You are on page 1of 26

RENCANA PENGGUNAAN BAHAN, ALAT & UPAH KERJA

KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA


PEKERJAAN : PEMB. RUMAH PRODUKSI KRIPIK NENAS DAM SELAI NENAS
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU
TAHUN ANGGARAN : 2021

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)
I BELANJA MODAL
BAHAN BANGUNAN/KONSTRUKSI
1 Pasir Pasangan 16.00 M2 360,000.00 5,760,000.00
2 Batu Gunung 8.50 M3 250,000.00 2,125,000.00
3 Semen 50 Kg 115.00 zak 75,000.00 8,625,000.00
4 Batu Pecah 1 : 2 4.00 m3 450,000.00 1,800,000.00
5 Batu Bata 6,000.00 bh 800.00 4,800,000.00
6 Besi Beton Polos dia. 10" 56.00 Btg 75,000.00 4,200,000.00
7 Besi Beton Polos dia. 6" 32.00 Btg 45,500.00 1,456,000.00
8 Kawat Beton 6.00 Kg 35,000.00 210,000.00
9 Papan Kayu Kls III 0.52 M3 3,000,000.00 1,560,000.00
10 Balok Kayu Kls III 0.20 M3 3,000,000.00 600,000.00
11 Paku Biasa 33.00 Kg 35,000.00 1,155,000.00
12 Tegel Keramik 40x40 cm 200.00 Bh 12,000.00 2,400,000.00
13 Balok Kayu Kls II 6/12 0.69 M3 4,500,000.00 3,105,000.00
14 Balok Kayu Kls II 5/10 0.41 M3 4,500,000.00 1,845,000.00
15 Papan Kayu Kls II 2/20 0.57 M3 4,500,000.00 2,565,000.00
16 Besi Strip 6.00 Kg 35,000.00 210,000.00
17 Atap Spandek 70.00 M2 55,000.00 3,850,000.00
18 Nok Spandek 8.00 Kg 35,000.00 280,000.00
19 Paku Seng 3.00 Kg 35,000.00 105,000.00
20 Kaca bening 5 mm 8.00 M2 95,000.00 760,000.00
21 Cat meni kayu 5.00 Kg 35,000.00 175,000.00
22 Plamur kayu 4.00 Kg 50,000.00 200,000.00
23 cat dasar kayu 4.00 Kg 35,000.00 140,000.00
24 Cat Penutup kayu 8.00 Kg 50,000.00 400,000.00
25 Pengencer 6.00 Ltr 15,000.00 90,000.00
26 Kuas 2.00 bh 15,000.00 30,000.00
27 Amplas 5.00 Lbr 10,000.00 50,000.00
28 Plamur tembok 13.00 Kg 50,000.00 650,000.00
29 Cat Dasar Tembok 13.00 Kg 30,000.00 390,000.00
30 Cat Penutup tembok 43.00 Kg 70,000.00 3,010,000.00
31 Kuas Roll 4.00 Bh 50,000.00 200,000.00
32 Balok Kayu Kls II 4/6 0.69 M3 4,500,000.00 3,105,000.00
33 Triplex 4 mm 18.00 Lbr 75,000.00 1,350,000.00
34 Tanah Timbunan 8.50 M3 200,000.00 1,700,000.00
35 Kunci 2 Putaran 1.00 bh 100,000.00 100,000.00
36 Engsel Pintu 3.00 bh 35,000.00 105,000.00
37 Engsel Jendela 8.00 bh 20,000.00 160,000.00
38 Grendel Pintu 1.00 bh 25,000.00 25,000.00
39 Grendel Jendela 7.00 bh 15,000.00 105,000.00
40 Hak angin 7.00 bh 10,000.00 70,000.00
SUB JUMLAH I 59,466,000.00
II BELANJA BARANG DAN JASA
A PERALATAN KERJA
SUB JUMLAH A
B UPAH KERJA
1 Pekerja 177.00 hok 100,000.00 17,700,000.00
2 Tukang Kayu 54.00 hok 125,000.00 6,750,000.00
3 Tukang Batu 50.00 hok 125,000.00 6,250,000.00
4 Tukang Cat 16.00 hok 125,000.00 2,000,000.00
5 Tukang Besi 15.00 hok 125,000.00 1,875,000.00
6 Kepala Tukang 24.00 hok 150,000.00 3,600,000.00
SUB JUMLAH B 38,175,000.00
C HONOR
1 Perencanaan Teknis 1.00 Paket 2,132,000.00 2,132,000.00
2 Pengawasan Teknis 1.00 Paket 711,000.00 711,000.00
3 Pelaksanaan Teknis 1.00 Kegiatan 711,000.00 711,000.00
SUB JUMLAH C 3,554,000.00
SUB JUMLAH II 41,729,000.00
JUMLAH TOTAL 101,195,000.00
DIBULATKAN 101,195,000.00
Terbilang : Tujuh Puluh Empat Juta Enam Ratus Dua Puluh Ribu Rupiah

DESA PATTALASSANG …………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI


MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
REKAPITULASI RENCANA ANGGARAN BIAYA
PELAKSANAAN PEMBANGUNAN DESA
PEKERJAAN PEMBANGUNAN RUMAH PRODUKSI KRIPIK NENAS DAN SELAI NENAS
DESA PATTALASSANG, KEC. TOMPOBULU TAHUN 2020

HARGA (Rp) JUMLAH


NO URAIAN PEKERJAAN VOL SAT
BAHAN ALAT UPAH HARGA (Rp)
1 Galian Tanah 13.44 M3 - - 1,150,000.00 1,150,000.00
2 Pas. Pondasi 7.56 M3 5,440,000.00 2,000,000.00 7,440,000.00
3 Struktur Beton (Cor Beton) 4.74 M3 5,325,000.00 1,200,000.00 6,525,000.00
4 Struktur Beton (Pembesian) 433.30 Kg 5,866,000.00 3,675,000.00 9,541,000.00
5 Struktur Beton (Bekisting) 13.10 M2 2,510,000.00 1,050,000.00 3,560,000.00
6 Pas. Batu Bata 84.56 M2 7,740,000.00 3,850,000.00 11,590,000.00
7 Plesteran 169.12 M2 2,790,000.00 1,525,000.00 4,315,000.00
8 Lantai Keramik 40x40 cm 30.00 M2 3,390,000.00 3,500,000.00 6,890,000.00
9 Pas. Kuda-Kuda 0.40 M3 2,260,000.00 975,000.00 3,235,000.00
10 Pas. Gording 0.37 M3 1,880,000.00 850,000.00 2,730,000.00
11 Pas. List plank 33.20 M' 1,770,000.00 1,200,000.00 2,970,000.00
12 Pas. Atap Spandek 68.80 M2 4,235,000.00 - 850,000.00 5,085,000.00
13 Kusen Pintu Jendela 0.20 M3 1,160,000.00 850,000.00 2,010,000.00
14 Pintu Panil, Jendela dan Kaca 2.80 M2 1,660,000.00 1,075,000.00 2,735,000.00
15 Pas. Penggantung 565,000.00 725,000.00 1,290,000.00

JUMLAH 46,591,000.00 - 24,475,000.00 71,066,000.00


Real cost (Dana Fisik) 71,066,000.00
Perencanaan Teknis 2,132,000.00
Pengawasan Teknis 711,000.00
Pelaksana Teknis 711,000.00
JUMLAH TOTAL 74,620,000.00
Dibulatkan 74,620,000.00
Terbilang : Tujuh Puluh Empat Juta Enam Ratus Dua Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :

LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Galian Tanah


TAHUN ANGGARAN : 2020 VOLUME : 13.44 M3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
-
-
-
SUB JUMLAH I -
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.75 10.00 hok 100,000.00 1,000,000.00
2 Kepala Tukang 0.03 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,150,000.00
JUMLAH TOTAL 1,150,000.00
DIBULATKAN 1,150,000.00
Terbilang : Satu Juta Seratus Lima Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Pas. Pondasi
TAHUN ANGGARAN : 2020 VOLUME : 7.53 M3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Pasir Pasangan 0.52 4.00 M3 360,000.00 1,440,000.00
2 Batu Gunung 1.10 8.50 M3 250,000.00 2,125,000.00
3 Semen 50 Kg 3.26 25.00 Zak 75,000.00 1,875,000.00
SUB JUMLAH I 5,440,000.00
II ALAT

SUB JUMLAH II -
III UPAH
1 Pekerja 1.50 11.00 hok 100,000.00 1,100,000.00
2 Tukang Batu 0.75 6.00 hok 125,000.00 750,000.00
3 Kepala Tukang 0.08 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 2,000,000.00
JUMLAH TOTAL 7,440,000.00
DIBULATKAN 7,440,000.00
Terbilang : Tujuh Juta Empat Ratus Empat Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS :
KODE ANGGARAN
: Struktur Beton (Cor
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU
SUB PEKERJAAN Beton)
TAHUN ANGGARAN : 2020 VOLUME : 4.74 M3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Pasir Pasangan 0.50 2.50 M3 360,000.00 900,000.00
2 Batu Pecah 1 : 2 0.77 4.00 M3 450,000.00 1,800,000.00
3 Semen 50 Kg 7.42 35.00 Zak 75,000.00 2,625,000.00
SUB JUMLAH I 5,325,000.00
II ALAT

SUB JUMLAH II -
III UPAH
1 Pekerja 1.65 8.00 hok 100,000.00 800,000.00
2 Tukang Batu 0.28 2.00 hok 125,000.00 250,000.00
3 Kepala Tukang 0.03 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,200,000.00
JUMLAH TOTAL 6,525,000.00
DIBULATKAN 6,525,000.00
Terbilang : Enam Juta Lima Ratus Dua Puluh Lima Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS :
KODE ANGGARAN
: Struktur Beton
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU
SUB PEKERJAAN (Pembesian)
TAHUN ANGGARAN : 2020 VOLUME : 385 Kg

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Besi Beton Polos 1.05 404.00 Kg 14,000.00 5,656,000.00
2 Kawat Beton 0.02 6.00 Kg 35,000.00 210,000.00

SUB JUMLAH I 5,866,000.00


II ALAT

SUB JUMLAH II -
III UPAH
1 Pekerja 0.04 15.00 hok 100,000.00 1,500,000.00
2 Tukang Besi 0.04 15.00 hok 125,000.00 1,875,000.00
3 Kepala Tukang 0.004 2.00 hok 150,000.00 300,000.00
SUB JUMLAH III 3,675,000.00
JUMLAH TOTAL 9,541,000.00
DIBULATKAN 9,541,000.00
Terbilang : Sembilan Juta Lima Ratus Empat Puluh Satu Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS :
KODE ANGGARAN
: Struktur Beton
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU
SUB PEKERJAAN (Bekisting)
TAHUN ANGGARAN : 2020 VOLUME : 13.10 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Papan Kayu Kls III 0.04 0.52 M3 3,000,000.00 1,560,000.00
2 Balok Kayu Kls III 0.02 0.20 M3 3,000,000.00 600,000.00
3 Paku biasa 0.40 10.00 Kg 35,000.00 350,000.00
SUB JUMLAH I 2,510,000.00
II ALAT

SUB JUMLAH II -
III UPAH
1 Pekerja 0.30 4.00 hok 100,000.00 400,000.00
2 Tukang Kayu 0.33 4.00 hok 125,000.00 500,000.00
3 Kepala Tukang 0.03 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,050,000.00
JUMLAH TOTAL 3,560,000.00
DIBULATKAN 3,560,000.00
Terbilang : Tiga Juta Lima Ratus Enam Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Pas. Batu Bata
TAHUN ANGGARAN : 2020 VOLUME : 84.56 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Batu Bata 70.000 6,000.00 Bh 800.00 4,800,000.00
2 Pasir Pasangan 0.045 4.00 M3 360,000.00 1,440,000.00
3 Semen 50 Kg 0.230 20.00 Zak 75,000.00 1,500,000.00
SUB JUMLAH I 7,740,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.32 27.00 hok 100,000.00 2,700,000.00
2 Tukang Batu 0.10 8.00 hok 125,000.00 1,000,000.00
3 Kepala Tukang 0.01 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 3,850,000.00
JUMLAH TOTAL 11,590,000.00
DIBULATKAN 11,590,000.00
Terbilang : Sebelas Juta Lima Ratus Sembilan Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Plesteran
TAHUN ANGGARAN : 2020 VOLUME : 169.12 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Pasir Pasangan 0.026 4.00 M3 360,000.00 1,440,000.00
2 Semen 50 Kg 0.104 18.00 Zak 75,000.00 1,350,000.00
SUB JUMLAH I 2,790,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.03 5.00 hok 100,000.00 500,000.00
2 Tukang Batu 0.04 7.00 hok 125,000.00 875,000.00
3 Kepala Tukang 0.001 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,525,000.00
JUMLAH TOTAL 4,315,000.00
DIBULATKAN 4,315,000.00
Terbilang : Empat Juta Tiga Ratus Lima Belas Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :

LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU


: Lantai Keramik 40 x
SUB PEKERJAAN 40 cm
TAHUN ANGGARAN : 2020 VOLUME : 30 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Tegel Keramik 40 x 40 cm 6.630 200.00 Bh 12,000.00 2,400,000.00
2 Pasir Pasangan 0.045 1.50 M3 360,000.00 540,000.00
3 Semen 50 Kg 0.196 6.00 Zak 75,000.00 450,000.00
SUB JUMLAH I 3,390,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.70 21.00 hok 100,000.00 2,100,000.00
2 Tukang Batu 0.35 10.00 hok 125,000.00 1,250,000.00
3 Kepala Tukang 0.04 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 3,500,000.00
JUMLAH TOTAL 6,890,000.00
DIBULATKAN 6,890,000.00
Terbilang : Enam Juta Delapan Ratus Sembilan Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG
SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Kuda-Kuda
TAHUN ANGGARAN : 2020 VOLUME : 0.40 M3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Balok Kayu Kls II 6/12 1.100 0.44 M3 4,500,000.00 1,980,000.00
2 Besi Strip 15.000 6.00 Kg 35,000.00 210,000.00
3 Paku Biasa 5.600 2.00 Kg 35,000.00 70,000.00
SUB JUMLAH I 2,260,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 4.00 2.00 hok 100,000.00 200,000.00
2 Tukang Kayu 12.00 5.00 hok 125,000.00 625,000.00
3 Kepala Tukang 1.00 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 975,000.00
JUMLAH TOTAL 3,235,000.00
DIBULATKAN 3,235,000.00
Terbilang : Tiga Juta Dua Ratus Tiga Puluh Lima Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Gording
TAHUN ANGGARAN : 2020 VOLUME : 0.37 M3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Balok Kayu Kls II 5/10 1.100 0.41 M3 4,500,000.00 1,845,000.00
2 Paku Biasa 3.000 1.00 Kg 35,000.00 35,000.00

SUB JUMLAH I 1,880,000.00


II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 4.00 2.00 hok 100,000.00 200,000.00
2 Tukang Kayu 12.00 4.00 hok 125,000.00 500,000.00
3 Kepala Tukang 1.20 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 850,000.00
JUMLAH TOTAL 2,730,000.00
DIBULATKAN 2,730,000.00
Terbilang : Dua Juta Tujuh Ratus Tiga Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : List Plank
TAHUN ANGGARAN : 2020 VOLUME : 33.20 M'

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Papan Kayu Kls II 2/20 0.011 0.37 M3 4,500,000.00 1,665,000.00
2 Paku biasa 0.100 3.00 Kg 35,000.00 105,000.00

SUB JUMLAH I 1,770,000.00


II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.10 3.00 hok 100,000.00 300,000.00
2 Tukang Kayu 0.20 6.00 hok 125,000.00 750,000.00
3 Kepala Tukang 0.02 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,200,000.00
JUMLAH TOTAL 2,970,000.00
DIBULATKAN 2,970,000.00
Terbilang : Dua Juta Sembilan Ratus Tujuh Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Atap Spandek
TAHUN ANGGARAN : 2020 VOLUME : 68.80 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Atap Spandek 1.020 70.00 M2 55,000.00 3,850,000.00
2 Nok Atap Spandek 8.00 M' 35,000.00 280,000.00
3 Paku seng 0.040 3.00 Kg 35,000.00 105,000.00
SUB JUMLAH I 4,235,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.02 2.00 hok 100,000.00 200,000.00
2 Tukang Kayu 0.04 4.00 hok 125,000.00 500,000.00
3 Kepala Tukang 0.004 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 850,000.00
JUMLAH TOTAL 5,085,000.00
DIBULATKAN 5,085,000.00
Terbilang : Lima Juta Delapan Puluh Lima Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG

SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :

LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU


: Kusen Pintu dan
SUB PEKERJAAN Jendela
TAHUN ANGGARAN : 2020 VOLUME : 0.20 M3

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Balok Kayu Kls II 6/12 1.200 0.25 M3 4,500,000.00 1,125,000.00
2 Paku Biasa 1.250 1.00 Kg 35,000.00 35,000.00

SUB JUMLAH I 1,160,000.00


II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 6.00 2.00 hok 100,000.00 200,000.00
2 Tukang Kayu 18.00 4.00 hok 125,000.00 500,000.00
3 Kepala Tukang 1.80 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 850,000.00
JUMLAH TOTAL 2,010,000.00
DIBULATKAN 2,010,000.00
Terbilang : Dua Juta Sepuluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG
SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :

: Pintu Panil, Bingkai


LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU Jendela dan Kaca
SUB PEKERJAAN Bening
TAHUN ANGGARAN : 2020 VOLUME : 2.80 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Papan Kayu Kls II 0.20 M3 4,500,000.00 900,000.00
2 Kaca Bening 5 mm 1.100 8.00 M2 95,000.00 760,000.00

SUB JUMLAH I 1,660,000.00


II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 3.00 hok 100,000.00 300,000.00
2 Tukang Kayu 5.00 hok 125,000.00 625,000.00
3 Kepala Tukang 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,075,000.00
JUMLAH TOTAL 2,735,000.00
DIBULATKAN 2,735,000.00
Terbilang : Dua Juta Tujuh Ratus Tiga Puluh Lima Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG
SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Pek. Penggantung
TAHUN ANGGARAN : 2020 VOLUME :

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Kunci Pintu 2 Putaran 1.00 Bh 100,000.00 100,000.00
2 Engsel Pintu 3.00 Bh 35,000.00 105,000.00
3 Engsel Jendela 8.00 Bh 20,000.00 160,000.00
4 Gerendel Pintu 1.00 Bh 25,000.00 25,000.00
5 Gerendel Jendela 7.00 Bh 15,000.00 105,000.00
6 Hak Angin 7.00 Bh 10,000.00 70,000.00
SUB JUMLAH I 565,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 2.00 hok 100,000.00 200,000.00
2 Tukang Kayu 3.00 hok 125,000.00 375,000.00
3 Kepala Tukang 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 725,000.00
JUMLAH TOTAL 1,290,000.00
DIBULATKAN 1,290,000.00
Terbilang : Satu Juta Dua Ratus Sembilan Puluh Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG
SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Cat Kayu
TAHUN ANGGARAN : 2020 VOLUME : 23.10 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Cat Meni 0.200 5.00 Kg 35,000.00 175,000.00
2 Plamur 0.150 4.00 Kg 50,000.00 200,000.00
3 Cat Dasar 0.170 4.00 Kg 35,000.00 140,000.00
4 Cat Penutup 0.350 8.00 Kg 50,000.00 400,000.00
5 Pengencer 0.030 6.00 Ltr 15,000.00 90,000.00
6 Kuas 0.010 2.00 Bh 15,000.00 30,000.00
7 Amplas 0.200 5.00 Lbr 10,000.00 50,000.00
SUB JUMLAH I 1,085,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.07 2.00 hok 100,000.00 200,000.00
2 Tukang Cat 0.09 2.00 hok 125,000.00 250,000.00
3 Kepala Tukang 0.06 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 600,000.00
JUMLAH TOTAL 1,685,000.00
DIBULATKAN 1,685,000.00
Terbilang : Satu Juta Enam Ratus Delapan Puluh Lima Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG
SUBHAN, SE. MM
RENCANA ANGGARAN BIAYA
KEGIATAN : BIDANG PELAKSANAAN PEMBANGUNAN DESA NO. RAB :
: PEMB. RUMAH PRODUKSI KRIPIK NENAS DAN SELAI
PEKERJAAN NENAS KODE ANGGARAN :
LOKASI : DESA PATTALASSANG, KEC. TOMPOBULU SUB PEKERJAAN : Cat Tembok
TAHUN ANGGARAN : 2020 VOLUME : 169.12 M2

HARGA SATUAN JUMLAH HARGA


NO URAIAN PEKERJAAN KOEFISIEN VOLUME SATUAN
(Rp) (Rp)
I BAHAN
1 Cat Penutup 0.260 30.00 Kg 70,000.00 2,100,000.00
2 Cat Dasar 0.100 8.00 Kg 30,000.00 240,000.00
3 Plamur 0.100 8.00 Kg 50,000.00 400,000.00
4 Kuas Roll 2.00 Bh 50,000.00 100,000.00
SUB JUMLAH I 2,840,000.00
II ALAT
-
-
-
-
-
-
SUB JUMLAH II -
III UPAH
1 Pekerja 0.02 3.00 hok 100,000.00 300,000.00
2 Tukang Cat 0.06 11.00 hok 125,000.00 1,375,000.00
3 Kepala Tukang 0.01 1.00 hok 150,000.00 150,000.00
SUB JUMLAH III 1,825,000.00
JUMLAH TOTAL 4,665,000.00
DIBULATKAN 4,665,000.00
Terbilang : Empat Juta Enam Ratus Enam Puluh Lima Ribu Rupiah

DESA PATTALASSANG…………………2020

DIKETAHUI OLEH DIBUAT OLEH


SEKDES TIM PERENCANA

HAERUDDIN SUPARJAN SIDI

MENGETAHUI
KEPALA DESA PATTALASSANG
SUBHAN, SE. MM

You might also like