Dam safety regulations are also required to address enforcement of rules and
procedures, legal restrictions, roles and responsibilities of agencies and authorities,
contractual obligations, licensing system for designing, constructing and operating of
dams, etc.
3.1 Instrumentation
The use of instrumentation to monitor the performance of dams is widely accepted
as a prudent component of a successful dam safety program to manage and
minimize the risks to the public posed by dams. Instrumentation observations are
used to supplement and complement visual inspections to verify the integrity of the
dam and appurtenant features, assuring protection of life and property.
Instrumentation provides data for monitoring the safe performance during the various
phases of a dam’s life including design; construction; first filling of the reservoir;
evaluation of long-term, in-service performance (normal operation); and to manage
or predict unsatisfactory performance. Installation of instrumentation typically occurs
1) during construction to monitor short and long term behavior and verify design
assumptions; and 2) during the life of the dam to address new or changing
conditions such as seepage.
The function, purpose, and type of instruments may vary widely, depending on the
specific application, from a simple v-notch weir to a complex network of automated
vibrating wire piezometers. Data acquisition methods can also vary widely from
manual readings to automated data acquisition with periodic data recording
capabilities. If in-house expertise is not available, engineering consultants,
instrument manufacturers, or suppliers can be consulted to help identify an
1
instrumentation program appropriate to the project. Dam owners with multiple dams
should note that an instrumentation monitoring program established at one dam may
not be appropriate at another dam regardless of the extent of similarities. Therefore,
it is imperative that each project be evaluated independently to assess the objectives
of the instrumentation program. The evaluation should be part of a structured
process that identifies plausible failure modes unique to a dam and develops
appropriate responses, including instrumentation requirements.
Dam owners should carefully evaluate the need for instrumentation, periodically
review the need, and modify the program accordingly when specific issues of
performance arise. Among several considerations in developing an instrumentation
program, the following items will be considered:
Responsibility
Most successful organizations, in any endeavor, clearly define the roles of their
personnel; certainly this is an important procedure in the management of dam safety
instrumentation programs. Personnel involved in an instrumentation monitoring
program would preferably include a technical supervisor, engineers, and technicians.
However, regardless of the titles used, and depending on the size and how the group
or entity is organized, the most important concept is that responsibilities for
acquisition of data, maintenance of instrumentation, interpretation and reporting of
data should be clearly defined (this may be filled by one person or a full crew of
dedicated personnel). Essential to this is to identify those responsible for accurate,
clear and prompt communication to the dam owner of any conditions identified by the
instrumentation program that may be adverse to the safety of the dam.
2
Monitoring Planning
Planning of instrumentation, whether for an existing dam, or during the design phase
for a new dam, includes several essential considerations. Considerations include
selecting the parameters for monitoring; defining the purpose of the instrument;
predicting the life cycle of the instrument and its replacement challenges; predicting
the influences that drive fluctuations; predicting the range of measurements
expected; and establishing thresholds for safe performance. After logically evaluating
these considerations, an appropriate instrumentation system then may be selected.
The Potential Failure Mode Analysis procedure is a valuable tool for planning and
selecting the parameters for monitoring.
Installation of Instruments
Consideration of methods to collect the data must be evaluated. Data collection may
be via either an automated data collection system or manually (using a readout
device or conventional pen and note paper to record readings). Depending upon the
type of system designed and installed, procedures should be developed to include
how instruments will be read (frequency of readings, time of day, conversions to
other units, etc.) and how data reports can be generated when needed. Decisions
regarding data storage (physical and electronic) will vary from project to project. If a
central storage system is used, procedures to access the reports or manipulate them
should be documented.
Evaluation of data collected is vital for achieving the goals of effectively monitoring
the performance of the dam structures. It is of the utmost importance that data be
regularly and promptly evaluated as it is collected; standard turn-around times from
collection to evaluation should be established, as well as procedures to address how
3
abnormal readings are handled. It is recommended that an annual monitoring report
be prepared with an evaluation of the instrumentation data for submittal to the dam
owner. The report should include a comparison of recent behavior to historical trends
and conclusions as to the performance of the dam with respect to the parameters
measured.
Maintenance
Once the program is developed and implemented, the dam owner must consider
long-term maintenance of the system. This includes documentation of the
instruments and data logging equipment and how they are to be maintained. Such
items as a maintenance schedule, maintenance logs, processes for each instrument
and system component type, and other maintenance needs should be addressed on
a site-specific basis. Manufacturers’ Operation and Maintenance (O&M) manuals
should be available for the life of the instrument. If possible, training on the general
maintenance and trouble-shooting of the instruments should be provided at the time
of installation.
Dam owners should evaluate their instrumentation requirements using the Potential
Failure Mode Analysis (PFMA) process. The PFMA process is used to identify
potential failure modes at a specific project or project feature at the time of
evaluation. These modes can help evaluate and select project features where
instrumentation may or may not be needed for inclusion in the monitoring program.
The PFMA evaluation must be thoughtful and thorough, and include input from the
dam owner, operating personnel, independent engineering consultants, regulatory
agencies, and designers familiar with the dam and foundation. Among the decisions
to be made are deciding what generic type of instrument is required and then what
specific type. For example, to monitor seepage, the decision may be that a weir will
be required. Then a decision must be made on the specific type of weir (e.g., V-
notch, rectangular, Parshall flume) and whether to use a visually read staff gauge or
4
an electric water level transducer. There are then various level transducers available:
float-type devices with a vibrating wire or magnetostrictive transducer or diaphragm
pressure transducer, each with their own advantage and disadvantage. The type of
instrument selected will be influenced by the time of installation - during original dam
construction, before first reservoir filling, or with a full reservoir (possibly after many
years of operation).
Each type of instrument involves a different installation method, some being more
disruptive than others for the material in which they are installed, especially for earth
core materials of embankment dams. The installation method needs to be
considered as an integral part of the instrument selection process. Additionally, for
most instrument choices, another consideration is whether to use manual or
automated reading, and in the case of automated reading, with or without telemetry
to transfer the readings to a site office or a remote location.
Inclinometer: Inclinometers are used to measure angles from vertical. They can be
used both in the concrete mass or extended into the foundation. Extending the
inclinometer into the foundation can provide information on a potential sliding plane
being investigated.
Joint meters: One or two joint meters are required in every other monolith joint at
the mid height elevation of alternate grout lifts.
5
Figure 3.1Recommended location of embedded instruments in arch dams (elevation
looking upstream)
6
Triangulation and trilateration targets: Targets should be placed at the crest and
at one or more points on the downstream face. The targets should correspond to the
location of the plumblines.
Stress/strain Clusters: Clusters of strain meters, "no-stress" strain meters, and stress
meters should be positioned along four or five arch elevations that correspond to
arch elevations used in the design and analysis.
7
V-notch weir to measure seepage at an embankment dam
For the case of concrete dam Seepage, through the joints and through the drains
can be measured at two weirs, each located to collect seepage through the drains
along each abutment. Measurements of individual drains should also be made on a
regular basis. Additional seepage monitoring points can be added after the initial
reservoir filling, if the need arises.
8
Standpipe piezometer at the downstream toe of an embankment dam.
9
Figure 3.6 Relative movement device for three directions on a concrete joint
Total pressure cell: The total pressure cell measures the combined pressure of
effective stress and pore-water pressure. Typical applications include:
Figure 3.7 Total Pressure Cell and Jackout Total Pressure Cell
Total pressure is the intergranular pressure in the soil (effective stress) combined
with the pressure of water in the voids between soil grains (porewater pressure).
The pressure cell is formed from two circular plates of stainless steel whose edges
are welded together to form a sealed cavity. The cavity is filled with a non-
compressible fluid. The cell is installed with its sensitive surface in direct contact with
10
the soil. The total pressure applied to that surface is transmitted to the fluid inside the
cell and measured with a pneumatic or vibrating wire pressure transducer.
Figure 3.8 Total pressure cells in an embankment dam. Detail shows multiirectional
orientation of cells in an array.
11
Figure 3.10 Recommended locations of embedded instruments in concrete gravity
dams
12
Table 3.1 Recommended Readout schedule
1 Initial reading for all embedded instruments should be made within 3 hours after
embedment.
2 After initial readings are obtained, readings are continued every 12 hours for 15
days, daily for the next 12 days, twice weekly for 4 weeks, and weekly thereafter.
13
4 After initial readings are obtained, readings are continued every 6 hours for 3 days,
every 12 hours for 12 days, daily for the next 12 days, twice weekly for 4 weeks, and
weekly thereafter.
14