Professional Documents
Culture Documents
4
4
1. introductions
2.How To identify the project schedule management
knowledge area’s processes
3. How to Plan schedule Management
4. How to Define Activities
5. How to Sequence Activities
7. How to Estimate Activity Duration
8. How to Develop Schedule
9. How to Control Schedule
Time MGMT Processes
Plan Schedule Management Planning
T i m e M a n a g e m e n t
6.1 Plan Schedule Management
Inputs :
Project Management Plan
Project Charter
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Expert Judgment
Data analysis
Meetings
Outputs :
Schedule Management Plan
I/P:
1-Project Management Plan…..It includes the Scope Baseline which contains the
Work packages which need to be decomposed to Activities , it includes also the Risks
which needed to be added as contingencies and also to not start from Scratch , Risk
Management Plan to consider The Risk Management Activities Time and
development approach .
2-Project Charter….. The project charter defines the summary milestone schedule
and project approval requirements which may be very difficult or need more
approvals to get the final approval and all of this will increase the Time.
4-OPA…..Templates for Sch. MGMT Plan or Lessons Learned from Previous Projects ,
Procedures of Change Control .
T&T:
It includes:
• Scheduling methodology and the scheduling tool to be used.(MS Project or
Primavera – CPM or CCM).
• Acceptable accuracy of activity duration estimates.(1% to 10% for each
Activity for risk as the Estimate still not totally accurate)
• Units of measure (hour / day / week).(Staff Hour , Staff Days as Activity
Duration will be with Hours , days , Weeks)
• Process and frequency to update the status and record progress.
• Allowed variance before some action needs to be taken (thresholds).(You
must not Exceed 10% increase in Activity Estimation)
• Rules of performance measurement (Percent complete, EVM).(Measure the
Performance during the Execution)
• Formats and frequency for the various schedule reports. (The Agreed Format)
Define activity
• Definition
The process of identifying and documenting
the specific actions to be performed to
produce the project deliverables.
Lecture 06 : Project Time Management (5/31)
2. Define Activities (Planning)
T i m e M a n a g e m e n t
6.2 Define Activities
Inputs :
Project management plan
Schedule Management Plan
Scope Baseline
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Decomposition
Rolling Wave Planning
Expert Judgment
meeting
Outputs :
Activity List
Activity Attributes
Milestone list
Define Activities
The key benefit of this process is to break down work packages into activities that
provide a basis for estimating, scheduling, executing, monitoring, and controlling the
project work.
Scope Baseline……. It contains the WBS which contains Work packages which will
be decomposed to Activities and also it contains WBS Dictionary which describe each
WP .
Note: Involving team members in the decomposition can lead to better and more
accurate results due to their Experience in his work moreover you get the Team Buy-
In as all the Teams know the work and agreed on it .
T i m e M a n a g e m e n t
6.3 Sequence Activities
Inputs :
Schedule Management Plan
Schedule management plan
Scope baseline
Project documents
Activity List
Activity Attributes
Milestone list
Assumptions log
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Precedence Diagramming Method (PDM)
Dependency Determination
Leads and Lags PMIS
Outputs :
Project Schedule Network Diagram Project document Updates
Sequence Activities
The key benefit of this process is that it defines the logical sequence of work to
obtain the greatest efficiency given all project constraints.
I/P:
Project management plan
1-Schedule Management Plan….. How to Sequence the Activities & What is the
used tool : MS Project and the method of Sequencing ..
2.Scope base line
Project Scope Statement……….It includes Product Characteristics and Assumptions
and Constraints .
(Ex. You can’t install the Door of the Villa without installing the Villa , You can’t test
the Car without Completing it , you must check that there is a Spoon , Cup , Sugar and
Tea before Proceeding in making a cub of Tea or may be a Competent Resource which
will proceed in specific activity will not be available before 1 Month)
Project documents
1.Activity List……It contains the activities which need to be sequenced.
2.Activity Attributes……It includes the necessary Logical Relationships to help in this
Process .
3.Milestone List……The milestone list may have scheduled dates for specific
milestones, which may influence the way activities are sequenced.
4. Assumption log
6-EEF………PMIS (MS Project or Primavera) , if there is a security problem in the
Country so you must get a car from the police to be with the team and must inform
the Police 2 days before or if there is a Bedding so I must follow the steps of this
Bedding.
• Finish to Start ……. A logical relationship in which a successor activity cannot start
until a predecessor activity has finished.
Example: The awards ceremony (successor) cannot start until the race (predecessor)
has finished.
I must finish the Work before testing it , Development can not be started until the
design is finished
• Finish to Finish……A logical relationship in which a successor activity cannot finish
until a predecessor activity has finished. Example: Writing a document (predecessor)
is required to finish before editing the document (successor) can finish. , In Pray , The
Leader must finish the Pray to let the others Finish The Pray , The broadcast of a
football match cannot finish until the match is finished. So the match is not depended
in broadcast, but the broadcast is, if the match takes longer than the initial estimated
time broadcast will also continue till that time.
3-Leads and Lags…. A lead is the amount of time whereby a successor activity can be
advanced with respect to a predecessor Activity , Ex. starting the Installation
although the design not totally finished “Fast Tracking” to compress the Schedule .
A lag is the amount of time whereby a successor activity will be delayed with respect
to a predecessor activity , Ex. The Food must take some time in the Oven to be ready
so this time is Lag and as well we must wait till the Concrete be dried to start the
Work or wait the Walls to be dried , this waiting time is Lag .
O/P:
1-Project Schedule Network Diagrams
A project schedule network diagram is a graphical
representation of the logical relationships, also
referred to as dependencies, among the project
schedule activities.
T i m e M a n a g e m e n t
6.5 Estimate Activity Duration
Inputs :
project Management Plan
Project documents
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Expert Judgment
Analogous Estimating
Parametric Estimating
Three-Point Estimates
Group Decision-Making Techniques
data Analysis
Meeting
Bottom-up estimate
Outputs :
Duration Estimates
Basis for estimates
Project document Updates
Estimate Activity
Durations
The key benefit of this process is that it provides the amount of time each activity
will take to complete , more accurate cost and duration estimates.
I/P:
Project management plan
Schedule Management Plan…. The schedule management plan defines the
Estimation to be used and the level of accuracy and units of Measures like hours or
Days .
Project documents
1.Activity List….. The activity list identifies the activities that will need duration
estimates
2.Activity Attributes……. provide the primary data input for use in estimating
durations required for each activity in the activity list like imposed date or constraints
like this activity must not exceed 10 Days .
4.Resource Calendars…..To check the Skills of Resources as The Competent one will
finish the Task speeder than the Low competent one .
5. Project Scope Statement …….It contains Constraints like country law as you
can’t hire anyone from outside the country so you must use the existing resources
and consider their availability and Skills .
6.Risk Register………It includes risks and their analysis and the Response plan so it
must be considered to add this Extra Time , Ex. To lift the Materials by the Labors has
a Risk to get the Materials Scratched or Damaged , The activity Duration Estimate
input to risk register to check the Estimation risks before adding the Contingencies
then Risk register input to Estimate Duration .
8.EEF….If you work in Compound or Mobile Network in Rooftop and the instructions
says that you can work 4 hours/Day Maximum or to work on Network in Specific
Bank , you will work on Friday and Saturday only so all of these will increase the
Duration .
Ex. The Bank informed you that you can work only in
Week end 1 day or 2 days so the Optimistic will be based
On 2 Days , Pessimistic based on 1 Day but Most Likely
Will assume that he will allow 2 days in a week and 1 day in
Another Week
5.Data analysis.
Reserve Analysis……. Duration estimates may include contingency reserves,
sometimes referred to as time reserves or buffers, into the project schedule to
account for schedule uncertainty.
O/P:
1-Duration Estimates…. Activity duration estimates are quantitative assessments of
the likely number of time periods that are required to complete an activity
Duration estimates do not include any lags
For example:
• 2 weeks ± 2 days, which indicates that
the activity will take at least eight days
and not more than twelve
(assuming a five-day workweek);
T i m e M a n a g e m e n t
6.6 Develop Schedule
Inputs :
project Management Plan
Project documents
agreements
Enterprise Environmental Factors
Organizational Process Assets
Tools and Techniques :
Schedule Network Analysis ■ Critical Path Method
PMIS ■ Resource Optimization Techniques
Agile release planning ■ Leads and Lags
Schedule Compression ■ Scheduling Tool
Outputs :
Schedule Baseline ■ Project Schedule
Schedule Data
Change request ■ Project Calendars
Project Management Plan Updates ■ Project document Updates
Develop Schedule
The key benefit of this process is that by entering schedule activities, durations,
resources, resource availabilities, and logical relationships into the scheduling tool, it
generates a schedule model with planned dates for completing project activities.
“”Planned Start Date and Planned Finish Date””
I/P:
Project management plan
1-Schedule Management Plan…. The schedule management plan identifies the
scheduling method and tool used to create the schedule, and how the schedule is to
be calculated (Schedule Compression Method , CPM or CCM).
2.Scope baseline
Project documents
1.Activity List…. identifies the activities that will be included in the schedule
2.Activity Attributes….It contains all needed data for each activity + it contains if
there is a specific date I must start with .
8-Risk Register…..If the Needed skill will not be found in the Existing Country or if
the Top resource may be resign so my response will affect the Schedule or the Crane
lifetime may be expired soon so it will delay me as to buy another one , it will take
time , if you are new Project Manager and received the Project After Duration
Estimates so you must check the Risks and Calendars again through Develop
Schedule .
T&T:
1-Schedule Network Analysis….Analytical Technique which used to decide
according to the Schedule and Constraints to use CPM or CCM , Resource Leveling or
Smoothing (If there is Limited Resource : CCM , There is available Budget : Crashing
,…..)
2-Critical Path Method…. The critical path method, which is a method used to
estimate the minimum project duration and determine the amount of scheduling
flexibility on the logical network paths , calculates the early start, early finish, late
start, and late finish dates for all activities without regard for any resource
limitations (Ex. If I need Critical Resource in my Project but he will not be available in
the needed time but after that by 2 days so this method will not consider this and will
not search for free resources from non critical Activities , it will count the Float only)
by performing a forward and backward pass analysis through the schedule network .
CP: Longest path through a project, which determines the shortest possible project
duration and The critical path method is used to calculate the amount of scheduling
flexibility on the logical network paths
Notes
• A CPM critical path is normally characterized by zero total float on the
critical path.
• Any activity on the critical path is called a critical path activity and has Zero Float .
• Free float…..the amount of time that a schedule activity can be delayed without
delaying the early start date of any successor or violating a schedule constraint
• Total Float…. schedule activity can be delayed or extended from its early start date
without delaying the project finish date or violating a schedule constraint .
• The Float can be Positive or Negative as per the Schedule Constraint.
Lecture 02 Project Scheduling.ppt •
Examples
Example 1
D
Activity Dependency
(Days)
A 8 Start
8 3 9
B 5 Start
A D G
C 2 Start
D 3 A
E 6 A, B
5 6 7
F 4 C
Start B E H End
G 9 D
H 7 D, E
Consider all relationships are FS=0
Form C F
ES D EF
Activity Name
LS TF LF
Answer1
D
Activity Dependency
(Days)
A 8 Start
0 8 8 8 3 11 11 9 20
B 5 Start
A D G
C 2 Start 0 0 8 9 1 12 12 1 21
D 3 A
E 6 A, B
0 21
0 5 5 8 6 14 14 7 21
F 4 C
Start B E H End
G 9 D
3 3 8 8 0 14 14 0 21
H 7 D, E 0 21
Form C F
15 15 17 17 15 21
ES D EF
Notes :
Activity Name Critical Path is : A – E – H •
LS TF LF FFB = 3 •
Example 2
Start 0
1 Start 2
2 Start 3
3 1 7
4 1,2 9
5 2 3
6 3 2
7 4 8
End 5,6,7 0
7 2
2 9 9 11
2
3 6
11 18 18 20
0 2
1
1 3 9 8
3 12 12 20
start 3
4 7 Finish
3 12 12 20
0 3
2 3
0 3
3 6
5
17 20
D 3 A
E 6 A, B
5 6 7
F 4 C
Start B E H End
G 9 D
H 7 D, E
Consider all relationships are FS=0
Form C F
ES D EF
Activity Name
LS TF LF
Lecture 06 : Project Time Management (23/31)
6. Develop Schedule (Planning)
D 3 A
E 6 A, B 0 21
0 5 5 8 6 14 14 7 21
F 4 C
Start B E H End
G 9 D 3 3 8 8 0 14 14 0 21
0 21
H 7 D, E
Consider all relationships are FS=0
Form C F
15 15 17 17 15 21
ES D EF
Notes :
Activity Name Critical Path is : A – E – H •
LS TF LF FFB = 3 •
PMP Lectures
Project Time Management
6. Develop Schedule (Planning)
A 8 Start : FS=0
0 8 8 8 3 11 11 9 20
B 5 Start : FS=0 A D G
0 0 8 8 0 11 11 0 20
C 2 Start : FS=0
D 3 A : FS=0
20
A : FS=0 0 5 5 8 6 14 11 7 18
E 6
B : FS=0
Start B E H End
F 4 C : FS=0 SS=1
7 7 12 12 4 18 13 2 20
G 9 D : FS=0
D : FS=0
H 7
E : SS=1 0 2 2 2 4 6
C F
14 14 16 16 14 20
Critical Path Method (Example 2 Solution)
D
Activity Dependency
(Days)
A 8 Start : FS=0
0 8 8 8 3 11 11 9 20
B 5 Start : FS=0 A D G
0 0 8 8 0 11 11 0 20
C 2 Start : FS=0
D 3 A : FS=0
A : FS=0 0 5 5 8 6 14 11 7 18
E 6
B : FS=0
Start B E H End
F 4 C : FS=0 SS=1
7 7 12 12 4 18 13 2 20
G 9 D : FS=0
D : FS=0
H 7
E : SS=1 0 2 2 2 4 6
C F
14 14 16 16 14 20
Notes :
Critical Path is : A – D – G •
FFB = 3 •
2-Critical Chain Method…. method that allows the project team to place buffers on
any project schedule path to account for limited resources and project uncertainties.
The Activities which has Float is not on CP , for sure have free resources so I can use
them to work in critical path to avoid the violation of Schedule Duration so it takes
uncertainty in Consideration .
Ex. What if the Labors make a Strike as a result of Salaries Delay or What if the
Cement Delivery from the Supplier Delayed .
• Simulation…… The most common simulation technique is Monte Carlo analysis ,
Put the best case and worst case and other cases and check their Impact on the
Schedule .It accounts for Uncertainty .
4-Project Calendars……. identifies working days and shifts that are available for
scheduled activities. (like the work which need to be done in specific days and by who
? With excluding the Weekends)
T i m e M a n a g e m e n t
6.7 Control Schedule
Inputs :
Project Management Plan
Work Performance Data
Project documents ■ Organizational Process Assets
Tools and Techniques :
CPM ■ Data analysis
Resource Optimization Techniques ■ PMIS
Leads and Lags ■ Schedule Compression
Outputs :
Work Performance Information
Schedule Forecasts
Change Requests
Project Management Plan Updates
Project Document Updates
Control Schedule
The key benefit of this process is that it provides the means to recognize deviation
from the plan and take corrective and preventive actions and thus minimize risk.
I/P:
Project Management Plan…..Schedule MGMT Plan (How to Control) and Schedule
Baseline(To compare with it the Actual Schedule to get the Variance).
.
• Schedule baseline
• Scope baseline
• Performance measurement baseline
Project documents
1.Project Schedule…. The Actual Schedule to be
compared with Baseline
2.Resource calendars
3.Lesson learned register
4-Project Calendars….To check if the Work done as per the Calendar or not .
5-Schedule Data….To check that we are still use the same planned data.
Work Performance Data…. actual duration, remaining duration, and physical percent
complete , which activities have started and which activities have finished .
T&T:
data analysis….
Trend Analysis….examines project performance over time to determine whether
performance is improving or deteriorating
Performance review
• Critical path method….Check the Critical path as any variance on it will delay the
Project .
• Critical chain method….. Check the Remaining Buffer and the Needed Buffer as the
Variance means that there is a Problem and corrective Action needed .
Earned value management….SV , SPI will be explained in Cost MGMT .
What if scenario analysis….. Review the Various scenarios to get the Schedule
aligned with the Plan .
Leads and Lags and Compression …….to try to compress the Schedule as to start
an activity before finishing of its precedence
O/P:
1-Work Performance Information…..SV , SPI .
2-Schedule Forecasts…… Where we are now and what we will do in Future to get
the schedule aligned with baseline.
3-Change Requests…. Schedule Corrective action or Added Scope so need to adjust
the Baselines like I will add resources to finish on time or make fast track and so on.
1. Schedule Baseline
2. Dependency Determination
3. Activity List
4. Schedule Compression
You are taking over a project that is currently in the planning stage. •
The previous project manager worked with the team to finalize the
process of defining activities, and you joined the team at the end of
this process. The next process requires the determination and
documentation of the relationships among project activities. Of the
following, which is a tool and technique used in this process?
1. Schedule Baseline
2. Dependency Determination
3. Activity List
4. Schedule Compression
The studio you are working for has assigned you as the project
manager for a movie project where the producer left midway due to
health issues. As a project manager, you are responsible for meeting
the project schedule deadlines. If there is a delay in the project
schedule, you should: