You are on page 1of 4

EJEMPLOS DE POZOS TIPO HORIZONTAL

11) Given the following profile variables, choose the correct answer below after calculating the
maximum hold angle for a horizontal well:

· Target Displacement = 2100 ft

· Target Direction = 35° AZM

· Target TVD = 3300 ft

· 1st Build Up Rate = 6° per 100 ft

· 2nd Build Up Rate = 8° per 100 ft

· Kickoff Point = 1000 ft

Select the correct answer

a) 26.72°

b) 70.91°

c) 2.66°34’

d) 42.88°

12) Given the following profile variables, choose the correct answer below after calculating the
first end of build’s displacement for a horizontal well:

· Target Displacement = 2100 ft

· Target TVD = 3300 ft

· 1st Build Up Rate = 6° per 100 ft

· Kickoff Point = 1000 ft

· MAX Inclination Angle (q ) = 42.88°


Select the correct answer.

a) 289.11 ft

b) 300 ft

c) 763.8 ft

d) 255.21 ft

13) Given the following profile variables, choose the correct answer below after calculating the
start of second build measured depth of a horizontal well:

· Target Displacement = 2100 ft

· Target TVD = 3300 ft

· 1st Build Up Rate = 6° per 100 ft

· Tangent Section = 1939.74 ft

· Kickoff Point = 1000 ft

· Maximum Hold Angle = 44.88°

Select the correct answer.

a) 3869.11 ft

b) 4000 ft

c) 3654.46 ft

d) 2763.8 ft

14) Given the following profile variables, choose the correct answer below after calculating the
target’s total measured depth of a horizontal well:
Target Displacement = 2100 ft

Target TVD = 3300 ft

1st Build Up Rate = 6° per 100 ft

2nd Build Up Rate = 8° per 100 ft

Tangent Section = 1939.74 ft

Kickoff Point = 1000 ft

Maximum Hold Angle = 44.88°

Select the correct answer.

a) 4000 ft

b) 4243.43 ft

c) 3869.11 ft

d) 2763.8 ft

EJERCICIO POZO #1 TIPO HORIZONTAL


Target location = 2,000´@ 150° AZIMUTH
KOP (V1) = 2500´
Target TVD (V4) = 4,000´
BUR1 = 5,20°
BUR2 = 8,60°
EJERCICIO POZO #2 TIPO HORIZONTAL
Target location = 2,500´@ 125° AZIMUTH
KOP (V1) = 2700´
Target TVD (V4) = 5,000´
BUR1 = 5,25°
BUR2 = 8,70°