a) $5.400 million
b) $5.036 million
c) $5.170 million
d) $3.620 million
2. Use the power-sizing model to estimate the cost of a piece of equipment that has 75% more
capacity than a similar piece of equipment that cost $1,000. The appropriate power-sizing
exponent for this type of equipment is 0.725.
a) $1,750
b) $725
c) $750
d) $1,500
3. Use a combined cost index and the power-sizing cost estimating model to estimate the
current cost of a piece of equipment that has 50% more capacity than a similar piece of
equipment that cost $30,000 five years ago. The appropriate power-sizing exponent for this type
of equipment is 0.8, and the ratio of the cost indexes (current to 5 years ago) is 1.24.
a) $29,760
b) $51,454
c) $55,800
d) $44,640
4. Use the cost index method to estimate the current construction cost for a building equivalent
to one constructed in 1980 at a cost of $2.7 million. According to the Engineering News-Record,
the 1980 average Building Cost Index was 1941. Suppose that the current year Building Cost
Index has been estimated at 3620.
INGENIERIA ECONÓMICA ACTIVIDAD DE APRENDIZAJE
5. Use the power-sizing model to estimate the cost of a piece of equipment that has 75% more
capacity than a similar piece of equipment that cost $1,000. The appropriate power-sizing
exponent for this type of equipment is 0.725.
6. Use a combined cost index and the power-sizing cost estimating model to estimate the
current cost of a piece of equipment that has 50% more capacity than a similar piece of
equipment that cost $30,000 five years ago. The appropriate power-sizing exponent for this type
of equipment is 0.8, and the ratio of the cost indexes (current to 5 years ago) is 1.24.