PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING

(EPCC) OF GAS DEHYDRATION PLANT AND DRY GAS PIPELINE FOR PETRONAS
CARIGALI IRAQ HOLDING B.V

INSPECTION TEST RECORD


Pipe Stringing Inspection Checklist QC-PL-0004
Project No. PCIHBV/2016/P&E/1469 Location/Facilities
Information
System ITP No.
Sub System RFI No.
Ref. Drawing No. Record No.
Inspection Date
INSPECTION / TEST
Inspection Conclusion
NO. Activity Remark
Ok N/A PL No
1 Ensure the pipe size, length, coating and condition are complied
with the specifications drawing.

2 Pipes shall be arranged at the side of pipe lining up of ROW.


3 Pipes shall be around 1.0 m away from the pipeline ditch bank.
4 Ensure that the pipes shall be assembled in a short time as soon as
possible during stringing in the gully and valley.

5 Approved pipe hooks, wire rope or slings kits were used for pipe
handling.

COMMENT(S) AND ADDITIONAL INFORMATION

COMPLETED BY VERIFIED BY ACCEPTED BY

Designation SCOP-PEG TPI PCIHBV Representative

Name

Signature