SOLUTION – PROJECT MANAGEMENT

Sample test

SECTION 1:

SECTION 2:
Question 1

Question 2
Question 3
Status report: Ending period 1
%
Task AC EV PV SV CV Assessment
complete
A 50 6 6 4 2 0 Above schedule, right cost
B 40 8 6 0 6 -2 Above schedule,overcost
C 25 3 2 4 -2 -1 Behind schedule, overcost
Cumulative totals 17 14 8 6 -3 Above schedule, overcost
Status report: Ending period 3
%
Task AC EV PV SV CV Assessment
complete
A Finished 13 12 12 0 -1 Right schedule, overcost
B 80% 15 12 10 2 -3 Above schedule, overcost
C Finished 10 8 8 0 -2 Right schedule, overcost
D 50% 4 3 6 -3 -1 Behind schedule, overcost
E 0% 0 0 0 0 0 N/A
F 20% 4 1.8 0 1.8 -2.2 Above schedule, overcost
Cumulative totals 46 36.8 36 0.8 -9.2 Above schedule, overcost

Final CV: -9.2

Final SV: 0.8

Final CPI: 0.8

PCIB = EV/BAC = 0.57