Provisional Acceptance Certificate

The Acceptance Tests of Optical Fiber network, deployed for CMPak sites 92143060 for the b/m
sections under PO: PPC-119897 has successfully been completed and ready to achieve acceptance
certificate.

Field Effective
Contractual Actual Length
City Name Section Name Acceptance Acceptance
Length (M) (M)
Date Date
Bunir 92143060 27800 28420 3-July-20 7-July-20

The physical inspection of the Route along with testing of fibers has been carried out.

The Acceptance Certificate is thus issued for the necessary record of the event.

Effective acceptance dates are mentioned above against sections, however signing of this certificate
shall not absolve AMANULLAH KHAN & CO (PRIVATE) LIMITED from its contractual obligations and
responsibilities and subsequent problems during the operation of cable.

CMPak Representative AKL Representative

Signature: Signature:

Name: Name: Asif Manan


Date: Date: 7-Aug-2020