You are on page 1of 4

Proceedings of the National Power Systems Conference (NPSC) - 2018, December 14-16, NIT Tiruchirappalli, India

Short circuit force in an AIS with special reference


to L-L and L-L-L faults
Sudarshan V J Gururaj. S. Punekar
PG Scholar, CTM program, Dept. of Electrical Engg., NITK
National Institute of Technology Karnataka National Institute of Technology Karnataka
Surathkal, India Surathkal, India
jaisudarshan.geo@gmail.com gsp@nitk.edu.in

Abstract—Short circuit force (SCF) in an air insulted phase. This leads to the force of repulsion between the phase to
substation is a feature which is of importance in its phase conductors [3]. In the case of three phase short circuit
electromechanical design. SCF which are generated due to short faults (L-L-L), the resultant electromagnetic force on one phase
circuit current is transferred from conductors (flexible or rigid) of the current carrying conductor is influenced by the current in
to end connections where the conductors are being held. The end the other two phases. For instance, the electromagnetic force on
connections and the conductor are supported by means of Y-phase is the resultant force caused due to R-phase on Y-
insulator, steel structure, and foundation. Thus, SCF is phase and force caused due to B-phase on Y-phase.
transferred from conductors to end connections and then to steel Due to large magnitude of fault current and reduced
structures via insulator. If estimation of SCF is erroneous, then
clearances within the substation, fault current level (fault level)
the end result will be a disaster (as the structural designs are
based on this). On the other hand, too much conservative
plays a vital role in deciding the magnitude of dynamic forces
structural designs based on the estimated SCF results in (SCFs). High fault current magnitudes impose severe
increased size and cost of insulators, steel structure, and mechanical stress on conductors, associated hardware, and
foundation requirements. Hence, the computation of SCF support structures. High fault currents cause large conductor
becomes mandatory in design of the substation from the displacements in case of flexible conductors and bending
reliability and economic considerations. In this paper, SCF in a stresses in cases of rigid conductors [4]. Fault levels are
400 kV air insulated (upcoming) substation (in Africa) due to increasing in the utility systems all over the globe.
line-to-line short circuit currents and three phase short circuit Management of fault currents is crucial to avoid damage and
currents on flexible conductor are computed using basic malfunction of station equipment. As fault currents and forces
electromagnetic laws and are discussed. The computed values are increases, the physical demand on the foundations and the
compared with the values of SCF obtained as per IEC 60865 supporting-structures will also increase.
standard. The total force acting on the conductors, terminals,
structures and foundations will have both (i) electromagnetic
Keywords— Air Insulated Substation, Drop force, Pinch force, force caused due to short circuit current and (ii) force due to
Short circuit force, Tensile force. dead load of the conductor. To obtain the force due to dead
I. INTRODUCTION load of the conductor, initial static tension is calculated using
sag tension calculation. Initial static tension gives the static
Substation within the power system network performs a tensile force with which the flexible conductor is held by the
primary function of transmitting and distributing power to the tower-gantry. The calculation steps are enlisted in the IEC
consumers with guaranteed safety, reliability, and integrity of standard [5]. The standard aids in calculating the
the entire power system [1]. In case of short circuit faults in the electromagnetic forces due to short circuit currents.
power system, the substation equipment carries huge amount of In this paper, the electromagnetic forces in a 400 kV
current (short circuit currents). The substation equipment’s are flexible conductor configuration of AIS (upcoming substation
designed to carry and sustain these currents for a short duration in Africa) are computed using the basic electromagnetic laws
till the circuit breaker interrupts these currents. Thus, short for L-L and L-L-L faults and they are compared. The forces
circuit in a substation results in flow of fault current for a experienced due to dead load on the conductor are computed
shorter time which flows within the conductors and whose
using the IEEE guidelines [7]. These are added with the
duration is limited (governed) by the protective devices
electromagnetic force to obtain the total SCF acting on the
(current transformers, relaying scheme and circuit breaker).
Even though protective devices clear the short circuit faults, phase conductor. The computed values are compared with the
within the substation, they result in the momentary flow of values obtained using IEC 60865 standard. All the data used
very high currents. High electromagnetic fields produced by related to the substation pertains to an actual design data of a
these currents result in electromagnetic forces (SCFs) between 400 kV substation which is under construction in Africa. The
the conductors [2]. SCF estimations for a substation are case specific (as faults
The line-to-line short circuits between two phases (R-phase levels are specific to substation). It is believed that this case
and Y-phase) results in the short circuit currents flowing study would help in understanding the SCFs and their
between two phase conductors. Also, for line-to-line faults estimations in substation designs.
(L-L), short circuit current flow in the R-phase will be in
opposite direction to the short circuit current flow in the Y-

978-1-5386-6159-8/18/$31.00 ©2018 IEEE


Proceedings of the National Power Systems Conference (NPSC) - 2018, December 14-16, NIT Tiruchirappalli, India

II. TYPES OF FAULT AND FORCES shown in Fig.1 (Case b). It also shows the reduction of phase to
Short circuit current creates electromagnetic forces. Thus, phase air clearance during three phase short circuits. The air
these force have an impact on the design of mechanical clearances reduce from r, during normal operating conditions
structure and foundation of substation equipment. to amin, during the drop down at the end of the short circuit
Three different faults, namely, (i) single line to ground conditions. Thus, from Fig.1 it is clear that the reduced air
fault, (ii) L-L fault and (iii) three phase (L-L-L) faults can clearances (amin) during L-L faults are lesser when compared to
result into SCFs. Short circuit currents due to single line to that of three phase faults.
ground faults results in relatively much lower stresses when
compared to other types of faults because of larger distance
between the phase conductor and the return path (ground).
Hence, single phase short circuits and results SCFs are not
significant. They generally not considered for SCF based
structural designs. In the present study, electromagnetic
stresses on conductors due to L-L faults and those of L-L-L
faults are computed using the case specific data pertaining to a
upcoming substation, and compared.
In the event of a short circuit in a system, due to the short
circuit force (SCF), the flexible-bus-conductor in the substation
starts to swing. Fig. 1 shows the probable (typical) movement
of flexible conductors due to L-L faults (Case a) and three
phase faults (Case b). When L-L faults occur between R-phase
and Y-phase of the three-phase system, short circuit current of
equal magnitude will flow in R-phase and Y-phase conductors.
The direction of current flow in one phase will be in the
opposite direction compared to the other phase. This results in
the electromagnetic repulsive forces being experienced by the
phase conductors. This force of repulsion between the
conductors, results in swinging of flexible conductors. During
Figure 1. Flexible conductor movement due to L-L and three phase
L-L faults, the flexible conductors swing out as shown in Fig.1 short circuit faults.
(case a). After the end of short circuit, there will be a
downward pull due to the gravity and the conductors will
continue to move towards each other as shown in Fig.1 (case III. CALCULATION OF SCF
a). This results in the reduction of phase to phase air clearance Using the Biot-Savart law and the Lorentz Force law, the
during L-L short circuits. The air clearances reduce from r, electromagnetic force between two parallel current carrying
during normal operating conditions to amin, during the drop conductors can be computed. The electromagnetic force
down at the end of the short circuit conditions. However, there experienced on one phase of the conductor (say “m” phase) due
is no short circuit current flowing in the third phase (B-phase, to current in the other conductor running in parallel (say “n”
healthy phase) during line-to-line faults and it doesn’t phase), ǁFmnǁ, is given by,
contribute to electromagnetic force (SCF).
In case of three phase short circuit faults, unlike L-L faults, | | = (1)
SCF involves all the three phases and the conductors. The
electromagnetic force on one of the phase conductor (R-phase) Where,
is influenced by the current flowing in the other two-phase
conductors (Y-phase and B-phase). Hence, the force exerted on µ0 indicates the absolute permeability of air (4п x 10-7
a phase conductor is the resultant of force produced by other Wb/A-m).
two phases. For example, the short circuit current flowing in Y- Im and In, are the short circuit currents (in kA) being carried
phase conductor (central conductor) during three phase faults by “m” phase conductor and “n” phase conductor, respectively.
are in opposite direction to that of short circuit currents flowing l is the conductor length (m)
in R-phase and Y-phase conductors. This leads to the force of r is the phase to phase spacing (m) between the conductor’s
repulsion between the R-phase and Y-phase conductors, and m and n.
between B-phase and Y-phase conductors. Thus, Y-phase (Fig
1; Case b) will be experiencing repulsive forces in opposite The conductors are assumed to be of horizontal disposition
directions caused due to short circuit current flowing in R- with phase to phase spacing of r. With this configuration the
phase and B-phase conductors. However, R-phase and B-phase force on each conductor will be along the line joining the
conductors will experience the force of attraction or repulsion conductors. This force can be attractive or repulsive based on
based on the interaction of short circuit current flowing in the the relative direction of the currents in the two conductors.
other two conductors. The SCFs in case of L-L-L faults are not This electromagnetic force caused due to the short circuit
unidirectional over a cycle. Thus, the movement of conductors current contributes to the SCF which is experienced by the
(mechanical system) and change in clearance are lower in case conductors, terminations, and structures. In case of flexible
of L-L-L faults when compared to those of L-L faults. This buses, as per IEC 60865 [5], the short circuit force computation
results in the movement of flexible conductors (typically) as involves computation of various components of SCF such as (i)
Tensile force (ii) Drop force and (iii) Pinch force
Proceedings of the National Power Systems Conference (NPSC) - 2018, December 14-16, NIT Tiruchirappalli, India

The definitions of these and their computational procedure The short circuit fault currents are balanced in case of three
is given in [5-7]. The maximum among these three force phase faults. In order to compute the instantaneous values of
components is chosen as the SCF [5]. forces over a cycle the following relations ((2) to (4)) are used
for the currents.
IV. 400 KV SUBSTATION DETAILS
= sin ( ) (2)
A 400/132 kV air insulated substation located (upcoming)
in Africa is considered for the computation of SCF in the = sin ( − 120) (3)
substation. The design parameters of significance to SCF and = sin ( + 120) (4)
their magnitudes for the substation under study are given in Where,
Table I. Im – Peak short circuit current magnitude (kA).
TABLE I. DETAILS OF THE 400 KV SUBSTATION UNDER STUDY iR, iY, and iB – Instantaneous short circuit current of R, Y
and B-phases respectively (in kA).
S.No Parameter Magnitude
The instantaneous current values of the phases will have
1 Voltage level 400 / 132 / 33 kV different polarities and magnitudes at different time instants.
2 MVA rating 1 x 200 MVA Hence, the force experienced between the conductors will vary
both in magnitude and direction (attractive or repulsive) instant
3 Three phase Fault Level 40 / 31.5 / 20 kA
to instant. At each time instant, force experienced by a phase
4 Fault current duration 3s conductor is calculated as the sum of forces produced due to
5 Continuous current carrying 3.15 / 3.15 / 1.25 kA the interaction of short circuit current flowing in the other two
capacity conductors. In the present estimation of electromagnetic forces
6 Frequency 50 Hz and SCF, the fault current magnitude is assumed be sinusoidal
with a fixed magnitude (in actuality this may not be true).
7 Phase to phase spacing between 4.5 m The electromagnetic force experienced by the phase
flexible conductors
conductors during three phase fault is calculated using (1) over
8 Length of the flexible conductors 55 m a cycle. Figs. 2 and 3 shows the instantaneous electromagnetic
9 Initial Static Tension 19.6 kN forces due to three phase short circuit faults in R-phase and Y-
phase of the system considered, respectively. Fig. 4 shows the
V. RESULTS AND DISCUSSION comparison of resultant electromagnetic force on Y- phase due
to L-L and three phase short circuit faults. In generating the
For the substation under study, electromagnetic forces on a plots (Figs. 2 and 3) the force of repulsion is considered as
flexible conductor due to L-L short circuits and three phase positive and the force of attraction is considered as negative.
short circuits are computed using (1). Using this force (tensile) For the three phase faults, the average electromagnetic
component, the SCF is estimated. The computed SCF values forces on R-phase, Y-phase and B-phase conductors is
are compared with those obtained using IEC 60865 [5]. 2.8532 kN, 3.963 kN and 2.8532 kN, respectively. The
The fault level for this substation (see Table 1) is 40 kA maximum value of electromagnetic forces obtained for R-
(rms) at 400 kV level. Hence, 40 kA (rms) is the magnitude of phase (and B-phase) is 6.27 kN, and that for Y-phase is 7.82
current that is considered for three phase faults with kN. However, instant of occurrence of peak value varies for
corresponding peak magnitude of the fault current being different phase conductors. The total force acting on the phase
56.6 kA. For the line-to-line faults the fault current magnitudes conductors, at any instant is given by the sum of peak
are decided by the negative as well as the positive sequence electromagnetic force and initial static tensile force (19.6 kN).
impedances. Assuming these sequence components to be equal, Thus, the maximum value of SCF due to three phase faults on
the magnitude of fault current under line-to-line fault will be R-phase and B-phase conductors are 25.87 kN (sum of 6.27 kN
0.866 times that of the three phase fault currents. The same is and 19.6 kN). SCF on Y-phase conductor is 27.42 kN (sum of
used in the computation of the SCF due to L-L faults. 7.82 kN and 19.6 kN). The initial-static-tension for a conductor
During line-to-line faults, the fault current will be flowing of this substation is evaluated as suggested in reference [7].
in opposite directions in both the phases. Hence, both R-phase
and Y-phase conductors experiences the electromagnetic force Table II shows the comparison of tensile forces due to L-L
which is repulsive. This electromagnetic force between R- and L-L-L faults computed using equation (1). In the present
phase and Y- phase is computed using (1). For the peak value study it is observed that the SCF due to L-L-L are higher
of the fault current considered, the average electromagnetic compared to those of L-L, marginally. This validates the
force calculated (over a cycle) is 2.853 kN and the statement given in CIGRE-105 [2] substantiating the usage of
corresponding peak electromagnetic force calculated is 5.86 forces due to L-L-L as the basis for estimating SCFs as far as
kN. The total force acting on the conductors is the sum of magnitudes of forces are concerned. On the contrary the SCF’s
electromagnetic force and the force due to dead load of the in case of L-L faults are unidirectional (repulsive) unlike those
conductor. For the current study, the force due to dead load of of due to L-L-L faults which results in pulsating force. The
the conductor (initial-static-tension) is given as 19.6 kN (see mechanical systems due to their inertia may not have any or
Table I). Thus, the total SCF due to L-L faults on R-phase and much displacement in case of L-L-L faults compared to L-L
Y-phase conductors is 25.46 kN (sum of 5.86 kN and 19.6 kN). faults. Hence, from the point of phase to phase clearances the
The initial-static-tension for a conductor is evaluated using the L-L faults and SCF’s are of importance. This validates the
sag-tension calculations for the conductor. This depends on the usage of L-L faults for flexible systems as stated in CIGRE-
size and type of the conductor used [7]. 105 [2]. It is clear from the Table II that; the maximum tensile
Proceedings of the National Power Systems Conference (NPSC) - 2018, December 14-16, NIT Tiruchirappalli, India

force occurs for the three phase short circuit at Y-phase (central
conductor). It is found to be 27.42 kN.

Figure 4. Comparison of electromagnetic force on Y-phase due to


line-to-line and three phase (resultant) short circuit faults.
Figure 2. Instantaneous electromagnetic force variation on R-phase due to
three phase short circuit fault. TABLE III. ESTIMATED SCF FOR THE 400 KV AIS

Parameters SCF obtained using IEC 60865 (kN)


Tensile Force 27.46
Drop 30.30

Pinch 31.33

VI. CONCLUSIONS
Tensile SCF for line-to-line faults (peak force) and three
phase faults (instantaneous values over a cycle) are computed
and compared as case study for a 400 kV AIS.
During three phase faults, Y-phase conductor (central
conductor in horizontal disposition) experiences higher
electromagnetic forces when compared to R-phase and B-phase
conductors. The average and maximum electromagnetic force
due to three phase faults is marginally higher when compared
to that of line-to-line faults.
Figure 3. Instantaneous electromagnetic force variation on Y-phase due to The unidirectional (repulsive) forces due to L-L faults
three phase short circuit fault.
would result in lesser dynamic air clearances between the
phases. Thus, from the point of phase to phase clearances, L-L
The short circuit tensile force, short circuit drop and short
faults are of significance in SCF computation of flexible
circuit pinch forces are computed for 400 kV substation (see
conductors, although their magnitudes are marginally lower.
Table 1) flexible conductors as per IEC 60865 [5] and are
For the substation under study, the estimated SCF useful in
given in Table III. It is clear from Table III that, the short
the structural design is due the pinch force; a pinch force
circuit tensile force computed using IEC 60865 [5] matches
(31.33 kN).
with that estimated maximum tensile force (using equation (1))
for the three phase short circuit at Y-phase (central conductor; REFERENCES
see Table II).
[1] M.A.C.Camargo, A.J.Rivera and R.R.Pena, “Impact Assessment of
Substation Contingencies in Power Systems,” in IEEE Transmission &
TABLE II. COMPARISON OF TENSILE FORCES DUE TO L-L AND Distribution Conference and Exposition,Nov. 2014.
L-L-L FAULTS COMPUTED USING EQUATION (1) [2] CIGRE 105, "The Mechanical Effects of Short-Circuit Currents in
Open Air Substations," Working group 23.11, April-1996.
Tensile Forces (kN) [3] CIGRE 214, “The Mechanical Effects of Short-Circuit Currents in
Open Air Substations (Part II),” Working group 23.11, Oct 2002.
[4] D. B. Craig and G. L. Ford, " The Response of strain bus to short
For L-L-L short circuits For L-L short circuits circuit currents," in IEEE Transactions on Power Apparatus and Systems,vol.
pas-99, no.2,April 1980.
R-phase, B-phase Y-phase [5] IEC 60865-1, “Short-circuit currents - Calculation of effects - Part
1: Definitions and calculation methods,” edition-3, 2011-10.
25.87 27.42 25.46 [6] IEC 60865-2, “Short-circuit currents - Calculation of effects - Part
2: Examples of calculation,” edition-1,2015.
[7] "IEEE Guide for Bus Design in Air Insulated Substations," in IEEE
Power & Energy Society std 605-2006 (Revision of IEEE std 605-1998).

You might also like