You are on page 1of 23

Research Policy 29 Ž2000.

871–893
www.elsevier.nlrlocatereconbase

The project-based organisation: an ideal form for managing


complex products and systems?
Mike Hobday )
Science and Technology Policy Research (SPRU), Complex Prod. Sys. (CoPS) InnoÕ. Cen., Mantell Building, UniÕersity of Sussex, Falmer,
Brighton, East Sussex BN1 9RF, UK

Abstract

This paper examines the effectiveness of producing so-called CoPS Ži.e., complex high value products, systems,
networks, capital goods, and constructs. in a project-based organisation ŽPBO., as compared with a more traditional
functional matrix organisation. A simple model is developed to show how the PBO relates to identified forms of matrix and
functional organisation and a case study is used to identify some of the strengths and weaknesses of the two organisational
forms for CoPS production. On the positive side, the PBO is an intrinsically innovative form as it creates and recreates new
organisational structures around the demands of each CoPS project and each major customer. The PBO is able to cope with
emerging properties in production and respond flexibly to changing client needs. It is also effective at integrating different
types of knowledge and skill and coping with the project risks and uncertainties common in CoPS projects. However, the
PBO is inherently weak where the matrix organisation is strong: in performing routine tasks, achieving economies of scale,
coordinating cross-project resources, facilitating company wide technical development, and promoting organisation-wide
learning. The PBO can also work against the wider interests of corporate strategy and business coordination. Strategies to
stimulate organisational learning and technical leadership include the deployment of coordinators along functional lines to
cut across project interests and incentives. Project tracking and guidance at the corporate level is also important for achieving
broader business goals. The paper illustrates the wide variety of organisational choices involved in producing CoPS and
argues that the nature, composition, and scale of the product in question have an important bearing on appropriate
organisational form. q 2000 Elsevier Science B.V. All rights reserved.

Keywords: Project-based organisation; Complex products and systems ŽCoPS.; Functional organisation; Matrix organisation

1. Introduction kets, cross-functional business expertise, customer-


focused innovation and market, and technological
In contrast to the functional and matrix organisa- uncertainty. This applies particularly to high value,
tion, the project-based organisation ŽPBO. has been complex industrial products and systems Žor ‘CoPS’.,
put forward as a form ideally suited for managing the sophisticated high technology capital goods,
increasing product complexity, fast changing mar- which underpin the production of goods and ser-
vices. Some studies suggests that the PBO is a
natural organisational form for CoPS producers, es-
)
Tel.: q44-1273-686758; fax: q44-1273-685865. pecially when several partner suppliers are engaged
E-mail address: m.g.hobday@susx.ac.uk ŽM. Hobday.. with the user through the various stages of innova-

0048-7333r00r$ - see front matter q 2000 Elsevier Science B.V. All rights reserved.
PII: S 0 0 4 8 - 7 3 3 3 Ž 0 0 . 0 0 1 1 0 - 4
872 M. Hobdayr Research Policy 29 (2000) 871–893

tion and production ŽHobday, 1998; Gann and Salter, and performance attributes Že.g., flexibility, effec-
1998.. tiveness, efficiency, and return on investment. to
Existing firm-level research explores the potential particular factors such as organisational form, rather
advantages of PBOs, tensions between project- and than other factors Že.g., project leadership, company
corporate-level processes, PBO suitability for pro- culture, product market differences, and senior man-
ducing service-enhanced products, and the nature of agement support.. The method adopted to overcome
PBO behaviours and structures ŽBrusoni et al., 1998; some of these difficulties is to take the case of a
Gann and Salter, 1998.. Focusing on the project single large CoPS supplier which, for particular his-
rather than the firm, the new product develop- torical reasons, operates a mix of both project-based
ment ŽNPD. field points to the benefits of strong and functionalrmatrix forms, addressing similar
projects in NPD, the leadership requirements for product markets and clients with the same senior
‘heavyweight’ project teams ŽClark and Wheel- management team.1 The paper analyses and com-
wright, 1992., and the need for the greater profes- pares two CoPS projects of similar value, duration,
sionalisation of project management as projects as- technology, and customer, in the two distinct strate-
sume increasing importance across various high gic business units, one PBO and one functionalrma-
technology industries ŽPinto and Kharbandha, 1995.. trix. By identifying process differences, as well as
So far, however, there has been little research on the advantages and disadvantages of both forms, the
the scale or pace of diffusion of the PBO form, or paper points to some important limits of the PBO in
how the PBO actually operates in practice in the the management of CoPS projects. It also identifies a
management of CoPS. We know very little about the modified form of the PBO, termed here the ‘project-
PBO or how its processes differ from those of led organisation’, which has been used to overcome
various matrixrfunctional forms of organisation or some of the limits of the pure PBO.
how disadvantages of the PBO can be overcome in The paper is structured as follows. Section 2
practice. Nor has there been much discussion of the examines the nature of the project management chal-
various different types of PBO Že.g., large vs. small lenge in CoPS. Section 3 then provides a working
PBOs, single project vs. multiple project PBOs.. definition of the PBO and develops a simple model
The aim of this paper is to identify some of the to show how the PBO differs from and relates to
features of the PBO by looking in depth at how other forms of organisation identified in the litera-
CoPS projects are managed in one large PBO, com- ture. Section 4 then presents the case of a producer
paring this with CoPS produced in a functional of highly complex, particle accelerator systems
division of the same company. The purpose of taking ŽComplex Equipment Inc.. to illustrate the advan-
a ‘bottom up’ project perspective is to explore the tages and disadvantages of the PBO structure, focus-
dynamics of project structures, processes, and perfor- ing on project processes, problems, and performance.
mance in the PBO vs. a functional organisation. Section 5 interprets the evidence arguing that the
Although it is outside the scope of the paper to PBO provides a concurrent and outward-looking ap-
examine corporate-level structures and processes, the proach to project management, while the
case illustrates some of the key advantages and functionalrmatrix form embodies a more linear, in-
disadvantages of the PBO in the execution of major ward-looking and less flexible approach. Section 5
CoPS projects and draws attention to tensions be- also comments on the underlying economic motiva-
tween project and company-wide processes in PBOs. tions for adopting a project-based form for CoPS and
The paper also suggests how some of the problems
intrinsic to the PBO form can be overcome in prac-
tice.
1
One of the problems of case study research of this Although the case study design allows an in-depth compari-
kind is the counterfactual difficulty of knowing what son of the different structures and projects within the same firm,
the method cannot fully overcome the problem of project unique-
would have happened Že.g., in terms of performance. ness and history Žsee Section 4.1 for a discussion of the limitations
if another organisational structure had been applied. of the method and possible ways of overcoming these in future
It is also difficult to attribute particular behavioural research..
M. Hobdayr Research Policy 29 (2000) 871–893 873

indicates strategies which can be used Že.g., the tremely complex’, embodying many highly elabo-
deployment of a milder form of PBO, the ‘project-led rate, customised sub-systems and components, new
organisation’. to resolve corporate strategy and com- knowledge and multiple feedback loops in both de-
pany-wide learning problems inherent in the PBO. sign, and production Že.g., a new generation military
aircraft.. At the other end of the spectrum, there are
less complex products where the boundaries of un-
2. Innovation in CoPS certainty are better understood, architectures and
components are relatively well-established, reducing
the risk inherent in the production of each good Že.g.,
2.1. What are CoPS? a new model flight simulator.. In between there are
‘highly complex’ and ‘moderately complex’ goods.
CoPS are the high-technology, business-to-busi- In all cases though, ‘complex products’ can be dis-
ness capital goods used to produce goods and ser- tinguished from simpler or even complicated prod-
vices for consumers and producers. Unlike high vol- ucts, where architectures are relatively simple, com-
ume consumption goods, each individual CoPS is ponents are relatively few in number Žand usually
high cost and made up of many interconnected, often standardised., the degree of new knowledge required
customised parts Žincluding control units, sub-sys- for each product is fairly constrained and production
tems, and components., designed in a hierarchical tasks can be codified, routinised, and automated to
manner and tailor-made for specific customers ŽHob- produce process efficiency and cost reduction based
day, 1998; Walker et al., 1988.. Often their sub-sys- on volume Že.g., a bicycle or toaster could be de-
tems Že.g., the avionics systems for aircraft. are scribed as ‘simple’ products, whereas a passenger
themselves complex, customised, and high cost vehicle could be described as ‘complicated’ but not
ŽMowery and Rosenberg, 1982.. As a result of their complex, as defined here.
cost, physical scale, and composition, CoPS tend to Technical progress, combined with new industrial
be produced in projects or small batches, which demands have greatly enhanced the functional scope,
allow for a high degree of direct user Žsometimes complexity, pervasiveness, and performance of CoPS
owner–operator. involvement in the innovation pro- Že.g., business information networks, tailored soft-
cess, rather than through arms-length market transac- ware packages, and internet super-servers.. The na-
tions as is normally the case in commodity goods. ture of CoPS can lead to extreme task complexity,
During design and production, small design which, in turn, demands particular forms of manage-
changes in one part of a system can lead to large ment and industrial organisation.
alterations in other parts, calling for more sophisti-
cated control systems, new materials, and novel de- 2.2. Industrial innoÕation in CoPS
sign approaches. Once installed, some CoPS Že.g.,
intelligent buildings and computer integrated manu- CoPS are often produced within projects which
facturing systems. further evolve as users expand, incorporate prime contractors, systems integrators,
optimise, adopt, and operate the system ŽGann, 1993; users, buyers, other suppliers, small- and medium-
Fleck, 1988.. sized enterprises ŽSMEs. and sometimes government
Product complexity, of course, is a matter of agencies and regulators. Often, these ‘innovation
degree. Hobday Ž1998. puts forward various dimen- actors’ collaborate together, taking innovation Že.g.,
sions of product complexity, including numbers of new design. decisions in advance of and during
components, the degree of customisation of both production. Sometimes users and suppliers engage in
system and components, the number of design co-engineering throughout the production process.
choices, elaborateness of system architectures, the Prime contractors and systems integrators are re-
range, and depth of knowledge and skill inputs re- sponsible for managing CoPS projects, which amount
quired, and the variety of materials and information to temporary multi-firmruser alliances. Given the
inputs. According to an amalgam of these dimen- nature of CoPS, systems integration, and project
sions, some products can be categorised as ‘ex- management competencies are critical to production
874 M. Hobdayr Research Policy 29 (2000) 871–893

effectiveness and efficiency.The project is a widely complete information, relying on inputs from other
used form of coordination in CoPS. The project is a suppliers who may be competitors in other projects.
focusing device which enables different types of In some cases these challenges have led firms to
innovation actors to agree the fine detail of CoPS re-organise their entire business activities along pro-
development and production. The project is responsi- ject-based lines, leading to project-based organisa-
ble for realising the market, for coordinating deci- tional structures.
sions across firms, for enabling buyer involvement,
and for matching technical and financial resources
through time. The project exists to communicate 3. The nature of the PBO
design and architectural knowledge and to combine
the distinctive resources, know-how, and skills of the 3.1. Definition and key propositions
collaborators.
Because production is oriented to meet the needs In contrast to the matrix, functional, and other
of large business users, the project management task forms, the PBO is one in which the project is the
is fundamentally different from the mass production primary unit for production organisation, innovation,
task. As Joan Woodward Ž1958, p. 23. put it in her and competition.2 Although the PBO is commonly
research into UK project-based companies in the used in private manufacturing enterprise, it is also
1950s: Athose responsible for marketing had to sell, deployed in other organisations Žpublic and private.,
not a product, but the idea that their firm was able to including the legal profession, consultancy firms,
produce what the customer required. The product marketing, the film industry, and advertising. While
was developed after the order had been secured, the a project can be defined as any activity with a
design being, in many cases, modified to suit the defined set of resources, goals, and time limit Že.g.,
requirements of the customer. In mass production for information technology or new materials., within
firms, the sequence is quite different: product devel- a PBO the project is the primary business mecha-
opment came first, then production, and finally mar- nism for coordinating and integrating all the main
keting.B business functions of the firm Že.g., production, R &
The specific CoPS in question will shape the form D, engineering, NPD, marketing, personnel, and fi-
and nature of the project. In the case of very large nance..
engineering constructs, entire project-based industrial Within a pure PBO Ži.e., an organisation in which
structures can be called into being by various stake- no other form is present., major projects will em-
holders for the purpose of creating a single product. body most, if not all, of the business functions
The Channel Tunnel, for example, entailed a massive normally carried out with departments of functional
task of financial, managerial, and technological coor- and matrix organisations. In some cases, the project
dination involving hundreds of contractors, at least involves a consortium of companies Že.g., Sematech,
208 lending banks and around 14,500 employees at Airbus, the Channel Tunnel, and the Millennium
its peak ŽLemley, 1992, p. 14, 23.. By contrast, with Dome.. In other PBOs, much or all of the project
smaller CoPS Že.g., flight simulators and telecommu- may be carried out within the boundaries of a single
nications exchanges. much of the project task is company. Because core business processes are or-
carried out within the managerial span of control of a ganised within projects rather than functional depart-
single firm. ments, the PBO is an alternative to the matrix, where
In CoPS, design-intensity and product complexity business functions are carried out both within pro-
lead to many extremely complicated, non-routine jects and along functional lines. In the PBO, the
tasks ŽHobday and Rush, 1999.. Users frequently
change their requirements during production, leading
to unclear goals, uncertainty in production, and un-
predictable, unquantifiable risks. Success and failure 2
This paper uses the term PBO rather than project-based firm
are multifaceted and hard to measure. Managers have as a single firm may deploy both project-based divisions as well
to proceed from production stage-to-stage with in- as functional divisions Žas in the case example in Section 4..
M. Hobdayr Research Policy 29 (2000) 871–893 875

knowledge, capabilities, and resources of the firm tions handsets and exchanges.. Thus, particular pro-
are built up through the execution of major projects. jects may be ‘large’ for a small or medium-sized
Project managers ŽPMs. within the PBO typically firm or ‘small’ for a large or very large firm, imply-
have very high status and direct control over busi- ing that the manner in which project organisations
ness functions, personnel, and other resources. PMs are established, perceived, and deployed varies with
and directors are senior to resource coordinators Žthe firm characteristics.
nearest equivalent to the functional manager in the PBOs organise their structures, strategies, and
PBO., whose role is to support the needs of projects capabilities around the needs of projects, which often
and PMs and, sometimes, to coordinate business cut across conventional industrial and firm bound-
functions across various projects Že.g., technical, hu- aries. In CoPS industries, there are many different
man, and financial resources for project bidding, categories of PBO, ranging from large prime contrac-
management, systems engineering, and so on.. tors, which specialise in project management and
Because the project is a temporary organisational systems integration, to tiny specialised sub-contrac-
form, the PBO is inherently flexible and reconfig- tors, which supply tailored components, software or
urable in contrast with the anti-innovation bias of services. Any one project may combine these groups
large integrated, hierarchical organisations described in a variety of roles, with the same firm acting as
by Williamson Ž1975. and Teece Ž1996. and the core prime contractor in some projects and sub-contractor
rigidities identified by Leonard-Barton Ž1992.. in others. Not all firms within a project are necessar-
Within the PBO a project is often a major busi- ily PBOs. Also, PBOs can range from firms servic-
ness endeavour and the normal mechanism for crea- ing one single project to firms which execute many
ting, responding to, and executing new business hundreds of projects at any one time Že.g., in con-
opportunities. Each project is likely to involve a struction..
specific well-defined product and one or a few iden- The structures and business processes of PBOs
tified customers. In many cases, the customer Žoften are likely to be shaped by the changing profile of
a user or owner–operator. will be closely and di- projects, especially their size, complexity, and dura-
rectly engaged in primary innovation and production tion. Some PBOs Že.g., in construction. are likely to
processes, as each project will tend to be critical to derive most of their income from large projects over
the business functioning, performance, and prof- which they exercise little direct span of control
itability of the user. The PBO is widespread in ŽGann, 1993.. In other cases, firms may direct and
traditional industries Že.g., construction, shipbuild- control particular projects, largely from within the
ing, and major capital projects., industries that have firm, as noted earlier. Major new projects become
been regenerated through new technologies Že.g., central innovation events in some CoPS industries,
aerospace and telecommunications., newly emerging giving rise to new business opportunities and novel
industries Že.g., information and communication technological trajectories.
technologies. and many other examples of business-
to-business, high-technology, high value capital
goods.
3.2. Research perspectiÕes on the PBO
In principle, the PBO is not suited to the mass
production of consumer goods, where specialisation
along functional lines confers learning, scale, and Various bodies of research help inform our under-
marketing advantages. However, within large manu- standing of the position, nature, and advantages of
facturing firms the project form is used to organise the PBO. At the project level, research on NPD has
specific non-routine activities and complex tasks such long recognised the importance of the project for
as R & D, NPD, and advertising campaigns. Also, integrating business functions and responding to
some large multiproduct firms embody both PBO complex technical challenges for the purpose of de-
and functional divisions Žor strategic business units. veloping new products. Clark and Wheelwright
to deal with different types of products, technologies, Ž1992., for example, describe four basic types of
and markets Že.g., producers of both telecommunica- organisational structure for NPD: Ž1. functional; Ž2.
876 M. Hobdayr Research Policy 29 (2000) 871–893

lightweight project structure; Ž3. heavyweight project agement are required which are able to link functions
structure; and Ž4. project-based. In conventional such as R & D and marketing.3
functionalrlightweight project structures, PMs tend
to be junior to functional managers and have no 3.3. A simple positioning framework for the PBO
direct control over resources. In the heavyweight
project approach, functions such as marketing, fi- In order to understand the relationship between
nance, and production tend to be coordinated by the PBO and other types of organisation, Galbraith
managers across project lines, but PMs have high Ž1971, 1973. describes a range of alternatives from
status and direct control over financial resources and pure functional form through to pure product form,
people. where management structures are centred upon each
In their analysis of the influence of management product Žequivalent to the PBO.. Building on Gal-
structure on project success, Larson and Gobeli braith’s work, Larson and Gobeli Ž1987, 1989. de-
Ž1989. show how both project management structure scribe three distinct types of matrix. First, is the
and other variables such as new technology, project functional matrix, where the PM is confined to coor-
complexity, managerial competence, top manage- dinating resources, monitoring progress, and report-
ment support, project size, and well-defined objec- ing into one or more functional managers. Second, is
tives impact on project success. Pinto and Prescott the balanced matrix, where responsibilities and au-
Ž1988., analyse how critical success factors vary thority for each project are shared between func-
over the life cycle of projects, while Pinto and Covin tional and PMs. The third is the product Žor project.
Ž1989. show how such factors depend on the type of matrix, where the PM has authority over personnel,
product and activity in question. Shenhar Ž1993.
provides insights into the importance of new knowl-
edge in project risk and uncertainty, comparing low-
3
with high-technology projects. Building on the work of Burns and Stalker, Mintzberg Ž1979.
Focusing on the benefits of the project form, points out that appropriate organisational forms are contingent on
factors such as market, task, and technology. He describes five
some innovation scholars have argued that projects basic organisational forms: Ža. the machine bureaucracy with
and project management are the ‘wave of the future highly centralised control systems, suited to a stable environment;
in global business’ due to increasing technical and Žb. the divisional form suited to mass production efficiency; Žc.
product complexity, shortening time to market win- the professional bureaucracy made up of flat organisational struc-
dows, and the need for cross-functional integration tures, useful for delegating complex, professional tasks Že.g., in
universities.; Žd. the simple or entrepreneurial structure, valuable
and fast response to changing client needs ŽPinto and for its informality and flexibility; and Že. the adhocracy, which is
Kharbanda, 1995.. It is certainly reasonable to as- a temporary project team design, suited to complex tasks and
sume that as market change, risk, and uncertainty turbulent and uncertain markets. Similarly, Teece Ž1996. proposes
increase, the project form will grows in importance six categories of firm: Ž1. stand-alone entrepreneur inventor; Ž2.
in a wide range of industries and tasks. multiproduct integrated hierarchy; Ž3. high flex, Silicon Valley
type; Ž4. virtual corporation; Ž5. conglomerate; and Ž6. alliance
At the firm level, traditional innovation writers enterprise. Taking an historical perspective, Miles and Snow
have long recognised the advantages of flexible pro- Ž1986. argue the organisations have evolved from the owner–
ject-based organisational forms. Burns and Stalker manager of the 18th century, to the vertical organisation of the
Ž1961. made the classic distinction between organic mid-19th century, through to the divisionalised and matrix organi-
and mechanistic organisational forms, arguing that if sational structures suited to the mass production of industrial
goods in the mid-20th century. They argue that a new form Žthe
a stable routine environment prevailed and the mar- dynamic network. has recently emerged in high technology pro-
ket was fairly predictable, then firms can reap advan- duction. In the network, large and small firms collaborate to-
tage from mechanistic, functional organisational gether, responding to fast changing market needs. Key business
forms with clearly defined job descriptions, stable functions such as product design, R&D, manufacturing, and distri-
operational boundaries, and Taylorist methods of bution are performed by independent firms cooperating together
and linked by ‘brokers’ who provide information to network
working. However, in the case of rapidly changing members and coordinating overall operations. In Miles and Snow’s
technological and market conditions, then open and formulation, brokers and partners are similar to Teece’s virtual
flexible Ž‘organic’. styles of organisation and man- firm and alliance enterprise, respectively.
M. Hobdayr Research Policy 29 (2000) 871–893 877

finance, and other resources. Finally, the pure prod- departments of the organisation Že.g., marketing, fi-
uctrproject-based form is an extreme form where nance, human resources, engineering, R & D, and
the business is organised solely around productrpro- manufacturing. are represented by F1 to F5, while
ject lines. notional CoPS projects are represented by P1 to P5.
Interpreting the above literature, Fig. 1 provides a Type B is a functionally-oriented matrix, with weak
description of six ideal-type organisational forms project coordination Žas described in the case study
ranging from the pure functional form ŽType A. to ‘FMD’ below.. Type C is a balanced matrix with
pure project form ŽType F.. The various functional stronger project management authority. Type D is a

Fig. 1. Positioning the project-based organization. ŽA. Functional, ŽB. functional matrix, ŽC. balanced matrix. ŽD. Project matrix. ŽE.
Project-led organization. ŽF. Project-based organization.
878 M. Hobdayr Research Policy 29 (2000) 871–893

project matrix, where PMs are of equal status to ture, scale, and complexity of the product must be
functional managers. considered. With a balance of small batch, CoPS,
Beyond the project matrix, lies a form not identi- and mass produced goods, organisational choices
fied in the literature ŽType E., called here a ‘project- become messy, complex, and dynamic. Mistakes can
led organisation’, in which the needs of projects be very costly. As the product mix evolves, organisa-
outweigh the functional influence on decision-mak- tions need to change in order to respond to product
ing and representation to senior management, but market needs.
some coordination across project lines occurs. Fi-
nally, Type F is the pure PBO as defined in Sec. 3.1,
and illustrated below in the case study ‘PBD below’. 3.4. Gaps in the literatures
Here, there is no formal functional coordination
across project lines; the entire organisation is dedi- While Galbraith Ž1971. and others provide useful
cated to one or more CoPS projects and business tools for positioning the PBO in relation to other
processes are coordinated within the projects. organisational forms, they fall short of examining the
The positioning diagram helps to contrast the PBO itself and do not analyse its advantages and
various forms of organisation available and to high- disadvantages. Surveys of project successrfailure
light those most suited for different types of CoPS, factors are generally unable to explore intra-project
accepting that a mixed organisational structure is dynamics and tend to ignore the informal, human Žor
possible even within a single business unit. Forms A ‘soft’. side of project progress which are so impor-
to C are unsuitable to managing the CoPS, because tant to performance ŽKatz, 1997.. Much of the litera-
they are not appropriate for performing non-routine, ture tends to assume products are being developed
complex project tasks in an uncertain, risky, and ‘for the market place’ whereas CoPS are usually
changing environment. CoPS projects require ‘super- transacted with the user Žand other suppliers. in
heavyweight’ professional PMs Žor directors., capa- unique combinations and rarely, if ever, transacted in
ble of integrating both commercial and technical an arms length market setting.
business functions within the project and building Similarly, while studies of NPD and project per-
strong lines of external communication both with the formance help disentangle the many facets of project
client Žoften the source of the innovation idea. and success and failure, they do not explore PBO pro-
other collaborating companies. These external inno- cesses nor do they tend to distinguish between com-
vation actors typically have different goals, struc- plex capital goods and mass-produced products. Nor
tures and cultures, and the task of the CoPS project does the project success literature tend to examine
director is to skilfully negotiate a path towards suc- the changing nature of projects through time. This
cessful completion. issue is especially important for CoPS projects, which
The pure PBO is probably best suited for large involve several outside innovation partners in differ-
innovative projects and single project firms, where ent ways through the various stages of the project
resources have to be combined and shared with other cycle.
firms in the project Žthe multi-firm CoPS project.. To contribute to an understanding of innovation
The PBO is a form suitable for meeting innovative management in CoPS, Section 4 illustrates how one
needs, responding to uncertainty, coping with emerg- PBO deploys its resources to create and deliver
ing properties, responding to changing client require- single complex products. By comparing the progress
ments and learning in real time. By contrast, the of CoPS projects in the PBO and functional matrix
PBO is weak where the functional matrix is strong: forms, the case shows how well suited the PBO is
in coordinating resources and capabilities across pro- for creating and executing large and risky CoPS
jects, in executing routine production and engineer- projects. However, the case also highlights the diffi-
ing tasks, achieving economies of scale and meeting culties PBOs face in capturing and transferring pro-
the needs of mass markets. ject knowledge with pressures, structures, and rou-
More broadly the framework implies that in tines crowding out learning from one project to
choosing an appropriate organisational form the na- another.
M. Hobdayr Research Policy 29 (2000) 871–893 879

4. The case of complex equipment inc project P in PBD and F in FMD. in order to review
and compare project processes, problems and perfor-
4.1. Case objectiÕes, method, and limitations mance and to draw lessons for both organisations.6
The CoPS in question was an experimental form of
The purpose of the case study is to assess CoPS synchrotron particle accelerator which is used in
project performance and processes and to look at the sub-micron semiconductor R & D and other scientific
nature, strengths, and weaknesses of the PBO in applications. The price of each unit was in the order
comparison with the functional form through the lens of $10 million each and the duration of the projects
of two major projects, one in a PBO division and one was around 18 months in each case.
in a functional division. The case also examines how The research involved three stages: first, a struc-
PBO disadvantages can be overcome in practice. tured questionnaire was used to gather the views of a
The case study is a large German-owned pan- sample of practitioners in each project, including
European firm ŽComplex Equipment Inc., which em- scientists, engineers, draftsmen, technicians, and
ploys around 4000 people and produces a wide range PMs. Views were sought on the detailed, actual
of advanced, high-cost scientific, industrial, and experiences of PBD project P and FMD project F
medical equipment.4 For some years, the company and on perceptions of the wider strengths and weak-
had experienced serious problems Ždelays, cost ness of both organisations. Second, interviews were
over-runs, and customer dissatisfaction. in producing carried out with senior managers and directors on
CoPS within its functional matrix division Žcalled their perceptions of the projects and each organisa-
FMD here. in one of its strategic business units, tions strengths and weaknesses. Third, a workshop
which produced both CoPS and small batch, simpler was arranged with both groups to feedback results
products. In another strategic business unit, which and check the findings were consistent with the
reports to the same senior management, a pure pro- experiences of the staff, many of whom had worked
ject-based division Žcalled PBD. had been converted for both parts of the organisation and other strategic
from a matrix organisation to deal solely with large business units within Complex Equipment Inc.
CoPS projects.5 Twenty interviews were conducted for each pro-
The senior management wished to learn from the ject. Information was gathered on origin, history,
operating experiences of PBD, which had been in structure, management, client relations, supplier
pure PBO form for around 2 years. PBD had proved links, project processes, and performance. The sam-
highly successful in meeting customer needs and ple consisted of a ‘slice group’ Ži.e., representatives
project performance targets. A key strategic decision of most main functions and seniority levels of the
was whether or not to implement a pure PBO in two projects.. Within the case, the research focused
FMD, a larger division. The management felt that on:
there were lessons to learn from the good and bad
experiences of both organisations. Although both Ø Organisational structure,
PBD and FMD produced similar CoPS equipment, Ø Project management and leadership,
for geographical reasons the physical merging of the Ø Team identity and coherence,
two sites was not an option in the foreseeable future. Ø Client and client management,
The research method involved examining the ex- Ø Risk management,
perience of two similar, complex projects Žtermed

6
Project processes refer to patterns of managerial, technologi-
4
The name of the company, as well as project names, have cal, and operational practice: the ‘way things are done’, within the
been changed to protect confidentiality. project, including both formal and informal routines. At the
5
PBD corresponds to type F in Fig. 1, while FMD corresponds broader firm level, processes occur within and across the various
to type B. The firm provides an unusual opportunity to compare a functions of the firm Že.g., marketing, production, finance, engi-
PBO with an FMO in a single company, with the same company neering, R&D, and personnel. and occur both formally and infor-
culture and senior management. mally, shaping the efficiency and effectiveness of a firm.
880 M. Hobdayr Research Policy 29 (2000) 871–893

Ø Formal and informal tools and procedures, links between project performance, and wider busi-
Ø Organisation-wide learning and coordination, ness processes and comparisons between different
Ø Project performance, types of PBOs, including single project and multi-
Ø Organisational strategies and solutions. project firms.
Accepting these limitations, the case design was
able to illustrate some of the features of the PBO for
Each of these issues is reported upon below in CoPS compared with the functional matrix and ma-
turn, contrasting the functional matrix with the PBO jor differences in project processes, advantages, and
division. disadvantages of the two organisational forms. The
Regarding scope and limitations, the research took case also yielded insights into some of the wider
a ‘bottom up’ look at two real projects, but did not organisational issues, especially organisational learn-
systematically research the broader company pro- ing, which featured as a major problem in the case of
cesses or functions Že.g., corporate strategy, quality PBD. Some of these key issues are illustrated below
systems, bid processes, production, purchasing and using quotations from PMs, engineers, and other
cross-departmental communications.. Nor could the practitioners.
study look systematically at the relations between
project and wider company business processes. Both 4.2. Organisation structure
projects were carried out largely under the control of
the firm Že.g., the degree of co-engineering was low.,
FMD was run as a functional matrix with
so although other partners and users were actively
lightweight PMs. Projects were resourced by the
involved, the case is not an example of an extensive
heads of the functional departments. While PMs
multi-firm project where developments are shared
were nominally in charge of projects they had no
more equally between partners. In addition, the case
direct staff or control over resources, nor a regular
refers to the type of PBO conducting a small number
reporting mechanism into senior management. Within
of major CoPS projects, rather than the case of a
the matrix, PMs for CoPS reported in to one of the
PBO carrying out large numbers of smaller projects
functional managers Žusually engineering.. Tradition-
simultaneously. Even within this category, the case
ally, FMD was heavily biased towards the needs of
issues cannot claim to be generally applicable to
the functional departments and standard product lines
other large firms producing small numbers of elabo-
produced in small batches. However, increasingly
rate, high value CoPS.
CoPS were being processed in FMD leading to
In addition, while the case study design enables
problems, as noted earlier.
an in-depth comparison of different projects within
In contrast to FMD, PBD had been organised
divisions of the same firm, the approach cannot fully
along project-based lines for about 2 years, with PMs
overcome the problem of project uniqueness and
in direct control of project resources, team-building,
history, as noted in the introduction. Even within the
and project outcomes. The PBO had been an experi-
same firm with the same company culture and senior
mental move and was widely viewed as a success.
management, each project is still subject to specific
As noted earlier, the directors of Complex Equip-
factors, which shape overall performance, success
ment Inc wished to learn the lessons for the rest of
and failure, and it is very difficult to normalise for
company and in particular wanted to assess whether
these factors. However, alternative methods of as-
or not to implement a PBO to resolve CoPS prob-
sessing project success factors Že.g., cross-sectional
lems at FMD.
surveys. are also limited as they cannot look in-de-
pth at the evolution of projects through time, infor-
mal practices, and ‘soft’ issues, which are critical to 4.3. Project management and leadership
project success. One way of overcoming these diffi-
culties in future research may be to expand the Because of its functional orientation, the PM of
number and type of intra-project studies of PBOs in project F Žas with other PMs in FMD. had little
order to identify more CoPS project success factors, direct control over project resources, nor a heavy-
M. Hobdayr Research Policy 29 (2000) 871–893 881

weight representation into senior management. This FMD. The PM for project P dealt directly with the
lightweight PM structure had been introduced some client, having both control over, and responsibility
years earlier to run alongside the functional organisa- for, all technical and commercial issues.
tion to deal with CoPS projects. This led to prob- PBDrProject P was particularly strong on the
lems, as described by the PM for project F: AI had no intangible, informal activities essential to project
people working directly for me. They wthe heads of success in uncertain environments Že.g., project man-
the functional departmentsx took people off the pro- agement, close customer relations, good communica-
ject without telling me. The bosses didn’t come to tions, open honest meetings, and mutual respect
project meetings and didn’t really know what was among team members.. In PBDrP a good level of
going on in the project.B Similarly, the senior manu- communication and trust was built up with sub-con-
facturing engineer noted: AIn project F I was not tractors, both large and small. The PBDrP team was
involved or consulted about the original budget esti- as flexible and responsive to changes in specifica-
mates. There was no time to do this job wthe estima- tion, risks, and so on, as one would hope from a
tionx properly. This happens far too often. It wthe well-managed PBO.
projectx should have been resourced properly at the As the PM for Project P put it: AIn PBD we set up
outset but there were conflicts between Jim wthe PMx a new team for every project and we tend to work on
and the resource wi.e., functionalx managers.B one or two builds at a time. As the PM I do the
Given the number of functional departments Žand overall plan and delegate tasks to team members. I
bosses. in FMD, each with standard reporting sys- talk to the engineers and technicians every day be-
tems and procedures, a wide range of reporting cause working relations are vital. Its a matter of
requirements and sometimes conflicting demands mutual trust and respect.B A manufacturing techni-
were placed on the PM for project F. There were five cian for Project P further explained: AIt was a good
main functional departments: engineering, manufac- management set up. She wthe PMx knew exactly what
turing, marketing, finance, and human resources. to do even though it was a very difficult project. One
Reporting into the five departments absorbed a great of the suppliers let us down, so Jane wthe PMx went
deal of time and energy, leading to a reactive, rather down and ordered a new one from another supplier.
than a proactive stance towards risk, client manage- She had to bypass the finance department and tell
ment, product design, manufacture, and so on. them afterwards. That’s not following the rules, but
As discussed below, customer relations were also she judged it necessary to get the job done on time.B
difficult, with the PM looking to functional managers However, there were difficulties not only within
for answers to technical and schedule questions raised the project but also in the wider organisation. These
by the client, but with little direct contact between were proving difficult to address within the PBO
the functional managers and the client. This led to structure Žsee Section 4.8 below..
delays in dealing with client problems and also to
some confusion. In some instances, the two main
sets of client demands Žcommercial and technical.
4.4. Team identity
were in conflict Že.g., new technical specifications
were called for alongside demands to maintain costs
and keep to schedules.. These demands led to diffi- The FMDrProject F team felt that the project was
cult negotiations with the functional managers and under-resourced, given its size, complexity and de-
frequently placed the PM for FMD in a difficult velopment nature, and that insufficient numbers of
position with the client. full-time technical staff worked on the project at any
By contrast in PBD the heavyweight PM had given time. Most individuals worked on more than
direct control over resources and team personnel, as one project Žsome as many as six. and few, apart
well as a strong and direct representation into senior from the PM, felt any identity with Project F. Some
management Žthe company directors.. The PBD PM team members were under great pressure and two
for project P was more senior to other staff in PBD resigned from the company, partly due to the de-
and on equal terms with functional managers in mands of Project F.
882 M. Hobdayr Research Policy 29 (2000) 871–893

As one Senior Engineer on Project F stated: negotiate full costings or rescheduling, or to carry
AThere was not enough team spirit partly because of out the detailed internal planning needed. This had
all the politics between different people in the vari- resulted in unclear business relations. Conflicts de-
ous departments. Most of the team worked on sev- veloped as team members felt their customer was
eral other projects. They were in and out.B And from unwilling or unable to divulge essential information
a different perspective: AI had no feeling of owner- on detailed requirements or to sign off pieces of
ship, neither did the other team members. Jim wthe work when requested to: AThey wthe customerx inter-
PMx was running the project using resources pro- fered far too much with the design. They argued
vided from the departments as and when. It should about every single nut and bolt. They set the pattern
have been handled differently from the outsetB ŽElec- of being able to dominate the design and make us
tronics Engineer, Project F.. The PM concurred with take the risk. This eventually led to the point where
these views adding: AThe engineer responsible for the customer didn’t trust Jim wthe PMx.B ŽSenior
testing, where we had major difficulties, became Mechanical Engineer.. Similarly, Awe tried to get
overstressed and left the company. We managed to feedback from the client but we got no help. We
get a replacement from another division, who then decided it was better to be late on delivery than have
discovered serious technical problems with the sys- a system fail in the fieldB ŽPM, Project F..
tem, which had further knock-on affects.B Team members also felt let down by their own
Overall, the project suffered from weak team PM and senior management who did not seem able
coherence, poor team spirit, and fragmented commu- to sort out the difficulties. To them, seemingly arbi-
nications. This was due in part to initial project trary changes in specification were called for causing
under-resourcing, itself a reflection of the weak bar- delays in delivery and severe technical difficulties:
gaining position of the PM who was unable to insist AThe specification was not properly dealt with. The
upon a dedicated team within the functionally-ori- company was afraid to talk to the customer. You
ented organisational structure. These problems were need a high level PM from a business point of view
seen as resulting from the functional structure and on this type of project. Jim wthe PMx was down on
had occurred before in CoPS projects in FMD, lead- the shop floor fire fighting too muchB ŽManufactur-
ing to the decision to consider introducing a PBO ing Technician, Project F..
structure similar to PBD. However, official client procedures and be-
By contrast, in PBDrProject P the team felt they haviours on FMDrProject F were not dissimilar to
had achieved a highly effective and professional those of PBDrProject P, coming from a different
approach to project management and implementa- division of the same buyer organisation. FMDrPro-
tion, with strong team coherence and close identity ject F team members reacted defensively to client
with Project P. Most of the team were dedicated to demands, putting problems down to internal cus-
Project P and all felt allegiance to it. Project leader- tomer politics and commercial inexperience on the
ship and management were viewed as strong by team client’s part. Project F members perceived requests
members and internal communications proceeded for changes as the placing of unreasonable demands
well. on the project team who were already stretched and
under-resourced.
In the absence of clear ‘rules of engagement’,
4.5. Client and client management expectations on both sides of FMDrProject F were
difficult to manage and potential risks materialised to
The FMDrProject F team had developed poor the detriment of the project. Team members felt that
and confused relations with their client and felt the responsibility for dealing with these issues rested
‘unlucky to have a bad client’. Early on in the with the various functional managers Že.g., manufac-
project’s development, the PM had reacted to new turing for delivery, finance for costs, and engineering
client demands for changes in specification by at- for specification changes., while some senior func-
tempting to please the customer. However, the PM tional managers felt that the PM should have dealt
did not have the time nor authority to carefully with these problems or highlighted them earlier. All
M. Hobdayr Research Policy 29 (2000) 871–893 883

agreed that client relations were difficult and unclear. As a result, Project P team members felt that rela-
A draftsman on Project F summed this up: AWe need tions with the client were orderly and understood.
better contracts and better specification procedures.
We have them internally but we don’t have them 4.6. Risk management
with the customer. We’re too soft on the customer
— we accept costs to us too easily and lose money. Regarding risk, three types of risk were identified
Being a big project, it exposed weaknesses in our in both divisions: Ža. those wholly outside the con-
approach.B trol of the project Žexternal.; Žb. those wholly within
By contrast, PBDrProject P members felt that the ambit of the project Žinternal.; and Žc. risks
they were fortunate to have a ‘good client’, who was subject to negotiationrinternalisation Žnegotiated
willing to entrust design and development decisions risks..
to them. This was partly due to the involvement of In FMDrProject F, the PM was unable to estab-
PBD engineers in an early design study for the lish a pro-active approach to risk, particularly in
client, which specified some of the system. How- relation to risks inherent in customer–supply rela-
ever, the team had also developed a shared business tions Že.g., major changes to specification., common
‘negotiation’ mentality, now common in PBD. This in CoPS. Organisationally, the PM felt he Awas
assumed, for example, that any requests for changes being torn limb from limbB by the various demands
to specification had to be negotiated between the PM of the functional bosses, unhappy team members and
and the client, fully costed and, if necessary, re- the client. As a result, the PM was unable to estab-
flected in extended delivery schedules: AWe have lish an orderly business framework for managing
very good client relations but if they want to make client relations from the outset. Failing to meet
changes wto the specificationx we stop the clock, and changing needs, the project team had developed
price it.B ŽEngineer, Project P.. defensive relations with the client. The team mem-
Although this approach had developed informally bers were unable to manage internal and external
in PBD Žno explicit systems or detailed contractual risks well, and allowed negotiated risks to emerge.
arrangements existed over and above those in FMD., Because of the lack of team coherence and resources,
the negotiated approach had become standard prac- the PM and senior engineers were unable to regu-
tice because it helped meet the needs of engineers, larly visit the customer or key suppliers to avoid
especially when confronted with large complex pro- risks Že.g., delays in the delivery of sub-systems..
jects where frequent iterations with the client were Because management systems Že.g., internal design
needed. The rules Že.g., on specification changes. reviews. were not carried out regularly, as they
were alluded to in the contract Žas in the case of should have been, problems of risk were intensified
FMDrProject F. but also, and more importantly, by the failure to share information either in formal or
communicated through the ‘tone’ of day-to-day informal meetings.
channels of communication at all levels of the pro- By contrast, partly due to its tightly integrated
ject. This, in turn, required team ownership of the project structure, PBDrProject P members managed
project and good internal communications. By estab- internal and external risks well, and increased their
lishing project ground rules at the initial bid stage, control over negotiated risks. The PM and senior
changes to design, day-to-day misunderstandings and engineers paid regular visits to key suppliers and
other uncertainties could be dealt with in a system- helped to resolve delays in the delivery of compo-
atic professional fashion. nents and sub-systems. Referring to sub-contractor
In PBDrProject P, most of the liaison with the relations, as one senior engineer on Project P said:
client was carried out or co-ordinated by the PM AYou have to spend a lot of time on this. I went
who was able to build a good working partnership. through 19 different suppliers to find two or three
As the project progressed, more team members be- really good ones. You pay them a visit and ask
came involved directly with the client as the PM questions. It usually takes one min to tell whether
entrusted particular team members, at various stages, they are good or not. And it’s nothing to do with
to take actions with members of the customer’s team. firm size — some of our best suppliers are small
884 M. Hobdayr Research Policy 29 (2000) 871–893

companies.B The team avoided risks by sharing in- for the early bid stage, internal design reviews, re-
formation in their formal two-weekly review meet- porting to senior management, cost tracking and
ings, informal meetings and conversations, and regu- control, progress monitoring, and risk management
lar client and customer visits. were officially in place but were not applied. This
The business approach made possible by the ‘su- was put down to the absence of a coherent team,
per heavyweight’ project structure, allowed under-resourcing, time pressures, weak incentives for
PBDrProject P to deal with two major sources of team members Žwho reported to functional bosses.,
external risk Žsupplier and client relations., allowing and the ‘firefighting’ mode of the PM and team
space for dealing with unexpected events and scope members: Athere were no internal design reviews
for internalising negotiated risks. The Project P team held to ask ‘are we doing the right thing’. This was a
felt pleased with the informal way most problems very large complex project. Jim wthe PMx was dropped
were handled, the only formal risk management tools right in it with no commercial backupB ŽMechanical
being a two-page weekly reporting form and the Engineer, project F..
two-weekly project meetings. In the event, despite While Project F was a fairly extreme case, the
some problems, Project P progressed well and was divergences between formal and actual procedures
delivered on schedule, but slightly over budget Žsee occurred in other CoPS projects in FMD. Tools and
Section 4.9.. reporting were seen as an added bureaucratic burden,
On the negative side, senior management at Com- unhelpful in the managing of the project.
plex Equipment Inc felt that they Adid not really By contrast, in PBDrProject P the PM was in
know enough about PBDrProject PB, given its im- charge of implementing company tools and proce-
portance as a new product line for the company as a dures. The ‘leanness’ and flexibility of formal tools
whole. This had also been the case for other projects and systems within PBD, which involved no func-
carried out in PBD. The lack of regular reporting tional reporting or negotiating with departmental
into senior management created some tensions be- bosses, meant that tools and procedures were seen as
tween project progress and corporate-wide strategies helpful in getting tasks completed, although again
and goals. Company directors felt a degree of project there were some differences between official proce-
isolation in PBD had created risks in terms of overall dures Žwhat should have been. and real practices
marketing strategy and business coordination. Their Žwhat actually went on., particularly in terms of the
solution Žsee below Section 4.10. was to set up more informality in the use of tools. Some tools were
regular reporting with PMs along the lines of FMD. deployed very sparingly indeed and there were dif-
ferences in the ways PMs within PBD used company
4.7. Formal and informal tools and procedures tools and followed procedures.
Informal methods, experience, and trust were
Both FMD and PBD had fairly typical tools and viewed as more important than tools and formal
systems mandated by the company for bid review, procedures on Project P: AThe fancy 3D CAD tools
cost, and risk management, internal design, and spec- are really ‘boss dazzlers’. The main thing win project
ification change management. In both organisations, successx is delegating the right tasks to the right
there were formal systems for project recording, people and keeping in close touch. I use my imagina-
controlling, and reporting. In FMD, detailed proce- tion. I sketch things out in order to work out the best
dures were laid down by the functional departments, way of doing the job before doing the detailed
each with their different goals and needs, leading to design. We have a process manual but it doesn’t help
a heavy administrative load for FMD projects. with detailed design problems. Its experience that
In FMDrProject F, actual procedures followed mattersB ŽSenior Engineer — Project P.. Similarly, a
Ž‘what happened in practice’. diverged considerably veteran engineer working on the detailed design of
from formal tools and company best management Project P explained: AYou go down some routes,
practices Ž‘what should have happened’., as reflected abandon others, create new ones and so on. You
in senior management views and contained in a have to proceed even though the next steps are often
company toolbook and quality manual. Procedures uncertain.B
M. Hobdayr Research Policy 29 (2000) 871–893 885

PBD managers, over the past 2 years, had modi- in FMD by functional departments. were absent in
fied and simplified company tools and systems to PBD’s pure PBO.
suit their project needs and successfully resisted the The PPR was viewed by the company as an
introduction of more elaborate formal management important mechanism for learning from project-to-
tools and systems. project. The official procedure called for a PPR
involving all major project contributors, from the bid
4.8. Organisation-wide learning and coordination stage onwards. The PPR should have operated in
PBD as a mechanism for capturing lessons Žgood
In FMD, organisational learning Žinvolving infor- and bad., sorting out problems Že.g., closing the loop
mal knowledge sharing, training, reviews, personnel between bid stage decisions and project outcomes.,
development, and technical leadership. was centred and building up wider company communications Žin-
on the functional departments. In this area FMD as a volving project outsiders and senior managers..
whole performed well. Younger engineers felt that However, few PPRs had occurred in the past 2 years
they had good overall technical leadership from the due to work pressures and the lack of structure and
senior engineers and functional managers. They could incentives within PBD. Internal markets had devel-
see a career ladder within the organisation. Senior oped for good people and the most persuasive and
engineers had incentives and resources to recruit, senior PMs often get them, sometimes leading to a
train, and retain new younger engineers and techni- skewed performance among projects.
cians for their departments. Much of the knowledge At least three other problems of learning and
sharing and communications occurred in informal coordination were evident in PBD. The first con-
settings although there were also training pro- cerned technical leadership. In FMD, this role was
grammes and official seminars and meetings. Infor- played by senior engineers and department man-
mally, groups of engineers exchanged tacit knowl- agers. Younger and newer recruits in PBD were
edge and problem-solving tips through narratives, in concerned over career development and professional
what is sometimes called communities of practice progress because of the dispersion of technical lead-
ŽSeeley Brown and Duguid, 1996.. In this important ership across projects. Insecurity was highest to-
area, FMD out performed PBD. wards the end of a project when staff were not sure
In PBD, despite very good individual project per- ‘where they would go to next’. Related to this was
formance, in the previous two years the high pres- the lack of incentives for human resource develop-
sured work environment had left little space for ment. The PBD structure had reduced the incentive
formal training or staff development, either in techni- for senior engineers to bring on younger engineers as
cal or commercial areas. It was apparent that many they had previously done under the functional matrix
of the formal and informal activities associated with as a fairly natural thing to do. In FMD there were
organisational learning, and improvement Že.g., concrete incentives to groom young staff to improve
post-project reviews ŽPPR., technical mentoring, and the performance of various departments, but these
informal communications. were not being per- incentives did not exist in PBD and no senior indi-
formed: ASince we became project-based, I’ve had viduals had responsibility for this task. The func-
no incentive or time to train anyone up. Previously I tional departments served this role in PBD allowing
always looked after two or three younger engineers. space Žand time. for the sharing of knowledge and
In the old wfunctionalx organisation we had space for experience.
training and staff development.B ŽVeteran design A second problem was revealed in some of the
engineer, Project P.. small projects undertaken in PBD. While the organi-
Lessons learned from particular projects were not sation was suited to large complex projects, it was
shared formally because there were no structures or overly elaborate for dealing with small routine pro-
incentives for cross-project learning or communica- jects: ‘using a sledgehammer to crack a nut’ as one
tions. It had become hard to learn from project-to- engineer put it. In particular, there was no real need
project, leading to worries within PBD over its long- for a senior PM and a dedicated team to control
term effectiveness. The learning ‘silos’ Žrepresented smaller, especially more routine projects. Treating
886 M. Hobdayr Research Policy 29 (2000) 871–893

smaller projects ‘as if’ they were major projects had small projects and more standard product lines. In
led to heavy overheads and too much bureaucracy in scaling up from simpler to more complex products,
some cases. the organisation needed a heavier PM structure with
A third problem concerned cross-project integra- direct representation into senior management.
tion and senior management coordination and con- By contrast Project PrPBD was considered to be
trol. Some major projects had ‘gone their own way’ a major technical success and delivered ahead of
in PBD and it had become difficult for senior com- schedule. However, as noted earlier, the project was
pany managers at HQ to keep properly informed and completed slightly over budgeted costs, and with a
maintain some degree of control and consistency lower level of profit than expected. The costs of two
across the activities of PBD. Systems had come to sub-systems had been under-estimated. Neither sub-
vary somewhat from project-to-project, as PMs exer- systems posed special technical or supply challenges,
cised their discretion over which tools to apply and but one probable cause was the informality of PBD’s
how to apply them. The basic minimum of formal bid stagercosting process. Team members felt that a
controls Že.g., for risk management, cost, and design slightly more systematic bid process involving more
review. were not always adequately applied, as hap- specialists from other projects would have helped
pened in the case of PBDrProject P at the bid stage. avoid bidrcosting problems. Also, despite good rela-
Overall, senior management felt that control of PBD tions with suppliers, the delivery of some items was
had become difficult, especially as the organisation late. These problems were dealt with by visits to
had grown. supplier sites by the PM and senior engineers and
risks to the project schedule were averted. Again, the
4.9. Project performance team felt that a little more formality in dealing with
suppliers could have avoided some of these prob-
In FMDrProject F, the initial underestimation of lems.
costs produced a knock on effect throughout the Overall, problems on Project P were fairly minor
project, leading to under-resourcing and, in particu- and both the senior management and the customer
lar, insufficient full-time staff. As a result, there were pleased with end results. However, there were
were major technical problems, the project came in wider concerns about long-term learning and techni-
substantially over cost and delivery was late. Both cal developments as discussed earlier.
the client and FMD’s senior management considered
Project F a failure. 4.10. Organisational strategies and solutions
There were various causes of the poor perfor-
mance. In FMD, PMs did not report directly and In order to overcome the ‘mismatch’ between
regularly to the senior management team to share organisational structure and the needs of large pro-
problems, responsibilities and so on. In Project F, jects, FMD’s management decided to move to a
this led to the initial under-resourcing, which pre- heavyweight project matrix structure, maintaining a
vented both team-building and the development of a functional matrix for standard lines Ža move from
good team spirit. It was also difficult to rectify the ‘B’ to ‘D’ in Fig. 1 above.. The difficult task of
problem later, given the PM’s relatively low status in allocating resources between functions and CoPS
the organisation. FMD lacked the clear processes and projects was to be undertaken at senior management
procedures needed for controlling large complex pro- level, with project directors responsible for negotiat-
jects. The way the project was managed exacerbated ing for and controlling resources. Deploying a
problems with the customer and placed unreasonable heavyweight project structure for CoPS was viewed
demands on team members. Because team coherence as more suitable than either the existing functional
and commitment were low, risks materialised, and matrix or the pure PBO, given the need to cope with
problems were difficult to address. All in all, the large numbers of standard items. For major projects,
functionally-oriented structure of FMD was not suited heavyweight PMs would report directly into senior
either for the setting up or execution of CoPS pro- management on a regular basis at the same level as
jects. The heavy functional bias was appropriate for the functional managers.
M. Hobdayr Research Policy 29 (2000) 871–893 887

Recognising the burden placed on PMs in CoPS, standard PM tools and procedures Že.g., for schedul-
FMD also decided for very large projects to split the ing, team-building, bidding, cost control, risk man-
PM function into two with a commercial PM and a agement, and negotiation methods., along the lines
technical project engineer ŽPE., a practice followed also being followed by PBD. Regarding tools and
in some projects in PBD. The rationale was to procedures, it was decided not to introduce highly
increase the scope for negotiating with the client elaborate PM tools Že.g., for risk management, de-
ŽAgood guyrbad guyB androther routines. and to try sign walkthroughs, and cost control., following the
to overcome the need for PMs ‘with a super-human lessons of PBD. However, as with PBD, minimum
range of talents’ as one director put it. The PM formal processes were mandated. For example, risk
would have overall business control of the project, management was being built into the design review
including client relations, progress schedules, tools process so that problems could be communicated,
and procedures, team meetings, and so on. The PE, discussed and shared among project staff.
of equal status to the PM, would be responsible for Given the composition of FMD, most PMs would
all technical issues, including specifications, detailed be engineers or scientists who had demonstrated the
design, construction, sub-system interfacing, and so aptitude, skills, and desire to be PMs. People with
on. The PE would deal with the client on most flair in this direction were to be encouraged and
technical issues, but would avoid commercial deci- rewarded to undertake commercial PM responsibili-
sions, leaving these to the PM. ties, sometimes alongside their technical careers.
Reflecting on Project F, the Žthen. PM said: ATo- Alongside the new structure, much more attention
day a project like that would have a dedicated team would be given to developing a systematic, profes-
of full-time engineers and a full-time PM. We learned sional approach to managing client relations and
a lot from that project wFx. Big projects with a needs, including training in how to establish a busi-
development side must be handled differently, with ness framework, manage expectations, and negotiate,
different professionals in charge of technical work again along the lines of PBD. Complex and changing
and commercial issues. We now have a project-based clients needs are not unusual in CoPS; therefore, a
structure for all big projects where people can move pre-emptive, pro-active approach is essential to min-
in and out of teams.B imising risks.
The dual PMrPE system has both advantages and Turing to the case of PBD, to address the organi-
disadvantages. For the system to work effectively, sational learning problem, PBD’s management de-
the PM and PE have to be willing and capable cided to establish a programme to build space for
partners, able to share in strategy, decision-making, learning, training, staff development and PPRs, and
and team-building. In some organisations, the system to make time to reflect on important technical and
becomes accepted as the natural way of doing busi- business issues Že.g., new technical developments,
ness. Sometimes, but not always, the PM is also an project lessons learned, time management and cross-
engineer Žeither practising or by background.. Re- project design reviews.. To promote the long-term
gardless of background, the PM is responsible for productivity and effectiveness of PBD, younger team
mastering all the skills of managing projects effec- members would be encouraged to learn from more
tively and efficiently. In some companies, the PM experienced staff and to share in some of the ‘tacit’
organises commercial training for other team mem- knowledge, locked up in the heads of otherwise
bers Že.g., on negotiation skills, new tools, and risk busy, more experienced people.
and time management.. Although learning went on informally at the sin-
In addition, the PM function was to become more gle project level, PBD decided to structure and en-
professionalised in FMD, not only through training able learning to occur in more formal, cross-project
but through the fostering of a commercial PM ethos, settings Že.g., regular cross-project meetings, project
which values and rewards PMs. Courses on team- management workshops, off-site training and special
building and project management were being ar- technical seminars with outside speakers.. To ensure
ranged, while individuals were being encouraged to this occurred, PBD put specific people in charge of
engage in various PM associations and introduce coordinating particular themes and programmes
888 M. Hobdayr Research Policy 29 (2000) 871–893

across projects, forming a weak functional line across and match the needs of large projects with organisa-
the major projects of the unit. Other functional tasks tional structure, which the project-led organisation is
were being considered to help coordinate sub-con- formally designed to do.7
tractor relations and risk management procedures.
The aim was to ensure consistency in project ap-
proaches, to share best practices more widely and to 5. Managing CoPS in PBOs — interpretation
keep senior management at HQ better informed This section draws analytical lessons from the
through improved reporting procedures. This case study, interpreting the evidence in relation to
amounted to a step ‘back’ to a project-led organisa- project coordination for CoPS. The aim is to provide
tion, but fell short of a project matrix Ža shift from a framework for interpreting the various organisa-
‘F’ to ‘E’ in Fig. 1.. tional choices and strategies available to foster inno-
To provide incentives for senior people to give up vation in high technology capital goods, networks,
project time Že.g., to bring on new recruits. a formal constructs, and systems.
mentoring programme was set up with incentives for
good performance. PBD also restructured desk lay- 5.1. Interpreting the organisational strategies of PBD
outs and coffee spaces to enable more informal and FMD
communications to occur. Senior management recog-
As noted above, FMD was initially a Type B
nised that moves in this direction depended on more
organisation Žsee Fig. 1., but this led to extreme
resources being made available and some degree of
problems in project management and coordination
organisational slack in the system. However, the
both internally, and externally with the client and
high good performance and profitability of PBD
suppliers. In response to the problems, FMD decided
justified this long-term investment in learning.
to convert to a project matrix ŽType D. with a
Whether or not these formal organisational solu-
heavyweight PM structure in order to allow CoPS to
tions to the problems of organisational learning and
be managed more effectively within the organisation.
career development work effectively remains to be
However, it did decided not move to a PBO
seen. It is possible that moving a step back to a
ŽType F., in order to retain the functional depart-
project-led organisation and establishing resource and
ments needed for standard product lines and batch
task coordination may not solve the problem. Ulti-
production. The difficult task of allocating resources
mately, the success of the approach adopted depends
between functions and CoPS projects could then be
on taking senior Žand other. staff away from project
resolved by functional and PMs of equal status, with
work, which could, of course, be resisted by the PMs
their senior management Žin this case company direc-
who are in a powerful position and could potentially
tors.. The directors favoured this arrangement be-
prevent ‘interference’ with project operations. In-
cause the emerging CoPS were important new busi-
evitably, this kind of solution introduces its own
ness opportunities and needed to be understood and
tensions into the organisation, in this case pitting
supported at the highest level. Regular, direct feed-
shorter-term project needs against wider organisa-
back on the progress of these projects was vital to
tional needs. A key factor in whether or not the new
the company.
programmes and structures work effectively is the
By contrast PBD, organised as a Type F pure
health and dynamics of informal organisational struc-
PBO, had achieved a very good record at the individ-
tures and practices which, in turn, reflect the particu-
ual project level, but the overall organisation was
lar culture of a company. As shown by Pisano and
concerned for its long-run performance in areas such
Wheelwright Ž1995., informal, personal, and cross-
as technical leadership, organisation-wide learning
departmentrdivisional relationships play a vital role
and communications. PBD’s response was to move
in ensuring any official form of organisational struc-
back from a pure PBO to a project-led organisation
ture works effectively. Nevertheless, although there
can be no ‘mechanistic’ structural solution to prob-
lems of organisational learning, it is wise to adopt 7
The effectiveness of the formal solution adopted at Complex
structures and formal practices that promote learning Equipment Inc is an interesting subject for further research.
M. Hobdayr Research Policy 29 (2000) 871–893 889

ŽType E. in which PMs retain the most senior posi- monitor, and improve performance across the whole
tions but appoint new resource coordinators along organisation.
functional or generic task lines which cut across
project interests and incentives. This strategy was 5.2. From linear to concurrent models of project
adopted in PBD to stimulate organisational learning management
and to provide incentives and resources for greater
technical leadership. In PBD task force managers To illustrate the management advantages of the
could resolve specific problems and help coordinate, PBO for CoPS, Fig. 2 contrasts the PM task within a

Fig. 2. Comparing project management in functional and project-based organizations. ŽA. Functional matrix. ŽB. Project-based organization
Žinternal coordination.. ŽC. Project-based organization Žexternal coordination..
890 M. Hobdayr Research Policy 29 (2000) 871–893

functional matrix with the weak PM structure ŽType sents a shift from the linear model of project man-
B. deployed in FMD, with that of a pure PBO ŽType agement, which treats the user and other innovation
F. deployed in PBD. Fig. 2A shows the position of actors as ‘outside bodies’, to a concurrent model of
the weak PM within the functional matrix, involving project management which is able to integrate all the
multiple lines of communication, control and com- business functions within the project and includes
mand, and various department managers. users and suppliers in the core project processes. For
The PM function embodies a linear or sequential CoPS projects, the concurrent model is potentially
model of project management, in which the project very helpful in dealing with uncertainty, risk and
passes through various stages and departments in emerging properties common in CoPS.
turn. The model also treats the client and suppliers as
external to the project. The PM has to perform a 5.3. Economic motiÕations and determinants
highly complex internal task of balancing the various
internal interests and meeting the different demands Underlying the advantages and disadvantages of
Že.g., in terms of reporting and quality control. of the the two organisational form are economic motiva-
departments. Similarly, there are many lines of com- tions and determinants.8 In theory it would be possi-
munication with team members on the project who ble to mass produce consumer goods such as cam-
also report Žprimarily. to departmental managers to corders or hi-fi equipment in a PBO, rather than a
whom they owe their career allegiance, and to other functional organisation. Similarly, it would also be
PMs Žsome in FMD worked on four or five projects.. possible to produce a large CoPS Že.g., a power
PMs face similar complexities and difficulties in station or a flight simulator. in a functional organisa-
external coordination. To reply to customer requests tion. However, in both cases, the costs of production
they often have gain information and commitments would be far higher than if the more appropriate
from engineering, purchasing, and planning depart- organisational form had been adopted.
ments. The larger and more complex the project, the In economic terms, the large functional Chandle-
more difficult the task of keeping the client informed rian firm is most effective at achieving production
and responding to requests for changes from the scale advantages and exploiting economies of scope,
customer. systematically converting lower value inputs into
By contrast, Fig. 2B shows the position of the PM higher value outputs. However, these economic
in a PBO in relation to the specialist functions within drivers are largely irrelevant in CoPS production,
the project. The PM is the main line of communica- because the latter are produced either as one-offs or
tion and can exercise control to coordinate and inte- small-batch items. Therefore, efficiency gains must
grate specialists and functions in creative new ways, come from other sources, centred on other forms of
focusing on the needs of the project. Because there organisation. The PBO, with its focus and flexibility,
are few internal lines of command and communica- in theory and in contrast with the functional form,
tion to interfere with project objectives, the internal can achieve economies of: Ža. resource allocation —
coordination task becomes simpler and clearer. allocating and re-allocating physical and human re-
Similarly on the external front, clear strong lines sources when and where they are needed to each
of command and communications can be built up project; Žb. knowledge management — applying the
with the client ŽFig. 2C.. In principle, the PM is able know-how needed to deal with the technology, as
to quickly assess and react to change in client needs well as regulator and client needs; Žc. design optimi-
and learn from feedback from the client and major sation — enabling design cycles to be carried out
component suppliers. The PM has both the responsi- effectively and efficiently by reducing the number of
bility and power to react to unexpected events, nego- designrredesign cycles Žand costs. associated with
tiate changes with the client and, if necessary, put
suppliers of major components together with the
customer to resolve difficult problems.
In effect, the PBO embodies a concurrent model 8
This section draws heavily on ideas and comments provided
of project management. The move to a PBO repre- by Paul Nightingale ŽSPRU..
M. Hobdayr Research Policy 29 (2000) 871–893 891

additional cycles, caused in CoPS by backward feed- functional form. Realising a CoPS is often a creative
back loops from later to early design stages; and Žd. and difficult task, involving feedback and learning as
quality — enabling the organisation to produce a the project develops. CoPS not only require innova-
complex good to the exact specification and needs of tion at the product level but also at the process and
the buyer. Its inability to achieve such economies, organisational levels. Design and production involve
indicates that the functional form is economically many knowledge-intensive, non-routine tasks, and
wasteful as a form of production for one-off projects. decision-taking under conditions of uncertainty and
As shown above, the PBO can also assist in risk. These intelligent processes cannot be reduced to
managing risk and uncertainty, especially important routine project management procedures and plan-
in the many CoPS which exhibit emerging properties ning. Learning during production is required to as-
Žunforeseen and unforeseeable features which occur similate the knowledge required to complete the task
during design, systems integration and production. of production.
ŽHobday, 1998.. Given that formal planning is lim- Because each CoPS is different, the innovation
ited in its ability to deal with design and production needs of the product frequently demand experimenta-
unknowns, then the devolved decision-making al- tion in forms of project management. In short, pro-
lowed by the PBO enables a flexible allocation of ject-level innovation is required to produce innova-
resources to alleviate these problems when they tive products. Because the PBO creates and recreates
emerge. Furthermore, the nature of the CoPS project organisational structures and processes around the
task often changes as clients realise new needs dur- needs of each product and customer it is, in princi-
ing the design and production phases, especially in ple, a highly innovative form. Again, in theory at
very high value CoPS where production may take least, the PBO defies the anti-innovation bias of
two years or more. The PBO, in theory, allows the large functional organisations with their semi-perma-
swift transfer of information to relevant teams and nent departments and consequent core rigidities.9
team members who are then in a position to adapt The challenge of managing innovative CoPS projects
their activities and respond to new contingencies. is one of integrating business functions, ensuring
In short, the functional Chandlerian organisation flexibility and responsiveness to the needs of cus-
is appropriate for the mass production of known tomers, and dealing with the emerging properties
products with known processes, where the key task which inevitably arise in complex products which
is to optimise the production system in order to embody new knowledge. It is also a challenge of
transform large quantities of lower value inputs into thinking beyond current market and product needs to
large quantities of higher value outputs, by reducing anticipate future needs and especially to convince
unit costs. These economies are essentially scale- buyers of the firm’s competence to deliver further
based. By contrast, each CoPS product and process new CoPS.
involves uncertainty. Economies in production come
from reduced design cycles and efficient systems
integration, made possible by the flexible and effi- 6. Conclusion
cient allocation of knowledge and resources to each
good being produced. Therefore, in CoPS, as in Using a case study approach, this paper has com-
mass-produced goods, economic advantages are pared the efficiency and effectiveness of the func-
rooted in appropriate organisational form. The PBO, tionally-oriented, matrix organisation with the PBO,
in principle, is an appropriate organisational form for pointing to both the strengths and weaknesses of the
the technological and market environment of CoPS, PBO in the management of CoPS. On the positive
allowing for efficient project control and resource
coordination. 9
In practice, of course, the PBO form may not live up to its
5.4. InnoÕation adÕantages of the PBO innovative potential. Indeed, some project-based sectors are noto-
rious for failing to learn and innovate Že.g., construction.. Realis-
Beyond the economic advantages of the PBO, ing the innovative potential of the project-based organisation is a
there are dynamic innovation advantages over the key challenge for management.
892 M. Hobdayr Research Policy 29 (2000) 871–893

side, the PBO has the potential to foster innovation success and efficiency, although important, does not
and promote effective project leadership across the necessarily enable a firm to continue to execute
business functions. As resources, technical and other, projects successfully. Indeed, the case study revealed
are formally dedicated to the project, both power and a problem of ‘learning closure’ around major pro-
responsibility for project success lie with PMs. The jects, as there were no structures or incentives in the
latter, who tend to be ‘super heavyweight’, can focus PBO for cross-project learning or communications.
on team-building, meeting the clients needs, dealing The learning silos, represented by functional depart-
with technological uncertainties and making a suc- ments, are absent in the pure PBO. As a conse-
cess out of the project. By contrast, the functional quence, PBOs can suffer from a lack of technical
matrix is poorly equipped to coping with the needs leadership and direction, roles typically played by
of CoPS projects. engineering and R & D managers in functional and
Along the spectrum of six functional-to-project- matrix organisations. PBOs can also breed insecurity
based forms, the paper showed that the PBO is an over career development, especially among new re-
extreme form, having no functional division of labour cruits because of the dispersion of technical leader-
or task coordination across project lines. All major ship across projects. By contrast, functional depart-
business functions, including marketing and finance, ments provide space Žand often time. for the sharing
are coordinated within the project. The PBO is prob- of knowledge and experience. In short, the PBO is
ably best suited for large, risk-intensive projects, inherently weak where functional forms are strong:
where resources have to be combined and shared in executing routine production and engineering
with other firms in the project. Because of its flexi- tasks, achieving economies of scale and meeting the
bility and focus the PBO form is able to cope well needs of volume production.
with the emerging properties of CoPS by responding Cross-project integration and management control
to client needs in real time. The case example showed can also become a problem in PBOs if projects ‘go
why the PBO form was more effective than the their own way’. Systems may come to vary from
functional form in integrating different types of project-to-project, as PMs exercise a high degree of
knowledge and skill, learning within the project discretion over which tools to apply and how to
boundary and coping with project risks and uncer- apply them. It may become difficult for senior man-
tainties. While the functional matrix embodies an agers to track, control, and respond to the activities
inward-looking, linear form of project management, of project teams and directors, limiting the firms
the PBO embodies a concurrent model of project overall capacity for effective corporate strategy and
management which is able to realise innovation in business coordination. To be most effective the PBO
collaboration with clients and suppliers. requires that projects are coherently directed towards
Because CoPS tend to be major new business company-wide market and technology targets.
endeavours, simultaneous product, process and or- The case example identified various strategies for
ganisational innovation is required. The PBO is po- dealing with PBO weaknesses, particularly the prob-
tentially an effective form because it creates and lem of project isolation. To improve coordination in
recreates new organisational structures around the areas such as overall company strategy, regular re-
needs of each product and each major customer. porting channels into company directors were set up.
Unlike functional departments, the PBO is temporary To enable and encourage organisational learning,
and is, therefore, not subject to the anti-innovation cross-project communication and technical leader-
bias of functional organisations with their rigid de- ship the company moved one stage back from a pure
marcations and core rigidities. As Section 5 shows, PBO to a project-led organisation. In this arrange-
potentially, the PBO boasts significant economic ad- ment PMs retain their senior positions but new re-
vantages over the functional form in the production source and task coordinators along functional lines
of CoPS. are appointed, cutting across project interests and
On the negative side, the PBO is inherently weak incentives, in order to resolve specific problems and
in coordinating processes, resources and capabilities help coordinate, monitor, and improve performance
across the organisation as a whole. Individual project across the organisation and a whole.
M. Hobdayr Research Policy 29 (2000) 871–893 893

This move back from a pure PBO to a project-led Hobday, M., Rush, H., 1999. Technology management in complex
organisation shows the variety of choices involved product systems ŽCoPS.: ten questions answered. International
Journal of Technology Management, Special Issue: ‘Emerging
and the need to match organisational form with the Trends in Technology Strategy Development’, forthcoming.
product mix in question. More generally, the paper Katz, R. ŽEd.., The Human Side Of Managing Technological
indicates that the changing nature, composition, and Innovation: a Collection Of Readings. Oxford Univ. Press,
scale of productrs have an important bearing on New York.
appropriate organisational forms. The management Larson, E.W., Gobeli, D.H., 1987. Matrix management: contradic-
tions and insights. Californian Management Review 29 Ž4.,
challenge facing CoPS producers is both to realise 126–138.
the potential of project-based forms for current mar- Larson, E.W., Gobeli, D.H., 1989. Significance of project man-
kets, and to develop the firm’s overall capabilities to agement structure on development success. IEEE Transactions
exploit and create future market opportunities. on Engineering Management 36 Ž2., 119–125.
Lemley, J.K., 1992. The Channel Tunnel: creating a modern
wonder-of-the world, PMNetwork. The Professional Magazine
of the Project Management Institute, 14–22, July.
Acknowledgements
Leonard-Barton, D., 1992. Core capabilities and core rigidities: a
paradox in managing new product development. Strategic
This paper was prepared within the Complex
Management Journal 13, 111–125.
Product Systems Innovation Centre, supported by the Miles, R.E., Snow, C.C., 1986. Organizations: new concepts for
UK Economic and Social Research Council. The new forms. Californian Management Review 28 Ž3..
author would like to thank Paul Nightingale, Stefano Mintzberg, H., 1979. The Structuring of Organizations. Prentice-
Brusoni, Ammon Salter, Andrea Prencipe, Howard Hall, Englewood Cliffs, NJ.
Mowery, D., Rosenberg, N., 1982. The commercial aircraft indus-
Rush, Tim Brady, and two anonymous referees for
try. In: Nelson, R. ŽEd.., Government and Technical Progress:
comments on earlier drafts. The normal disclaimers a Cross-Industry Analysis. Pergamon, New York.
apply. Pinto, J.K., Covin, J.G., 1989. Critical factors in project imple-
mentation: a comparison of construction and R&D projects.
Technovation 9, 49–62.
References Pinto, J.K., Kharbanda, O.P., 1995. Lessons for an accidental
profession. Business, 41–50.
Brusoni, S., Prencipe, A., Salter, A., 1998. Mapping and Measur- Pinto, J.K., Prescott, J.E., 1988. Variations in critical success
ing Innovation in Project-based Firms. SPRU Mimeo, June. factors over the stages in the project life cycle. Journal of
Burns, T., Stalker, G.M., 1961. The Management of Innovation. Management 14 Ž1., 5–18.
Tavistock, London. Pisano, G., Wheelwright, S.C., 1995. High-tech R&D. Harvard
Clark, K.B., Wheelwright, S.C., 1992. Organizing and leading Business Review, 93–105.
AheavyweightB development teams. Californian Management Seeley Brown, J., Duguid, P., 1996. Organizational learning and
Review 34 Ž3., 9–28. communities of practice: towards a unified view of working,
Fleck, J., 1988. Innofusion or Diffusation? The Nature of Techno- learning, and innovation. In: Cohen, M.D., Sproull, L.S. ŽEds..,
logical Development in Robotics, ESRC Programme on Infor- Organizational Learning. Sage Publication, California, Chap.
mation and Communication Technologies. Working Paper Se- 3.
ries, University of Edinburgh. Shenhar, A.J., 1993. From low- to high-tech project management.
Galbraith, J., 1971. Matrix organizational designs — how to R&D Management 23 Ž3., 199–214.
combine functional and project forms. Business Horizons, Teece, D.J., 1996. Firm organization, industrial structure, and
29–40. technological innovation. Journal of Economic Behaviour and
Galbraith, J.R., 1973. Designing Complex Organizations. Addi- Organization 31, 193–224.
son-Wesley, Reading, MA. Walker, W., Graham, M., Harbor, B., 1988. From components to
Gann, D.M., 1993. Innovation in the Built Environment: the Rise integrated systems: technological diversity and integration be-
of Digital Buildings. Doctoral Thesis, SPRU, University of tween the military and civilian sectors. In: Gummett, P.,
Sussex. Reppy, J. ŽEds.., The Relations Between Defence and Civil
Gann, D., Salter, A., 1998. Learning and innovation management Technologies. Kluwer Academic Publishing, London.
in project-based firms. 2nd International Conference on Tech- Williamson, O.E., 1975. Markets and Hierarchies. Free Press,
nology Policy and Innovation, Lisbon, August 3–5. New York.
Hobday, M., 1998. Product complexity, innovation and industrial Woodward, J., 1958. Management and Technology, London. Lon-
organisation. Research Policy 26, 689–710. don, Her Majesty’s Stationary Office, London.

You might also like