Project Title: Yang Chow Interior Renovation

Owner:
Adress: FPIP, Batangas

DESCRIPTION QTY UNIT LABOR COST TOTAL


Dismantling/ Demolition
Tubular partition dismantling 1 lot 1,500.00 1,500.00
Window counter demolition 1 lot 1,500.00 1,500.00
Painting works
Walls 159 sqm 250.00 39,750.00
Ceiling 74.36 sqm 350.00 26,026.00
Electrical Works (Lighting Instl. & Wire Tapping etc.) 1 bulk 40,000.00 40,000.00
Fabrication and Installation works
Hanging shelves single layer 15.42 lm 2,500.00 38,550.00
Wall mounted counter table 2 layers 3.6 lm 3,800.00 13,680.00
Wall Framing & Glass Framing 4 lm 4,500.00 18,000.00
GRAND TOTAL 179,006.00

Conforme: