You are on page 1of 10

Pressure Test: Hydrostatic and Pneumatic Test

Requirements

CATEGORY REFRIGERATION

MOST
DISTRICT
DISTRICT
TURBINE INLET
THERMAL ENERGY

RECENT COOLING HEATING AIR COOLING STORAGE

INDUSTRIAL

REFRIGERATION

BLOG > PRESSURE TEST: HYDROSTATIC AND PNEUMATIC TEST REQUIREMENTS

5 min

Pressure tests are a non-destructive way to guarantee the integrity of equipment such as pressure vessels,
pipelines, plumbing lines, gas cylinders, boilers and fuel tanks. It is required by the piping codes to confirm
that a piping system is able to bear its rated pressure and it has no leaks. The most widely used code for
pressure and leak test is the ASME B31 Pressure Piping Code. Among its several sections, the
requirements and procedures listed in the codes below are followed by ARANER:

ASME B31.1 Power Piping


ASME B31.3 Process Piping
ASME B31.5 Refrigeration Piping
Pressure tests may be done either with liquid, usually water (hydrostatic), or with gas, usually dry nitrogen
(pneumatic).  

General requirements of pressure test


1. Stress exceeding yield strength: the test pressure may be reduced to the maximum pressure that
will not exceed the yield strength at test temperature.
2. Test fluid expansion: If the test pressure is to be maintained for a period of time and the fluid in the
system is subject to thermal expansion, precautions shall be taken to avoid excessive pressure.
3. Preliminary pneumatic test: a preliminary test using air at no more than 170 kPa (25 psi) gage
pressure may be made prior to hydrostatic or pneumatic testing to locate major leaks.
4. Examination for leaks: a leak test shall be maintained for at least 10 minutes, and all joints and
connections shall be examined for leaks.
5. Heat treatment: Leak tests shall be conducted after any heat treatment has been completed.
6. Low-test temperature: The possibility of brittle fracture shall be considered when conducting leak
tests at metal temperatures near the ductile-brittle transition temperature.
7. Personnel protection: Suitable precautions in the event of piping system rupture shall be taken to
eliminate hazards to personnel in the proximity of lines being tested.
8. Repairs or additions after leak testing: If repairs or additions are made after the leak test, the
affected piping shall be retested.
9. Test records: Records shall be made of each piping system during the testing, including:
Date of test
Identification of piping system tested
Test fluid
Test pressure
Certification of results by examiner 

Preparation for testing


1. Exposure of joints: all joints including welds not previously pressure tested shall be left uninsulated
and exposed for examination during the test.
2. Addition of temporary supports: piping systems designed for vapor or gas shall be provided with
additional temporary supports if necessary to support the weight of the test liquid.
3. Restraint or isolation of expansion joints: expansion joints shall be provided with temporary
restraint if required for the additional pressure load under test.

Isolation of equipment and piping not subjected to pressure test: Equipment that is not to be subjected
to the pressure test shall be either disconnected from the system or isolated by a blank or similar means.
Figure 1: Isolation of piping

Hydrostatic Test
1. Test fluid: The fluid shall be water unless there is the possibility of damage due to freezing or to
adverse effects of water on the piping or the process. In that case, another non-toxic liquid may be
used.
2. Provision of air vents at high points: Vents shall be provided at high points of the piping system to
purge air pockets while system is filling.
3. Pressure and procedure: The pressure limits are different for ASME B31.1 and ASME B31.3.

  

ASME B31.1

The hydrostatic test pressure at any point in the piping system shall not be less than 1.5 times the design
pressure, but shall not exceed the maximum allowable test pressure of any non-isolated component, nor
shall it exceed the limits of calculated stresses due to occasional loads.

ASME B31.3

The test pressure shall be not less than 1.5 times the design pressure. When the design temperature is
greater than the test temperature, the minimum pressure shall be calculated by eq.  P T = 1,5P S T/S , where
=allowable stress at test temperature, S=allowable stress at component design temperature, P=design gage
pressure. The test pressure may be reduced to the maximum pressure that will not exceed the lower of the
yield strength or 1.5 times the component ratings at test temperature. The pressure shall be continuously
maintained for a minimum time of 10 minutes and may then be reduced to the design pressure and held
for such time as may be necessary to conduct the examinations for leakage. Examinations for leakage shall
be made of all joints and connections.

Pneumatic Test
1. Precautions: Pneumatic testing involves the hazard of released energy stored in compressed gas.
Particular care must be taken. It is recommended to be used only when piping systems are so
designed that they cannot be filled with water, i.e, refrigerant systems; or when piping systems are to
be used in services where traces of the testing medium cannot be tolerated.
2. Test fluid: The gas used as test fluid, if not air, shall be nonflammable and nontoxic, such as nitrogen.
3. Pressure and procedure: the pressure limits and methodology is different for the codes mentioned
above.

ASME B3.1

The pneumatic test pressure shall not be less than 1.2 nor more than 1.5 times the design pressure of the
piping system. It shall not exceed the maximum allowable test pressure of any non-isolated component. The
pressure in the system shall gradually be increased to not more than 1/2 of the test pressure, after which
the pressure shall be increased in steps of approximately 1/10 of the test pressure until the required
test pressure is reached. The pressure shall be continuously maintained for a minimum time of 10 min. It
shall then be reduced to the lower of design pressure or 100 psig [700 kPa (gage)] and held for such time
as may be necessary to conduct the examination for leakage. Examination for leakage by soap bubble or
equivalent method shall be made of all joints and connections.

ASME B31.3
The test pressure shall not be less than 1.1 times the design pressure and shall not exceed the lower of
1.33 times the design pressure or the pressure that would produce a nominal pressure stress or
longitudinal stress in excess of 90 % of the yield stress of any component at the test temperature. The
pressure shall be increased until a gage pressure, which is the lower of 0.5 times the test pressure or 170
kPa (25 psi), at which time a preliminary check shall be made. Thereafter, the pressure shall be gradually
increased in steps until the pressure is reached, holding the pressure at each step until the piping strains are
equalized. The pressure shall then be reduced to the design pressure before examining for leakage.
During the test, a pressure relief device shall be provided, having a set pressure not higher than the test
pressure plus the lower of 345 kPa (50 psi) or 10% of the test pressure.

ASME B31.5

The test pressure shall be at least 1.1 and shall not exceed 1.3 times the design pressure of any
component in the system. The pressure in the system shall be gradually increased to 0.5 times the test
pressure, after which the pressure shall be increased in steps of approximately 1/10 of the test pressure
until the required test pressure is reached. The test pressure shall be maintained for at least 10 minutes.
It may then be reduced to the design pressure and conduct the examination for leakage. During the test, a
pressure relief device shall be provided, having a set pressure above the test pressure, but low enough to
prevent permanent deformation of any of the system components.
ARANER, the industrial cooling engineering experts
We are experts in designing, manufacturing and installing tailor-made industrial cooling solutions with a
positive economic impact. We have worked worldwide in the development of Turbine Inlet Air Cooling,
District Cooling and Thermal Energy Storage. Get in touch with our experts if you are interested in any of
our solutions or if you need technical advice. We will be glad to help!    
Related posts

Refrigeration

WHICH FACTORS WILL AFFECT THE CHILLER SIZING PROCESS?

An industrial chiller protects processing equipment despite costing a small ...

READ MORE

Refrigeration

DIFFERENT HEAT REJECTION CONDENSING TECHNOLOGIES

Any process that does work or uses energy produces heat, according to ...

READ MORE
READ MORE

Refrigeration

KEY TECHNOLOGY TO REDUCE CARBON FOOTPRINT IN THE


INDUSTRIAL SECTOR

  About 25% of greenhouse effect emanates from the industrial sector, either ...

READ MORE

Refrigeration

TEMPERATURE CONTROL TECHNOLOGY: BEST PRACTICES IN


POWER PLANTS

You recognize that all types of power plants (gas based, coal-fired or oil) ...
READ MORE

CONTACT

We want to become your trustful technological partner

We create solutions and guarantee success by taking full responsibility of the


overall project. 

GET IN REQUEST A
TOUCH MEETING

DISTRICT COOLING

THERMAL STORAGE

HEAT PUMPS

DISTRICT HEATING

INDUSTRIAL REFRIGERATION

ABSORPTION SYSTEM

TURBINE COOLING

DATA CENTER

ARANER © 2021
Privacy Policy
Legal advise
Cookie policy
Careers

LINKEDIN
YOUTUBE
info@araner.com

You might also like