Professional Documents
Culture Documents
Reactive (lagging) monitoring measures that could be readily available for use by the tyre fitting
organization are:
Timely first aid treatment was given to the injured worker and it was made sure that the first
aider is present with the unconscious worker until the help arrives.
Immediately the emergency services were called, and the injured worker was taken to the
nearest hospital for further treatment.
After the accident senior management was informed straight away so that the correct
measures can be taken.
For the time being the work is stopped and everything is left as it is.
Manager interrogated the customer in a private room and recorded the interview
conservation using mobile phone recorder
Manager visited the accident scene and took photograph to record observation for further
investigations.
manager telephoned the next of kin to inform about injured worker and hospital treatment
The enforcement agencies are notified, and an online report is submitted.
investigation of the accident is completed, and findings of the investigation are
communicated to the workers.
After some days labor inspector visited the workshop and checked all safety related
documents. online submitted accident report was also discussed, and control measure were
suggested
Reference: