Professional Documents
Culture Documents
EUAC
EUAP(Equivalent Uniform Annual Payment)
EUAB
S (Salvage Value) The value of the equipment by the end of its useful service life
Dr. Abdelmagid A. Abdalla Lecture 4 11/12/2020 6
➢ Service Lives are Equal (Analysis period is the service life)
EXAMPLE 3.1
A firm is considering which of two mechanical devices to install to reduce costs in a particular situation.
Both devices cost $1000 and have useful lives of five years and no salvage value. Device A can be
expected to result in $300 savings annually. Device B will provide cost savings of $400 the first year
but will decline $50 annually, making the second-year savings $350, the third-year savings is $300 and
so forth. With interest at 7% which device should the firm purchase?
SOLUTION
Both devices have the same initial cost and the same useful service lives, so the problem is a fixed
input problem, and the objective of the economic analysis is to maximize the output.
PWB
300 ≡
Device A 0 1 5 0 1 5
𝟏+𝒊 𝒏 −𝟏 𝟏.𝟎𝟕𝟓 −𝟏
𝑷𝑾𝑩 = 𝑬𝑼𝑨𝑩 , PWB = 𝟑𝟎𝟎 =$1230.059
𝒊 𝟏+𝒊 𝒏 𝟎.𝟎𝟕 𝟏.𝟎𝟕 𝟓
Dr. Abdelmagid A. Abdalla Lecture 4 11/12/2020 7
G=-$50 PWB
400 ≡
Device B 0 1 5 0 1 5
𝟏+𝒊 𝒏 −𝟏 𝟏+𝒊 𝒏 −𝒊𝒏−𝟏
𝑷𝑾𝑩 = 𝒑ƴ + 𝒑" = 𝑬𝑼𝑨𝑩 +𝑮
𝒊 𝟏+𝒊 𝒏 𝒊𝟐 𝟏+𝒊 𝒏
𝟏.𝟎𝟕𝟓 −𝟏 𝟏.𝟎𝟕𝟓 −𝟓×𝟎.𝟎𝟕−𝟏
= 𝟒𝟎𝟎 𝟓 − 𝟓𝟎
𝟎.𝟎𝟕 𝟏.𝟎𝟕 𝟎.𝟎𝟕𝟐 ×𝟏.𝟎𝟕𝟓
=1640.078 – 382.333= $1257.745
The firm should purchase device B
NOTE : Both devices save $1500 during the 5 years period, but due to the concept of the time value
of money, the analysis shows that device B is preferable.
EXAMPLE 3.2
A city plans to build an aqueduct. It can be built at a reduced size now for $300m and be enlarged after
25 years for an additional $350m. An alternative is to construct the full-sized aqueduct now for $400m.
Both alternatives would provide the needed capacity for the 50-year analysis period . Maintenance
costs are small and may be ignored. At 6% interest which alternative should be selected ?
Dr. Abdelmagid A. Abdalla Lecture 4 11/12/2020 8
SOLUTION
Both Alternatives will provide the city with water for a 50-year period, i.e. fixed output problem, then the objective of the
analysis is to minimize the cost.
Alternative I 0 25 50 ≡ 0 50
350
𝑃𝑊𝐶 = 300 + = $381.5495𝑚
1.0625
Alternative II
$400 m
The cash flow diagram of alternative II is in the required form
The city should select the first alternative.
The interpretation of this answer is that if the city has $381.5495m now, they will use $300m to construct the reduced size
aqueduct and put $81.5495m in a bank with interest 6% for 25 years at which time they will be $350m
Dr. Abdelmagid A. Abdalla Lecture 4 11/12/2020 9
EXAMPLE 3.3
A purchasing agent is considering the purchase of some new equipment for the mail room. Two
different manufacturers have provided quotations. An analysis of the quotations indicates the
following: Manufacturer Cost ($) Useful Life (Year) Salvage Value ($)
Speedy 1500 5 200
Allied 1600 5 325
The performance of the equipment of the two manufacturers is expected to be at the desired level.
Assume 7% interest and equal maintenance cost, which equipment should be selected?
SOLUTION
This is a fixed output problem, so, the objective of the analysis is to minimize the input. The service
lives of the two equipment are equal 5 years, then, the analysis period is 5 years.
Speedy $ 200
0 $1500 5 ≡ 0 5
0 $1600 5 ≡ 0 5
PWC
325
𝑃𝑊𝐶 ȁ𝐴𝑙𝑙𝑖𝑒𝑑 = 1600 − = $ 1368 Select Speedy Equipment
1.075
EXAMPLE 3.4
A firm is trying to decide which of two alternate weighing scales should be installed to check a
package filling operation in the plant. The scales would allow better control of the filling operation
and result in less overfilling. If both scales have equal service lives of six years. Which one should
be selected ? Assume interest rate to be 8%.
Alternatives Cost ($) Uniform Annual benefit ($) Salvage value ($)
Atlas 2000 450 100
Tom Thumb 3000 600 700
Dr. Abdelmagid A. Abdalla Lecture 4 11/12/2020 11
SOLUTION $450 $100 PWB
Atlas 0 1 6 ≡ 0 6
$2000
100 1.086 −1
PWBȁAtlas = −2000 + + 450 = $143
1.086 0.08×1.086
Tom Thumb $700 PWB
$600
0 1 6 ≡ 0 6
$3000
700 1.086 − 1
PWBȁTom Thumb = −3000 + 6
+ 600 6
= $215
1.08 0.08 × 1.08
Choose Tom Thumb
EXAMPLE 3.5
Two alternatives have the following cash flows, which one should be selected? ( interest rate is 5%
Dr. Abdelmagid A. Abdalla Lecture 4 11/12/2020 12
Alternative I $800 PWB Year Alternative I ($) Alternative II ($)
0 1 3 0 3 0 -2000 -2800
$2000 1 800 1100
2 800 1100
1.053 − 1
𝑃𝑊𝐵 = 800 3
− 2000 = $178.4 3 800 1100
0.05 × 1.05
$2800
1.053 − 1
PWB = 1100 3
− 2800 = $195.3
0.05 × 1.05
Choose alternative II