PROCESS REVIEW MANPOWER HISTOGRAM

Project : PROCESS ENGINEERING REVIEW WORK PACKAGE OF EXISTING CGS 1, 3, 4 and 5


Client : CALTEX PACIFIC INDONESIA

250

200
MAN HOUR

150

100

50

PERIOD (DAY)

D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15 D16 D17 D18 D19 D20 D21 D22
MANPOWER 15
Manhour 7,000 FAC 1 1.05 1.1 1.15 1.2 1.25 1.3 1.35 1.4 1.45 1.5 1.55 1.6 1.65 1.7 1.75 1.8 1.85 1.9 1.95 2 2.05
MAN DAY FAC*WMHR 6 6 7 7 7 7 8 8 8 9 9 9 10 10 10 10 11 11 11 12 12 12
MANPOWER MAN HOUR 90 94 99 103 108 112 117 121 126 130 135 139 144 148 153 157 162 166 171 175 179 184
TOTAL MANHOUR 90 184 283 386 494 606 722 844 969 1099 1234 1373 1517 1665 1817 1974 2136 2302 2472 2647 2827 3011
450
D23 D24 D27 D28 D29 D30 D31 D32 D33 D34 D35 D36 D37 D38 D39 D40 D41 D42 D43 D44 D45

2.1 2.15 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2.2 2 1.8 1.6 1.4 1.2 1 0.8 78
13 13 13 13 13 13 13 13 13 13 13 13 13 13 12 11 10 8 7 6 5 7000
188 193 197 197 197 197 197 197 197 197 197 197 197 197 179 162 144 126 108 90 72 7000
3199 3392 3949 4146 4344 4541 4738 4936 5133 5331 5528 5726 5923 6121 6300 6462 6605 6731 6838 6928 7000