Professional Documents
Culture Documents
Answer:
(a) IRR 22.28% 27.14% IRR of Chinese Machine and Indian Machine are 22.28% and 27.14
(b) Crossover Rate 13.92% Cross over rate is 13.92%
(c) NPVs of the two options using discount rate are shown in below table
Discount Rates 10% 12% 14% 16% 18%
Chinese Machine $241,496.808 $190,240.193 $144,485.910 $103,531.131 $66,775.103
Indian Machine $211,459.965 $176,476.881 $144,997.349 $116,590.733 $90,887.468
(d)
NPV Profi le
$300,000.000
$250,000.000
$200,000.000
$150,000.000
$100,000.000
$50,000.000
$0.000
10% 12% 14% 16% 18% 20% 22% 24% 26% 28%
($50,000.000)
$250,000.000
$200,000.000
$150,000.000
$100,000.000
$50,000.000
$0.000
10% 12% 14% 16% 18% 20% 22% 24% 26% 28%
($50,000.000)
($100,000.000)
(e ) If cost of capital is 12%, the Chinese Machine must be selected because its has a higher NPV compared to the Indian
(f) NPV is better tan IRR because IRR cant be discounting a project’s future cash flow at predefined rates known NPV
that intermediate cash flow is reinvested at cutoff rate while under the IRR approach.
Low-risk projects are unlikely to have a high internal rate of return where businesses to pursue projects with high
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
d
The Project NPV is Positive. So the project can be recommended and sonnitron can expect profit
the rate 18% where it will be positive for Investor.
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
Question:
(b) As the NPV $24,236.929 is positve, The Project Can be seletcted as Cash flow positive and it will asses the R
(c)
If there is no Adjusment taken for Risk, Based one one Discount rate, there Project will be high Risk. Investor will no
the returns not correpoding to the risk. So Investment on these risky projects based on one discount rate will ulitim
destroy wealth for the share holders.
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
Given That,
Bond Investment, WD 0.4
Share Holder Investment, WE 0.6
ROE 30%
Share Price, P0 280
Payout Ratio 65%
EPS 60
Expected Devident, D1 39
KD 16%
Tax Rate 35%
(a) Ke `=(D1/P0)+g
24.429%
(b) WACC of Zosano `=Wd*Kd*(1-t)+We*Ke
18.817%
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
Question
WACC 18%
Project Risk Class IRR Risk Group
M Lowest 12.40% Lowest
N Above Average 20.80% Above Average
P Highest 25.90% Highest
Q Below Average 14.97% Below Average
R Average 18.90% Average
S Lowest 11.80% Lowest
T Above average 21.40% Above Average
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
Project X Project Y
NPV(tk) 5,205.63 6,278.84
Year, n 4 6
Discount Rate, i 22% 22%
PVIFAi,n 2.49 3.17
(a) EAA 2,087.56 1,982.63
(b)
Project X must be selected as it creates more value per year if this project is renewed and is the batter ch
then the project Y.
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
Total Capital
Current Equity 80,000,000.00
Retained Earning 10,000,000.00
Current Long term Debt 30,000,000.00
Unknown New Capital 40,000,000.00
TIE 6 6.00
EBIT 30,000,000.00
Interest 11% 3,300,000.00
Allowable Interest 5,000,000.00
Interest Slack 1,700,000.00
At Indifference Point
EBIT Option 1
Interest 304,280.000
EBT 108,000.000
Taxes 196,280.000
Earnings after taxes 52,995.600
Number of shares 143,284.400
EPS 87,625.000
1.635
Indifference Point
EBIT EPS
5.000
4.500
4.000
3.500
3.000
2.500
EPS
EBIT
Option 1 Option 2
0.500
-
200,000.000 250,000.000 300,000.000 350,000.000 500,000.000 550,000.000 600,0
EBIT
Option 1 Option 2
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
Issuing Debt
Option 2
450,000.000 600,000.000
143,000.000 143,000.000
307,000.000 457,000.000
82,890.000 123,390.000
224,110.000 333,610.000
72,000.000 72,000.000
3.113 4.633
At Indifference Point
Option 2
304,280.000
143,000.000
161,280.000
43,545.600
117,734.400
72,000.000
1.635
Issuing New Common Shares
Option 1
300,000.000 350,000.000 500,000.000 550,000.000 600,000.000
108,000.000 108,000.000 108,000.000 108,000.000 108,000.000
192,000.000 242,000.000 392,000.000 442,000.000 492,000.000
51,840.000 65,340.000 105,840.000 119,340.000 132,840.000
140,160.000 176,660.000 286,160.000 322,660.000 359,160.000
87,625.000 87,625.000 87,625.000 87,625.000 87,625.000
1.600 2.016 3.266 3.682 4.099
Issuing Debt
Option 2
300,000.000 350,000.000 500,000.000 550,000.000 600,000.000
143,000.000 143,000.000 143,000.000 143,000.000 143,000.000
157,000.000 207,000.000 357,000.000 407,000.000 457,000.000
42,390.000 55,890.000 96,390.000 109,890.000 123,390.000
114,610.000 151,110.000 260,610.000 297,110.000 333,610.000
72,000.000 72,000.000 72,000.000 72,000.000 72,000.000
1.592 2.099 3.620 4.127 4.633
IT
Option 2
00.000 500,000.000 550,000.000 600,000.000
IT
Option 2
Question
(a) As we know , small size project has higher IRR , though the project value is less. So for different size project we shou
We need to Choose Project with Highest NPV, Reject Others. NPV must be positive.
(b)
Capital planning choices should be made based on Common life analysis. NPV and IRR have to analyse fully.
©
When project risk is different certainaity equivalents are used to determine the best Certainty Equivalents are betw
Exchanges Risky Cash Flows for Risk-Free Flows. A risky Cash Flow of Taka 2,00,000 may be exchanged for a risk-fre
Factor of .8
Discount the Risk-free flows at risk-free rate and rate of return must be adjusted to compensate investor for the ris
EMB 660-Corporate Finance
Final Assignment
Aminul Islam, ID: 2016209690
ve to analyse fully.