You are on page 1of 40

Forecourt Installation

UPP Containment Installation


Containment (UPP™ Brand)
• Contents
– Tank Chambers – Shear Valves
• Models & Features • Models & Features
• Installation • Installation
– Covers – Flexible Connectors
• Models & Features • Models & Features
• Installation • Installation
– Dispenser Sumps • Best Practices
• Models & Features – Flexible Connectors
• Installation • Models & Features
– Entry Fittings • Installation
• Models & Features • Best Practices
• Installation – Sump Sensors
2
• Models & Features
Containment (UPP™ Brand)

INSTALLATION:
Tank Chambers

3
Containment (UPP™ Brand)

• Link to UPP® Fusion Tank ChamberSump Riser Installation video


• Link to UPP® Fusion Tank ChamberSump Base Installation video

4
Containment (UPP™ Brand)
– UST bury depth: Refer “File Name: Installation instruction – PCR & PDR Access Cover”. Tank hole
depth (tank manway to grade level distance) to design within 1200mm to 1400mm.

5
• Underground water table
Provision 20% -25% higher than annual average water level (raining season). Ensure OCH
riser is always 20mm higher than the estimated highest water level at design stage.
Example: Average underground water table is -600mm, estimate highest water table
during raining season to be -600mm x (-80%) = - 480mm (20%).

• Fuel Systems installer MUST verify


Tank bury depth with PCC (Notify L2 if tank bury depth is beyond 1400mm immediately).
Hot air welding work is required to raise the OCH riser to the highest point – 50mm below
the PCR manway cover bottom)
Understand underground water level control strategy during project kickoff meeting,
adjust OCH sump riser height accordingly.
6
Installation: Tank Chambers
• All Models:
– Final Backfilling:
• Use only correct back fill
o Well-rounded pea gravel
―3mm to 20mm
o Crushed rock ( Recommend )
―3mm to 16mm
o Clean washed sand ( Not recommend for high
underground water table cases)

7
Pre-Backfilling Requirements

• Geotextile Filter Fabric


– Install filter fabric between the backfill and adjacent unstable
soil, bogs, swampy areas, or landfills to prevent the backfill from
migrating and thus diminishing the support of tank or paving

– If dis-similar backfill materials, such as sand, pea gravel, are


used in same excavation, separate them with filter fabric to
prevent finer sand particles from migrating into voids between
pea gravel

Note: “Erosion Pollution- Fabric Geotextile


Functions” (2017) [ graphics-separation-
filtration ] retrieved from
https://www.erosionpollution.com/fabric-
geotextile.html
8
Pre-Backfilling Requirements

No Geotextile Filter
Fabric

9
Backfill Compaction

• The backfill should be placed in layers, or lifts, that are brought up evenly. Each lift or
layer should be approx. 30cm of crushed rock/stone or 25cm of sand. Each lift
should be thoroughly compacted prior to the placement of the next layer.
• During the backfilling, check for voids underneath the chambers. If the backfill
material appears loose in these areas, then the compaction is not adequate, and the
compaction process shall be continued.

Link to UPP®-Fusion-Tank-ChamberSump-Backfill-Installation Video


10
Backfill Compaction

11
Containment (UPP™ Brand)

INSTALLATION:
Covers

12
Installation: Covers
• Tools and Equipment Needed: PCR90 and PCR106
– Access cover and mounting frame
– Access Cover Skirt (sold separately)
– Single-component polyurethane sealant for bonding
skirt to frame (SoudaFlex 40FC needed)
– Two-part polyurethane sealant (example: CM200PF)
– Packing material or clean sand
– Nitrile gloves, applicator gun, 80/20 grit abrasive
paper, and approved cleaning solvent

13
• Installation: Composite Access Cover: Installation: Covers

⚫ Remove the protective, and place


the cover on a clean, level surface.
⚫ Remove the cover from the frame.
⚫ Abrade and clean the areas that
will be bonded with Acetone.
⚫ Use SoudaFlex® 40FC bonding
agent to attach the frame to the
skirt. Make sure the skirt fully
engages the inner lip of the frame.
⚫ Allow the skirt and frame to bond
fully before continuing. (24 hours)

14
• Installation: Composite Access Cover: Installation: Covers

Abrade, clean, apply


SoudaFlex40 sealant
24 hours cure time
15
Installation: Covers
• Installation: Composite Access Cover:
⚫ Place the skirt on top of the backfill, and
Prepare the area take account of how deep the frame is
buried and the desired finished surface
level.
⚫ Allow a minimum of 56 mm (2 ¼ inches)
clearance between the bottom face of
the access cover and the top face of the
tank chamber lid.
⚫ Allow a minimum of 56 mm clearance
between the bottom of the skirt and the
wider extending section of the tank
chamber to allow for tank movement.
⚫ Backfill around the area of the skirt to
secure its position.
17
• Installation: Composite Access Cover: Installation: Covers
Apply a two-part Polyurethane sealant

18
Installation: Covers
• CM200PF preparation

19
Installation: Covers
• CM200PF preparation sequence

The sealant must be kept warm


until just prior to installation,
keep it in a heated area at
approximately 20 Deg.C. Do not
install the sealant in the rain or if
rain is expected in the next 24
hours

It is essential that parts A and B are


properly mixed. The two part cold poured
sealant consist of one large tin pack A
and one small tin pack B. The combined
contents of pack A and B is 1 gallon so
repeat twice to get the two gallons
20
Installation: Covers
• CM200PF preparation sequence

Use the wooden stir stick Stir complete the contents Mix contents together for a full 5 minutes
provided with the sealant, stir of Pack B into the tin using a slow speed electric drill (400-500
content of pack B containing pack A to give a rpm) with a low viscosity mixing paddle
combined content of 1 until a completely homogeneous mix is
gallon obtained, mixing is made easier if pack B
is added in two stages

21
Installation: Covers
• CM200PF preparation sequence

22
• Installation: Composite Access Cover: Installation: Covers

Crown the cover : To improve the dispersion of water away from the cover.
◆ Crown the cover slightly above the finished surface level. Typically, a crown of 5–10
mm over a distance of 300 mm around the perimeter of the cover. 23
Installation: Covers

Insert actual crown picture from site

24
Containment (UPP™ Brand)

INSTALLATION:
Dispenser Sumps

25
Installation: Dispenser Sumps
• Installation: Dispenser Sump

Adjust sump height if required Locate sump securely Mark the pipe entry positions and install
entry seals
(If using flex connectors, skip this step)

Assemble Pipe
Insert channel nuts into unistrut and Risers
assemble one end of the stabilizer bar. 26
Installation: Dispenser Sumps
• Installation: Shear Valve Riser (PE Pipe):

C
B OR
A D

Assemble transition Measure length of Assemble welding coupler, PE


fitting into shear valve shear valve assembly. riser and mounting plate.

PE Riser Cutting Table A = Length of shear valve assembly.


B = Depth of entry seal from grade.
Tee C=B-(A+150mm)
C = Length required for tee arrangement.
Elbow D=B-(A+40mm) D = Length required for elbow arrangement.

Hang shear valve assembly at correct height. 27


Connect and weld to mating pipework.
Installation: Tank Chambers
• All Models:
– Final Assembly
• Ensure shear valve is correct positon
• Tighten all stabilizer bar bolts
– Final Backfilling:
• Use only correct back fill
o Well-rounded pea gravel
―3mm/0.12” to 20mm/0.79”
o Crushed rock
―3mm/0.12” to 16mm/0.63”
o Clean washed sand

29
Containment (UPP™ Brand)

INSTALLATION:
Entry Fittings

30
Installation: Entry Fittings
• Electrofusion Fittings (1 of 2):

1. CUT 2. MARK

3. SCRAPE 5. ASSEMBLE 31
4. CLEAN
Installation: Entry Fittings
• Electrofusion Fittings (2 of 2):

6. WELD 7. CHECK & MARK

UPP® Electrofusion Entry SealBoot Installation Video

32
8. COOL – 20 Minutes
Containment (UPP™ Brand)

MODELS & FEATURES:


Shear Valves

33
Models & Features: Shear Valves
• Shear Valve Features
– Fusible link closes poppet during fire event
– Single and double poppet options
• Main poppet seals in valve body
– Prevents accidents when replacing adapters
– E-coated body for corrosion protection, Fully AGB Compatible
– Standard 1-1/2" NPT or BSPT openings
• Allows minimal flow restriction
• Pre-drilled test plug included for line pressure testing
– Boss or U-bolt mountable
– 100% Factory tested
– Combo body
– ATEX and UL 847 A&B Approved
34
Containment (UPP™ Brand)

INSTALLATION:
Shear Valves

35
Installation: Shear Valves
• Installation (1 of 4):

Top Adapter

Closed Normally Open


CAUTION: Adapter 662 double poppet shear valves
with normally OPEN poppeted adaptors ONLY. Verify orientation of shear valves and mount to
662-501 or 602-511 plate using U-bolt or flat head screws.
Before installation, check to make sure the poppet in
the upper adapter is in its open position.
Do Not install the valve if poppet in top adapter is in its
closed position. 36
Refer to instructions F-1675-REV 2 for more detail.
Installation: Shear Valves
• Installation (2 of 4):

Thread the valve hand tight onto pipe.


Use wrench to finish tightening valve on
lower section of shear valve.

37
Refer to instructions F-1675-REV 2 for more detail.
Installation: Shear Valves
• Installation (3 of 4):

Leave 3 5/16" (84mm) clearance from Release valve linkage to closed


center line of inlet pipe during installation position and tighten adapters

38
Refer to instructions F-1675-REV 2 for more detail.
Installation: Shear Valves
• Installation (4 of 4):

Note: The riser pipe going to the inlet end of the valve must be cut so that
the shear section of the valve is level with the top of the island +/- ½".

39
Installation: Shear Valves
• Replacing Top Adapter
– Close valve manually and drain product from dispenser
– Remove three 5/16" (8mm) socket head cap screws,
square seal ring, and old/damaged top adapter
– Assemble new seal ring onto new adapter
– Thread new adapter and hand tighten three 5/16” (8mm)
screws
– Remove plastic zip tie from back of fusible link and metal
tool from between adapter top and base
– Open valve and engage latch pin
– Finish tightening socket head cap screws
– Fully test valve before returning it to service
40
Installation: Shear Valves
• Service and Maintenance:
– Operate valve manually several times at least once each year to ensure proper function

Opening the Valve Pressure Test Plug


Closing the Valve Manually Each valve has a ⅜" NPT pipe plug for
Rotate the fulcrum arm
Pull the outer end of the fusible link slightly pressure testing the system. Remember to
counterclockwise and latch the pin
outward to disengage the pin from the fulcrum arm. isolated the tank from the system and not
into the fulcrum arm.
subjected to piping system pressure. 41
Forecourt Installation
Containment (UPP™ Brand)

You might also like