Professional Documents
Culture Documents
9.1 a. To calculate the accounting breakeven, we first need to find the depreciation for each year.
The depreciation is:
Depreciation = $724,000 / 8
Depreciation = $90,500 per year
b. We will use the tax shield approach to calculate the Operating Cash Flow, OCF. The OCF
is:
OCFbase = [(Price – Variable cost) × Sales units – Fixed cost] × (1 – Tc) + Tc × Depreciation
OCFbase = [($39 – $23) × 75,000 – $850,000] × (0.65) + 0.35 × ($90,500)
OCFbase = $259,175
Now we can calculate the NPV using our base-case projections. There is no salvage value
or NWC, so the NPV is:
8
NPVbase = –$724,000 + $259,175 × Α 15%
NPVbase = $439,001.55
To calculate the sensitivity of the NPV to changes in the quantity sold, we will calculate the
NPV at a different quantity. We will use sales of 80,000 units. The NPV at this sales level
is:
So, the change in NPV for every unit change in sales is:
You may wonder why we chose 80,000 units. It doesn’t matter! Whatever sales number we
use, when we calculate the change in NPV per unit sold, the ratio will be the same.
c. To find out how sensitive OCF is to a change in variable costs, we will compute the OCF at
a variable cost of $24. Again, the number we choose to use here is irrelevant: We will get
the same ratio of OCF to a one dollar change in variable cost no matter what variable cost
we use. So, using the tax shield approach, the OCF at a variable cost of $24 is:
9.2 We will use the tax shield approach to calculate the OCF for the best- and worst-case scenarios.
For the best-case scenario, the price and quantity increase by 10 percent, so we will multiply the
base case numbers by 1.1, a 10 percent increase. The variable and fixed costs both decrease by
10 percent, so we will multiply the base case numbers by .9, a 10 percent decrease. Doing so, we
get:
OCFbest = {[($39) × (1.1) – ($23) × (0.9)] × (75,000) × (1.1) – $850,000 × (0.9)} × (0.65)
+ 0.35 × ($90,500)
OCFbest = $724,900.00
For the worst-case scenario, the price and quantity decrease by 10 percent, so we will multiply
the base case numbers by .9, a 10 percent decrease. The variable and fixed costs both increase by
10 percent, so we will multiply the base case numbers by 1.1, a 10 percent increase. Doing so,
we get:
OCFworst = {[($39) × (0.9) – ($23) × (1.1)] × (75,000) × (0.9) – $850,000 × (1.1)} × (0.65)
+ 0.35 × ($90,500)
OCFworst = –$146,100
Ross et al, Corporate Finance 8th Canadian Edition Solutions Manual
© 2019 McGraw-Hill Education Ltd.
9-3
The worst-case NPV is:
8
NPVworst = –$724,000 – $146,100 × Α 15 %
NPVworst = –$1,379,597.67
to solve for the unknown variable in each case. Doing so, we find:
9.4 If we purchase the machine today, the NPV is the difference between the present value of the
increased cash flows and the machine cost, so:
10
NPV0 = –$1,800,000 + $340,000 × Α 12%
NPV0 = $121,075.83
We should not necessarily purchase the machine today. We would want to purchase the machine
when the NPV is the highest. So, we need to calculate the NPV each year. The NPV each year
will be the difference between the present value of the increased cash flows and the machine cost.
We must be careful, however. In order to make the correct decision, the NPV for each year must
be taken to a common date. We will discount all of the NPVs to today. Doing so, we get:
9
Year 1: NPV1 = [–$1,670,000 + $340,000 × Α 12 % ] / 1.12
NPV1 = $126,432.97
8
Year 2: NPV2 = [–$1,540,000 + $340,000 × Α 12 % ] / 1.122
NPV2 = $118,779.91
7
Year 3: NPV3 = [–$1,410,000 + $340,000 × Α 12 % ] / 1.123
NPV3 = $100,843.05
The company should purchase the machine one year from now when the NPV is the highest.
9.5 We need to calculate the NPV of the two options, go directly to market now, or utilize test
marketing first. The NPV of going directly to market now is:
Now we can calculate the NPV of test marketing first. Test marketing requires a $1.5 million
cash outlay. Choosing the test marketing option will also delay the launch of the product by one
year. Thus, the expected payoff is delayed by one year and must be discounted back to year 0.
The company should test market first with the product since that option has the highest expected
payoff.
9.6 We need to calculate the NPV of each option, and choose the option with the highest NPV. So,
the NPV of going directly to market is:
Customer segment research requires a $1.2 million cash outlay. Choosing the research option
will also delay the launch of the product by one year. Thus, the expected payoff is delayed by
one year and must be discounted back to year 0. So, the NPV of the customer segment research
is:
The company should go directly to the market since it has the larger NPV.
9.8 Using the tax shield approach, the OCF at 90,000 units will be:
OCF = [(Sale price – Variable cost) × Sales units – Fixed cost] × (1 – TC) + TC × (Depreciation)
OCF = [($37 – $23) × (90,000) – $195,000] × (1 – 0.34) + 0.34 × ($480,000 / 4 years)
OCF = $743,700
To find the sensitivity of the operating cash flow to the changes in the quantity sold, we will
calculate the OCF at 91,000 units. The choice of the second level of quantity sold is arbitrary
and irrelevant. No matter what level of units sold we choose, we will still get the same
sensitivity. So, the OCF at this level of sales is:
So, the OCF will increase by $9.24 for every additional unit sold.
9.9 a. The base-case, best-case, and worst-case values are shown below. Remember that in the
best-case, unit sales increase, while costs decrease. In the worst-case, unit sales decrease,
and costs increase.
The OCF and NPV for the worst case estimate are:
4
NPVworst = –$820,000 – $157,105 Α 15 % + $153,304 .35
NPVworst = –$1,115,227.03
And the OCF and NPV for the best case estimate are:
b. To calculate the sensitivity of the NPV to changes in fixed costs, we choose another level of
fixed costs. We will use fixed costs of $620,000. The OCF using this level of fixed costs
and the other base case values with the tax shield approach, we get:
9.10The marketing study and the research and development are both sunk costs and should be
ignored. We will calculate the sales and variable costs first. Since we will lose sales of the
expensive clubs and gain sales of the cheap clubs, these must be accounted for as outflows and
inflows, respectively. The total sales for the new project will be:
For the variable costs, we must include the units gained or lost from the existing clubs. Note that
the variable costs of the expensive clubs are an inflow. If we are not producing the sets any
more, we will save these variable costs, which is an inflow. So:
Var. costs
New clubs –$430 60,000 = –$25,800,000
Exp. clubs –$620 (–12,000) = $7,440,000
Cheap clubs –$210 15,000 = –$3,150,000
–$21,510,000
The pro forma income statement and OCF calculations will be:
Investment -$29,400,000
WC -$1,400,000 $1,400,000
Sales $45,300,000 $45,300,000 $45,300,000 $45,300,000 $45,300,000 $45,300,000 45,300,000
Variable costs -21,510,000 -21,510,000 -21,510,000 -21,510,000 -21,510,000 -21,510,000 -21,510,000
Fixed costs -9,300,000 -9,300,000 -9,300,000 -9,300,000 -9,300,000 -9,300,000 -9,300,000
CCA at 20% -2,940,000 -5,292,000 -4,233,600 -3,386,880 -2,709,504 -2,167,603 -1,734,083
EBIT 11,550,000 9,198,000 10,256,400 11,103,120 11,780,496 12,322,397 12,755,917
Taxes at 40% 4,620,000 3,679,200 4,102,560 4,441,248 4,712,198 4,928,959 5,102,367
NI 6,930,000 5,518,800 6,153,840 6,661,872 7,068,298 7,393,438 7,653,550
Add CCA 2,940,000 5,292,000 4,233,600 3,386,880 2,709,504 2,167,603 1,734,083
Cash flows 9,870,000 10,810,800 10,387,440 10,048,752 9,777,802 9,561,041 9,387,633
from
operations
Total Cash -$30,800,000 $9,870,000 $10,810,800 $10,387,440 $10,048,752 $9,777,802 $9,561,041 $10,787,633
flows
IRR = 26.8%
9.11To calculate the sensitivity of the NPV to changes in the price of the new club, we simply need
to change the price of the new club. We will choose $885, but the choice is irrelevant as the
sensitivity will be the same no matter what price we choose.
We will calculate the sales and variable costs first. Since we will lose sales of the expensive
clubs and gain sales of the cheap clubs, these must be accounted for as erosion. The total sales
for the new project will be:
Sales
New clubs $885 60,000 = $53,100,000
Exp. clubs $1,100 (– 12,000) = -$13,200,000
Cheap clubs $400 15,000 = $6,000,000
$45,900,000
For the variable costs, we must include the units gained or lost from the existing clubs. Note that
the variable costs of the expensive clubs are an inflow. If we are not producing the sets any
more, we will save these variable costs, which is an inflow. So:
Var. costs
New clubs –$430 60,000 = –$25,800,000
Exp. clubs –$620(–12,000)= $7,440,000
Cheap clubs –$210 15,000 = –$3,150,000
–$21,510,000
Investment -$29,400,000
WC -$1,400,000 $1,400,000
Sales $45,900,000 $45,900,000 $45,900,000 $45,900,000 $45,900,000 $45,900,000 45,900,000
Variable -21,510,000 -21,510,000 -21,510,000 -21,510,000 -21,510,000 -21,510,000 -21,510,000
costs
Fixed costs -9,300,000 -9,300,000 -9,300,000 -9,300,000 -9,300,000 -9,300,000 -9,300,000
CCA at -2,940,000 -5,292,000 -4,233,600 -3,386,880 -2,709,504
20% -2,167,603 -1,734,083
EBIT 12,150,000 9,798,000 10,856,400 11,703,120 12,380,496 12,922,397 13,355,917
Taxes at 4,860,000 3,919,200 4,342,560 4,681,248 4,952,198 5,168,959 5,342,367
40%
NI 7,290,000 5,878,800 6,513,840 7,021,872 7,428,298 7,753,438 8,013,550
Ross et al, Corporate Finance 8th Canadian Edition Solutions Manual
© 2019 McGraw-Hill Education Ltd.
9-10
Add CCA 2,940,000 5,292,000 4,233,600 3,386,880 2,709,504 2,167,603 1,734,083
Cash flows 10,230,000 11,170,800 10,747,440 10,408,752 10,137,802 9,921,041 9,747,633
from
operations
Total Cash -$30,800,000 $10,230,000 $11,170,800 $10,747,440 $10,408,752 $10,137,802 $9,921,041 $11,147,633
flows
So, the sensitivity of the NPV to changes in the price of the new club is:
For every dollar increase (decrease) in the price of the clubs, the NPV will increase (decrease)
by $154,378.90.
To calculate the sensitivity of the NPV to changes in the quantity sold of the new club, we
simply need to change the quantity sold. We will choose 65,000 units, but the choice is
irrelevant as the sensitivity will be the same no matter what quantity we choose.
We will calculate the sales and variable costs first. Since we will lose sales of the expensive
clubs and gain sales of the cheap clubs, these must be accounted for as erosion. The total sales
for the new project will be:
Sales
New clubs $875 65,000 = $56,875,000
Exp. clubs $1,100 (– 12,000) = -$13,200,000
Cheap clubs $400 15,000 = $6,000,000
$49,675,000
For the variable costs, we must include the units gained or lost from the existing clubs. Note that
the variable costs of the expensive clubs are an inflow. If we are not producing the sets any
more, we will save these variable costs, which is an inflow. So:
Var. costs
New clubs –$430 65,000 = –$27,950,000
Exp. clubs –$620 (–12,000) = $7,440,000
Cheap clubs –$210 15,000 = –$3,150,000
–$23,660,000
Investment -$29,400,000
WC -$1,400,000 $1,400,000
So, the sensitivity of the NPV to changes in the quantity sold is:
For an increase (decrease) of one set of clubs sold per year, the NPV increases (decreases) by
$1,144.98.
b. We would abandon the project if the cash flow from selling the equipment is greater than
the present value of the future cash flows. We need to find the sale quantity where the two
are equal, so:
9
$950,000 = ($35) × Q × Α 16%
Q = $950,000 / ($35 × 4.6065)
Q = 5,892
c. The $950,000 is the market value of the project. If you continue with the project in one
year, you forego the $950,000 that could have been used for something else.
9.13a. If the project is a success, the expected sales will be revised upwards to 11,000 units. The
present value of the future cash flows will be:
9
PV future CFs = $35 × 11,000 units × Α 16%
PV future CFs = $1,773,519.39
From the previous question, if the quantity sold is 4,000 units, we would abandon the
project, and the cash flow would be $950,000. Since the project has an equal likelihood of
success or failure in one year, the expected value of the project in one year is the average of
the success and failure cash flows, plus the average cash flow in one year, so:
The NPV is the present value of the expected value in one year plus the cost of the
equipment, so:
b. If we couldn’t abandon the project, the present value of the future cash flows when the
quantity is 4,000 will be:
9
PV future CFs = $35 × 4,000 units × Α 16%
PV future CFs = $644,916.14
The gain from the option to abandon is the abandonment value minus the present value of
the cash flows if we cannot abandon the project, so:
The value of the option to abandon today is the likelihood of abandonment times the gain
from option to abandon discounted back to the present:
1
Option value = (.50) × ($305,083.56) × Α 16%
Option value = $131,501.53
Ross et al, Corporate Finance 8th Canadian Edition Solutions Manual
© 2019 McGraw-Hill Education Ltd.
9-13
9.14If the project is a success, present value of the future cash flows will be:
9
PV future CFs = $35 × 22,000 units × Α 16%
PV future CFs = $3,547,038.78
If the sales are only 4,000 units, from Problem #9.12 and #9.13, we know we will abandon the
project, with a value of $950,000. Since the project has an equal likelihood of success or failure
in one year, the expected value of the project in one year is the average of the success and failure
cash flows, plus the average cash flow in one year, so:
The NPV is the present value of the expected value in one year plus the cost of the
equipment,so:
The gain from the option to expand is the present value of the cash flows from the additional
units sold, so:
9
Gain from option to expand = $35 × 11,000 × Α 16%
Gain from option to expand = $1,773,519.39
The value of the option to expand today is the likelihood of expansion times the gain from
option to expand discounted back to the present:
9.15 The accounting breakeven is the after-tax sum of the fixed costs and depreciation charge divided
by the contribution margin (selling price minus variable cost). In this case, there are no fixed
costs, and the depreciation is the entire price of the press in the first year. So, the accounting
breakeven level of sales is:
9.16 The payoff from taking the lump sum is $12,000, so we need to compare this to the expected
payoff from taking one percent of the profit. The decision tree for the movie project is:
The value of one percent of the profits is as follows. There is a 30 percent probability the movie is
good, and the audience is big, so the expected value of this outcome is:
The expected value if the movie is good, and has a big audience, assuming the script is good is:
Carl, the screenwriter will receive only one percent of this amount. So, the payment to the
screenwriter will be:
The remaining life of the mine = 48,000 ounces / 6,000 ounces per year = 8 years
This will be true no matter when you open the mine. The after-tax cash flow per year if opened
today is:
If you open the mine in one year, the cash flow will be either:
9.18 a. The NPV of the project is sum of the present value of the cash flows generated by the project.
The initial investment = $51 million
Annual operating cash flow for the next 10 years = $10.5 million
Discount rate = 13%
b. The company should abandon the project if the PV of the revised cash flows for the next nine
years is less than the project’s after-tax salvage value. Since the option to abandon the project
occurs in year 1, discount the revised cash flows to year 1 as well. To determine the level of
expected cash flows below which the company should abandon the project, calculate the
equivalent annual cash flows the project must earn to equal the after-tax salvage value. We
will solve for C2, the revised cash flow beginning in year 2. So, the revised annual cash flow
below which it makes sense to abandon the project is:
9
After-tax salvage value = C2 × Α 13%
9
$31,000,000 = C2 × Α 13%
9
C2 = $31,000,000 / Α 13%
C2 = $6,040,935.96
9.19 a. The NPV of the project is sum of the present value of the cash flows generated by the
project. The annual cash flow for the project is the number of units sold times the cash flow
per unit, which is:
The cash flows from this project are an annuity, so the NPV is:
5
NPV = –$15,000,000 + $4,575,000 × Α 16%
NPV = –$20,106.53
b. The company will abandon the project if unit sales are not revised upward. If the unit sales
are revised upward, the after-tax cash flows for the project over the last four years will be:
The NPV of the project will be the initial cost, plus the expected cash flow in year one
based on 15 unit sales projection, plus the expected value of abandonment, plus the
expected value of cash flow after year one for next four years on 20 units sales projection.
We need to remember that the abandonment value occurs in year one, and the present value
of the expansion cash flows are in year one, so each of these must be discounted back to
today. So, the project NPV under the abandonment or expansion scenario is:
9.20 To calculate the unit sales for each scenario, we multiply the market sales times the company’s
market share.
We can then use the quantity sold to find the revenue each year, and the variable costs each
year. After doing these calculations, we will construct the pro forma income statement for each
scenario. We can then find the operating cash flow using the bottom up approach, which is net
income plus depreciation. Doing so, we find:
Note that under the pessimistic scenario, the taxable income is negative. We assumed a tax
credit in the case. Now we can calculate the NPV under each scenario, which will be:
6
NPVPessimistic = –$2,200,000 + $160,106.67 Α 13%
NPV = –$1,559,965.63
6
NPVExpected = –$2,100,000 +$627,500 Α 13 %
NPV = $408,462.49
6
NPVOptimistic = –$2,000,000 +$1,145,653.33 Α 13 %
NPV = $2,579,806.24
The NPV under the pessimistic scenario is negative, so the company may accept the project only
if the likelihood of occurrence of the pessimistic scenario is very low.
If the worst-case scenario is likely, the firm should not accept the project.
9.22To calculate the sensitivity to changes in quantity sold, we will choose a quantity of 36,000.
First, calculate the EACPVCCATS as follows:
CD T c 1+0.5 k SxDxT c 1
PVCCATS= x − x
k +d 1+k k +d (1+ k )n
The pro forma income statement and OCF at the level of Sales of 36,000:
You wouldn’t want the quantity to fall below the point where the NPV is zero. We know the
NPV changes $130.84 for every unit sale, so we can divide the NPV for 35,000 units by the
sensitivity to get a change in quantity. Doing so, we get:
For a zero NPV, sales would have to decrease 9,145 units, so the minimum quantity is:
Sales $6,850,000
Operating costs –2,800,000
Depreciation –2,000,000
EBT 2,050,000
Tax $779,000
Net income 1,271,000
+Depreciation 2,000,000
Operating CF 3,271,000
Change in NWC –$950,000 950,000
Capital spending –8,000,000 5,442,000
Total cash flow –$8,950,000 $9,663,000
If we abandon the project after three years, the cash flows are:
We should abandon the equipment after three years since the NPV of abandoning the project
after three years has the highest NPV.
9.24 a. The NPV of the project is the sum of the present value of the cash flows generated by the
project. The cash flows from this project are an annuity, so the NPV is:
10
NPV = –$7,000,000 + $1,300,000 Α 10 %
Ross et al, Corporate Finance 8th Canadian Edition Solutions Manual
© 2019 McGraw-Hill Education Ltd.
9-24
NPV = $987,937.24
b. The company will abandon the project if the value of abandoning the project is greater than
the value of the future cash flows. The present value of the future cash flows if the company
revises it sales downward will be:
9
PV of downward revision = ($285,000 x Α 10 % ) / 1.10
PV of downward revision = $1,492,110.72
Since this is less than the value of abandoning the project, the company should abandon in
one year under the downward revision scenario. So, the revised NPV of the project will be
the initial cost, plus the expected cash flow in year one based on upward sales projection,
plus the expected value of abandonment. We need to remember that the abandonment value
occurs in year 1, and the present value of the expansion cash flows are in year one, so each
of these must be discounted back to today. So, the project NPV under the abandonment or
expansion scenario is:
The company is faced with the decision of when to harvest the lumber. Whatever harvest cycle
the company chooses, it will follow that cycle in perpetuity. Since the forest was planted 20
years ago, the options available in the case are 40, 45, 50, and 55-year harvest cycles. No matter
what harvest cycle the company chooses, it will always thin the timber 20 years after harvests
and replants. The cash flows will grow at the inflation rate, so we can use the real or nominal
cash flows. In this case, it is simpler to use real cash flows, although nominal cash flows would
yield the same result. So, the real required return on the project is:
(1 + R) = (1 + r)(1 + h)
1.10 = (1 + r)(1.037)
r = 0.0608 or 6.08%
The conservation funds are expected to grow at a slower rate than inflation, so the real return for
the conservation fund will be:
(1 + R) = (1 + r)(1 + h)
1.10 = (1 + r)(1.032)
r = 0.0659 or 6.59%
The company will thin the forest today regardless of the harvest schedule, so this first thinning is
not an incremental cash flow, but future thinning is part of the analysis since the thinning
schedule is determined by the harvest schedule. The cash flow from the thinning process is:
Cash flow from thinning = Acres thinned × Cash flow per acre
Cash flow from thinning = 5,000 × ($1,000)
Cash flow from thinning = $5,000,000
The real cost of the conservation fund is constant, but the expense will be tax deductible, so the
after-tax cost of the conservation fund will be:
Excavator piling, broadcast burning, site preparation, and planting costs are the cost of each per
acre times the number of acres. These costs are the same no matter what the harvest schedule
since they are based on acres, not MBF.
Ross et al, Corporate Finance 8th Canadian Edition Solutions Manual
© 2019 McGraw-Hill Education Ltd.
9-26
Now we can calculate the cash flow for each harvest schedule. One important note is that no
depreciation is given in the case. Since the harvest time is likely to be short, the assumption is
that no depreciation is attributable to the harvest. This implies that operating cash flow is equal
to net income. Next we can calculate the NPV of each harvest schedule. The NPV of each
harvest schedule is the NPV of the first harvest, the NPV of the thinning, the NPV of all future
harvests, minus the present value of the conservation fund costs.
Harvest in 20 years
Revenue $40,359,135
Tractor cost 9,870,000
Road 3,525,000
Sale preparation & admin 1,269,000
Excavator piling 875,000
Broadcast burning 1,550,000
Site preparation 750,000
Planting costs 1,125,000
EBIT 21,395,135
Taxes 7,488,297
Net income (OCF) $13,906,838
Thinning will also occur on a 40-year schedule, with the next thinning 40 years from today. The
effective 40-year interest rate for the project is:
We also need the 40-year interest rate for the conservation fund, which will be:
Since we have the cash flows from each thinning, and the next thinning will occur in 40 years,
we can find the present value of future thinning on this schedule, which will be:
PVThinning = $5,000,000/9.5817
PVThinning = $521,825.80
Now we can find the present value of the conservation fund deposits. The present value of these
deposits at Year 20 is:
Harvest in 25 years:
Revenue $47,051,600
Tractor cost 11,480,000
Road 4,100,000
Sale preparation & admin 1,476,000
Excavator piling 875,000
Broadcast burning 1,550,000
Site preparation 750,000
Planting costs 1,125,000
EBIT 25,695,600
Taxes 8,993,460
Net income (OCF) $16,702,140
Thinning will also occur on a 45-year schedule, with the next thinning 45 years from today. The
effective 45-year interest rate for the project is:
We also need the 45-year interest rate for the conservation fund, which will be:
Since we have the cash flows from each thinning, and the next thinning will occur in 45 years,
we can find the present value of future thinning on this schedule, which will be:
PVThinning = $5,000,000/13.2111
PVThinning = $378,470.46
The operating cash flow from each harvest on the 45-year schedule is $16,702,140, so the
present value of the cash flows from the harvest are:
Now we can find the present value of the conservation fund deposits. The present value of these
deposits is at Year 25 is:
NPV = $4,456,093.33
Revenue $49,699,440
Tractor cost 12,110,000
Road 4,325,000
Sale preparation & admin 1,557,000
Excavator piling 875,000
Broadcast burning 1,550,000
Site preparation 750,000
Planting costs 1,125,000
EBIT 27,407,440
Taxes 9,592,604
Net income (OCF) $17,814,836
Thinning will also occur on a 50-year schedule, with the next thinning 50 years from today. The
effective 50-year interest rate for the project is:
We also need the 50-year interest rate for the conservation fund, which will be:
Since we have the cash flows from each thinning, and the next thinning will occur in 50 years,
we can find the present value of future thinning on this schedule, which will be:
PVThinning = $5,000,000/18.0852
PVThinning = $276,469.34
The operating cash flow from each harvest on the 50-year schedule is $17,814,836 , so the
present value of the cash flows from the harvest are:
Now we can find the present value of the conservation fund deposits. The present value of these
deposits is at Year 30 is:
Ross et al, Corporate Finance 8th Canadian Edition Solutions Manual
© 2019 McGraw-Hill Education Ltd.
9-30
PVConservation = –$162,500 – $162,500/23.3024
PVConservation = –$169,473.53
Harvest in 35 years
Revenue $52,057,863
Tractor cost 12,670,000
Road 4,525,000
Sale preparation & admin 1,629,000
Excavator piling 875,000
Broadcast burning 1,550,000
Site preparation 750,000
Planting costs 1,125,000
EBIT 28,933,863
Taxes 10,126,852
Net income (OCF) $18,807,011
Thinning will also occur on a 55-year schedule, with the next thinning 55 years from today. The
effective 55-year interest rate for the project is:
We also need the 55-year interest rate for the conservation fund, which will be:
PVThinning = $5,000,000/24.6310
PVThinning = $202,995.97
The operating cash flow from each harvest on the 55-year schedule is $20,535,286, so the
present value of the cash flows from the harvest are:
Now we can find the present value of the conservation fund deposits. The present value of these
deposits is at Year 35 is:
The company should harvest in 20 years since it has the highest NPV. Notice that when the NPV
began to decline, it continued declining. This is expected since the growth in the trees increases
at a decreasing rate. So, once we reach a point where the increased growth cannot overcome the
increased effects of compounding, harvesting should take place. There is no point further in the
future which will provide a higher NPV.