You are on page 1of 1

5A1 Snag List

No Comments Remarks
1 In sufficient Lightning.
2 Scaffolding needed to remove.
3 ATR 1 and ATR 2 secondary not connected.
4 ATR 1 and ATR 2 MV side torquing is required.
5 ATR 1 and ATR 2 chassy earthing with frame not connected.
6 Torquing required on Primary and secondary earthing Bus - Bar.
7 Feruls missing on Earthing Bar R2.
8 Ethernet cable addressing required inside LMVS.
9 House keeping Required.
10
11
12
13
14
15
16
17
General comments
DB installed and external and internal cables are pulled and terminated.
Can not open LV compatrment of LMVS to verify the internal cables because Scaffolding errected
Don’t have Key to open MCC SLVDB and SABC panel to verify the internal status.
SF6 on all compartments of LMVS is an optimal level (3.0 Bar).
At ACC panel all power control and earthing cables are terminated and tagged