Planned Value (PV) € 7,000.00 Monetary BAC * percentage planned Budgeted Cost of Work Scheduled (BCWS)
% Completed (inverted calculation) 67.00% Percentage EV/BAC
% Planned (inverted calculation) 70.00% Percentage PV/BAC
% Spent (inverted calculation) 80.00% Percentage AC/BAC
Performance:
Cost Performance Indicator (CPI) 0.84 Indice EV/AC How efficiently are we using our resources? (Less than 1 is over budget)
Schedule Performance Indicator (SPI) 0.96 Indice EV/PV How efficient are we using time? (Less than 1 is behind schedule)
To Complete Performance Index (TCPI BAC) 1.65 Indice (BAC-EV)/(BAC-AC) How efficient must we use our remaining resources? (if we want to reach our original BAC)
To Complete Performance Index (TCPI EAC) 0.84 Indice (BAC-EV)/(EAC-AC) How efficient must we use our remaining resources? (if we want to reach the currently calculated EAC)
Cost Schedule Index (CSI) 0.80 Indice CPI * SPI
Variance:
Cost Variance (CV) -€ 1,300.00 Monetary EV-AC Are we under or over budget?
Schedule Variance (SV) -€ 300.00 Monetary EV-PV Are we ahead or behind Schedule?
Cost Variance (CV%) -19.40% Percentage CV/EV Are we under or over budget?
Schedule Variance (SV%) -4.29% Percentage SV/PV Are we ahead or behind Schedule?
Variance at Completion (VAC) -€ 1,940.30 Monetary BAC-EAC Will we be under or over budget?
Variance at Completion (VAC%) -19.40% Percentage VAC/BAC Will we be under or over budget?
Status:
Earned Value (EV) € 6,700.00 Monetary BAC * percentage completed Budgeted Cost of Work Performed (BCWP)
Planned Value (PV) € 7,000.00 Monetary BAC * percentage planned Budgeted Cost of Work Scheduled (BCWS)
% Completed (inverted calculation) 67.00% Percentage EV/BAC
% Planned (inverted calculation) 70.00% Percentage PV/BAC
% Spent (inverted calculation) 80.00% Percentage AC/BAC
Performance:
Cost Performance Indicator (CPI) 0.84 Indice EV/AC How efficiently are we using our resources? (Less than 1 is over budget)
Schedule Performance Indicator (SPI) 0.96 Indice EV/PV How efficient are we using time? (Less than 1 is behind schedule)
To Complete Performance Index (TCPI BAC) 1.65 Indice (BAC-EV)/(BAC-AC) How efficient must we use our remaining resources? (if we want to reach our original BAC)
To Complete Performance Index (TCPI EAC) 0.84 Indice (BAC-EV)/(EAC-AC) How efficient must we use our remaining resources? (if we want to reach the currently calculated EAC)
Cost Schedule Index (CSI) 0.80 Indice CPI * SPI
Variance:
Cost Variance (CV) -€ 1,300.00 Monetary EV-AC Are we under or over budget?
Schedule Variance (SV) -€ 300.00 Monetary EV-PV Are we ahead or behind Schedule?
Cost Variance (CV%) -19.40% Percentage CV/EV Are we under or over budget?
Schedule Variance (SV%) -4.29% Percentage SV/PV Are we ahead or behind Schedule?
Variance at Completion (VAC) -€ 1,940.30 Monetary BAC-EAC Will we be under or over budget?
Variance at Completion (VAC%) -19.40% Percentage VAC/BAC Will we be under or over budget?
Indice Rendimiento del Costo IRC CPTR/CRTR (<1 = sobrepasado presupuesto) 0.92 =+H12/H13 Cost Performance Index - CPI
Indice de Rendimiento para Completar IRPC (CPF-CPTR)/(CPF-CRTR) 1.14 =+(H10-H12)/(H10-H13) To Complete Performance Index - TCPI
Costo Estimado a la Finalización CEF CRTR+(CRTR/CPTR)*(CPF-CPTR) 866.67 € =+H13+(H13/H12)*(H10-H12) Estimate At Completion - EAC
Variación al Finalizar VAF CPF-CEF - 66.67 € =+H10-H21 Variance At Completion - VAC
Calculadora para Gerenciamen
IDP
Mortgage Information
www.radardeprojetos.com.br
VA VP CR VA
CR (Real) (Agregado) Acumulado Acumulado Acumulado IDC VC IDP
-280.00
-1,450.00
4,280.00
-280.00
1.24
1450.00
ardeprojetos.com.br
VPR
0.00
0.00
-500.00
-950.00