Professional Documents
Culture Documents
Audit Sampling: Mcgraw-Hill/Irwin
Audit Sampling: Mcgraw-Hill/Irwin
Audit Sampling
McGraw-Hill/Irwin Copyright © 2010 by The McGraw-Hill Companies, Inc. All rights reserved.
What is Audit Sampling?
• Qualitative
• Quantitative
Risk
9-3
• Sampling risk
•
• Other methods
•
• Haphazard selection
•
• Attributes sampling
• Discovery sampling
• Classical variables sampling
•
• Mean-per-unit estimation
• Ratio estimation
• Difference estimation
• Probability-proportional-to-size sampling
Dual Purpose Test
9-11
Sampling Plans
• When planning the sample consider:
•
Extent of Operating
Effectiveness is
Adequate
Extent of Operating
Effectiveness
Inadequate
(Ris
C
9-16
Audit Sampling Steps for Tests of
Controls
• Determine the objective of the test
• Define the attributes and deviation conditions
• Define the population to be sampled
• Specify:
•
“I believe that the deviation rate in the population is less than 9 percent.” You will be
wrong 5 percent of the time when the deviation is exactly 9 percent. If the deviation rate is
in excess of 9 percent you will be wrong even less than 5 percent of the time. The planned
assessed level of control risk is achieved.
Approach 2
You have tested 68 items, a number not on Table 9-5 (next slide
To be conservative go to next lowest number on table (65) and use it for your
conclusions (we could, but won't interpolate for a more precise answer).
You have met your audit objective. Table 9-5 gives us an answer of 4.6 percent.
What can you say?
"I believe that the deviation rate in the population is less than 4.6 percent.” You will
be wrong 5 percent of the time when the deviation rate is exactly 4.6 percent. If the
deviation rate is in excess of 4.6 percent you will be wrong even less than 5 percent of the
time. The planned assessed level of control risk is achieved.
Figure 9.5 Statistical Sampling Results Evaluation Table for Tests
of Controls: Achieved Upper Deviation Rate at5 Percent Risk of
Assessing Control Risk Too Low
Example B--3 Deviations Identified (Evaluating
Attributes Sampling Results
Approach 1—You have not met your audit objective. What can you say?
“The achieved upper deviation rate is higher than 9 percent.” The planned assessed
level of control risk is not achieved. You need to consider increasing the assessed level of
control risk above the planned assessed level.
Accordingly, you may not “rely” on internal control to the extent planned. Thus, the
auditor will need to increase the scope of substantive procedures (the nature, timing, and/or
extent).
Approach 2—You have not met your audit objective. Table 9-5 provides us an answer of
11.5 percent
“I believe that the deviation rate in the population is less than 11.5 percent.” You will
be wrong 5 percent of the time when the deviation rate is exactly 11.5 percent. But this is
not good enough as you wanted 9 percent rather than 11.5 percent. The planned assessed
level of control risk is not achieved. You need to consider increasing the assessed level of
control risk above the planned assessed level.
Sampling Approaches
• Discovery sampling
•
Misstatement in
Account Exceeds
Tolerable Amount
C
Misstatement in D
Account Is Less
Than Tolerable
Amount
In
D
(Risk
Ac
Audit Sampling Steps for Substantive 9-27
Tests
⎛ $364,000 ⎞
Planned ASR = ⎜ ⎟ = $200,000
⎝ 1 + (1.64 / 2.00) ⎠
Determining Sample Size--MPU (2 of
2)
2
⎛ Population size * Incorrect rejection coefficient * Est. std. dev. ⎞
Sample Size = ⎜⎜ ⎟⎟
⎝ Planned allowance for sampling risk ⎠
2
⎛ 100,000 * 2.00 * $15 ⎞
Sample Size = ⎜ ⎟
⎝ $200,000 ⎠
= 225 Accounts
9-34
Adjusted allowance
for sampling risk =
• This formula “adjusts” the allowance for sampling risk to consider the standard deviation of
the audited values in the sample. It holds the risk of incorrect acceptance at its planned
level.
9-35
Variables Sampling
Using the text example with a standardIllustration--MPU
deviation of audited values of $16
Adjusted allowance
for sampling risk =
Tolerable _ (Population size * Incorrect acceptance coef. * Sample stan. dev.)
misstatement Sample size
225
= $189,067
We would still “accept” the book balance because the $6,250,000 (book value)
falls within this interval
Illustration
• Plan Sample:
•
• Population:
•
of Sample Size
Sample Results
• Sample results:
40 accounts in sample
$350 net overstatement
$60,000 book value of sample items
• Projected misstatement:
• Sample size =
= $6,250,000 * 3.0 = 66
$364,000 - ($50,000 * 1.6)
AR = IR x CR x DR
where
• AR=The allowable audit risk that a material misstatement might remain
undetected for the account balance and related assertions.
• IR= Inherent risk, the risk of a material misstatement in an assertion,
assuming there were no related controls.
• CR= Control risk, the risk that a material misstatement that could occur in
an assertion will not be prevented or detected on a timely basis by internal
control.
• DR= Detection risk, the risk that the auditors’ procedures will fail to detect
a material misstatement if it exists.