Professional Documents
Culture Documents
How To Prepare Planning Deliverables For LNG Project?: Sapto Hari Wibowo
How To Prepare Planning Deliverables For LNG Project?: Sapto Hari Wibowo
PLANNING DELIVERABLES
FOR LNG PROJECT?
The technical case and the venture are two scenarios run to understand
the impact of different sensitivities on the premises.
Further information can be found in the Schedule Risk report
Project Execution (EPC Scopes)
• FID Started with decision contract award to EPC Contractor
• Normally within 60 days to 90 days EPC Contractor must submit planning package for
review and approval to Client
• After planning package review and approved by Client’s planner team leader, Contractor
starting using this document for monitoring and contractual document as baseline
• Client’s planner must prepare high level schedule for management reporting and also in
schedule risk analysis for post mitigate update
• During this period project monitor closely by both parties (Client and Contractors)
• After Fabrication reaching 60% and Engineering almost complete (above 90% progress),
Contractor must able to develop and submit detail schedule for precomm and
Commissioning by systems and sub systems
• Focus on putting priority for systems and sub systems and also potentially for change
sequence based on availability of equipment to arrive and installed at site
• All MCC (Mechanical Completion Certificate) must inplace before precomm/
commissioning started (monitor closely by MCC coordinator and planners), normally
using skylines chart for monitoring
Hand Over to Operation
• During Precomm/ Commissioning, must witnessed and approved by
Client Project Team and Client Operation Team
• Hand Over to operation by partially system and also Final Handover
with all systems running in good operation condition as requirement
Q&A