MINUTES OF MEETING

Rhine Energy LLP, Manesar


Date :23 Jan. 2021

Present: Mr. Rakesh Gupta, Mr. Ramavtar, Mr. Keshav Bhardwaj (from RHINE)
Mr. Brijesh, Mr.Chirag, Mr. Chander ( from MAXBROS)
Next meeting: Friday 29th Jan 2021

1. Announcements
1. All designs developed & frozen except Type -1& Type-5.
2. Type-2 GAD approval given by Rhine To Maxbros. Hence, work on Type-2 has to start
immediately.
3. Type-4 sample has been inspected by the RHINE Team. Door Bulging to be addressed in
final assembly. The revision in Bottom sheet LT side shall be shared by Rhine by
25thJan.2021.
4. Components Dwg Files with stamp of Type-3, Type-4, Type-6, Type-7, Type-8, Type-9
are handed over to RHINE for approval & stamp, to be return to MAXBROS.
5. Special Components like partition sheets, Trafo- support, OLTC supports & any other
flexible components shall be intimated by Rhine in each Purchase Order in advance, this
shall be in .step file format.
6. Loading Fixture for safe loading of CSS to be developed.
7. All SS Hardware BOQ has been made separately for review.
8. On Every Friday there shall be a review meeting at MAXBROS/RHINE at 02:00PM for
ensuring smooth production & to address upcoming issues.

Sign.