You are on page 1of 7

7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems

Weldless repair of safety critical piping systems


Safety notice: 4/2005
Issue date: July 2005

Introduction
1. This notice provides advice on safe practice for the repair of piping used on offshore installations and highlights poor practice. It is possible during the design
life of a topside plant of an offshore installation that a pressurised system will require either modification or repair. The modification of a pressurised system is
generally covered by the dutyholder's change control procedures. However, maintenance activities such as patch repair or installation of mechanical clamps may
not be controlled to the same degree, partly due to the absence of a clear policy for piping repair.

Background
2. A major hydrocarbon release incident occurred because an unreliable method of repair was applied to safety-critical pipework. This incident is an example of
failure to select an appropriate repair technique for defects in a piping system.

Philosophy
3. For safety-critical pipework the repair philosophy should be:

replace like for like;


temporary repair until replacement can be carried out;

permanent repair only where replacement is not practical.

This approach is in line with the principles of prevention as outlined in the ACOP and guidance to the Management of Health and Safety at Work Regulations
1999. In particular, paragraph 30 of the guidance advises dutyholders to 'control risks at source, rather than taking palliative measures'.

Back to top

Risk assessment
https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 1/7
7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems

4. Before any repair is undertaken a risk assessment should be carried out to determine the suitability of using pipe repair technique. Factors that should be
considered at this stage include:

an understanding of the degradation mechanism leading to the requirement of pipe repair and evaluation of the current pipe condition;

consideration of full duty conditions for the repair including external loading, vibration, environmental deterioration, fire performance etc;
classification of repair as to whether it covers safety critical pipework and determination of suitable techniques;
determining whether the repair will be temporary or permanent;
the ongoing inspection requirements for the repair and suitable inspection techniques.

A suitable Technical Authority should approve these considerations before the repair proceeds.

Design of the repair


5. The basis of the design of repair should follow a recognised design code or demonstrate the equivalent. Most of the offshore topside piping systems are
designed to ASME B31.3 Process Piping - ASME code for Pressure Piping. In the first instance ASME B31.3 is not intended to apply to the operation,
maintenance or repair of piping systems. The common practice in the oil and gas industry is to use American Petroleum Institute (API) 570, the piping code for the
inspection, repair, alteration and re-rating of in-service piping systems According to API 570, the principles of ASME B31.3 shall be followed for repair and
alteration of piping system designed to ASME B31.3.

6. In order to follow the principles of ASME B31.3, the repair should meet the installation and operational requirements of piping systems. These requirements can
be divided into two categories: structural and functional. The former requirement relates to static strength and fatigue performance, while later include assembly,
installation and sealing.

7. For static strength, the repair should be designed to withstand design live loads as well as any cyclic loads imposed on the damaged pipework. To fulfil
functional requirement the repair should be made (ie assemble or disassemble) in a reliable manner consistent with the assumptions made in the analysis to
demonstrate compliance with both static and fatigue strength criteria. Where the repair has to contain internal or external pressure, seals should be provided that
remain functional after installation and during operation.

8. The static strength and fatigue performance of a repair should be validated by recognised finite element or engineering analysis with some degree of
experimental verification of the results.

9. Analytical modelling of variables, such as surface contact, surface roughness and friction is difficult and unreliable. These variables affect the functional
performance of repair in terms of assembly and sealing. Tests shall be conducted to demonstrate that the repair meets the functional requirements. Testing has to
include use of full-scale prototypes, under conditions equivalent to, or more stringent than, those expected during operation.

Back to top

Types of repairs
https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 2/7
7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems

10. Common practice for non-welded pipe repairs employed offshore fall into five broad categories:

wraparound, off-the-shelf, elastomer lined mechanical clamps;

engineered clamps manufactured to order;


off-the-shelf pipe connectors;
engineered pipe connectors manufactured to order;
composite overwrap repair, which basically comprises of a woven glass fibre or carbon fibre mat impregnated with a curable resin. This type of repair fall
into two groups – off-the-shelf repair kit or engineered design to suit particular applications.

11. Many off-the-shelf clamps and connectors available for use offshore have type approval from a number of inspection authorities. A type approval is an
approval of a representative item of equipment endorsed by an independent inspection authority such as Lloyds Register or DNV after appraisal/audit of design
and test documentation. There may be limitation on the approval for material of construction, pressure and temperature. Before using such repairs, the dutyholder
should make sure that all the structural and functional requirements have been considered in the approval process. For example, for off-the-shelf clamps, in
addition to the usual design pressure and temperature loads, the design approval shall include control of axial thrust loads if the damaged piping being clamped
has insufficient strength to control the pressure thrust. The effect of clamping and crushing forces on the damaged piping shall also be considered in the design
approval.

12. Further advice on the use of repair clamps is provided in the HSE publication 'Leak Sealing Repair Clamps[1]'.

13. For an engineered repair solution, it is common practice to carry out a 'fitness-for-purpose' engineering assessment. This includes: detailed design
assessment of repair for process and mechanical requirements; conformance to code requirements; and evaluation of all necessary specifications, drawings and
supporting documents.

Back to top

Installation of repair
13. For the installation of the off-the-shelf clamps or connectors manufacturer's instructions should be followed in full.

14. Even the simplest repair method, when applied without due attention to training, may result in integrity problems. It should be emphasised that only trained
and competent personnel should be used for applying any off-the-shelf repair kit or engineered design repair on piping systems.

Inspection
15. All the weldless repair method utilised to repair a damaged pipe should be regarded as placing a pressure vessel around the damaged area (no welding is
involved or substituted). In these situations the dutyholder must consider the life cycle of the repaired pipe system; will the internal metal loss of the pipe
underneath the repair continue or will degradation of the repair occur? These considerations will dictate the need to undertake periodic inspection and/or testing of
the repair.
https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 3/7
7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems

16. For all pipe repairs, the operator needs to perform a structured risk assessment that includes consideration of all the potential future damage or deterioration
mechanisms (see paragraph 4). The output from this risk assessment will typically be the specification of the necessary inspection and testing activities, and
associated periodicities, to ensure continuing 'fitness-for-purpose'.

Back to top

Maintenance
17. It is recommended that dutyholders maintain a register of piping repairs to improve the ease of monitoring the integrity of the repair throughout its design life.
This provides an immediate overview of the number and location of repairs and should also detail the installation date, inspection requirement and intended
replacement date.

Management system
18. Dutyholders should review their safety management system for the non-welded repair of piping system to ensure that the management system recognises the
specialist knowledge, skills and competence required for:

design or selection of repairs;


installation of a repair;
inspections of a repair.

Relevant legal requirements


1.

Health and Safety at Work etc Act 1974;

the Provision and use of Work Equipment Regulation 1998 SI 1998/2306 The Stationery Office 1998 ISBN 0 11 085625 2;
the Management of Health and Safety at Work Regulation 1999 SI 1999/3242 The Stationery Office 1999 ISBN 0 11 025051 6; and
Offshore Installations and Wells (Design and Construction etc) Regulations 1996 SI 1996/913 The Stationery Office 1996 ISBN 0 11 054451 X

There are legal duties on both the owner/operator of the plant and on those who carry out the repair and/or modification

Back to top

References
19. You can find additional information in the following publications:

https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 4/7
7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems

Management of health and safety at work. Management of Health and Safety at Work Regulations 1999. Approved Code of Practice and guidance L21
(Second edition) HSE Books 2000 ISBN 0 7176 2488 9
ASME B31.3 (ASME Code for pressure piping, An American National Standard)
API 570 [Piping Inspection Code –Inspection, repair, alteration, and rerating of in service piping system]

Leak sealing repair clamps[2]

Further information
Any queries relating to this notice should be addressed to:

Health and Safety Executive

Hazardous Installations Directorate

Offshore Division

Lord Cullen House

Fraser Place

Aberdeen

AB25 3UB

Tel: 01224 252500

Fax: 01224 252615

This guidance is issued by the Health and Safety Executive. Following the guidance is not compulsory and you are free to take other action. But if you do
follow the guidance you will normally be doing enough to comply with the law. Health and safety inspectors seek to secure compliance with the law and may
refer to this guidance as illustrating good practice

Back to top

Resources
Offshore publications[3]

Research reports[4]
Offshore statistics[5]

Related content
HSE's Sector and Health priority plans[7]
Diving [8]
https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 5/7
7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems
[9]
Pipelines
Electricity [10]
Carbon capture and storage [11]

Regulating major hazards [12]


Offshore Major Accident Hazards Advisory Committee (OMAHAC)[13]
Safety bulletin[14]

Link URLs in this page


1. Leak Sealing Repair Clamps

https://www.hse.gov.uk/chemicals/rclamps.htm
2. Leak sealing repair clamps

https://www.hse.gov.uk/chemicals/rclamps.htm
3. Offshore publications

https://www.hse.gov.uk/offshore/publications.htm
4. Research reports

https://www.hse.gov.uk/offshore/researchreports.htm
5. Offshore statistics

https://www.hse.gov.uk/offshore/statistics/index.htm
6. More resources

https://www.hse.gov.uk/offshore/resources.htm
7. HSE's Sector and Health priority plans

https://www.hse.gov.uk/aboutus/strategiesandplans/sector-health-plans.htm
8. Diving microsite

https://www.hse.gov.uk/diving/index.htm
9. Pipelines microsite

https://www.hse.gov.uk/pipelines/index.htm
10. Electricity microsite

https://www.hse.gov.uk/electricity/index.htm
11. Carbon capture and storage microsite

https://www.hse.gov.uk/carboncapture/index.htm
12. Regulating major hazards microsite

https://www.hse.gov.uk/regulating-major-hazards/index.htm

https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 6/7
7/8/2021 HSE Offshore: Safety Notice 4/2005 - Weldless repair of piping systems

13. Offshore Major Accident Hazards Advisory Committee (OMAHAC)

https://www.hse.gov.uk/aboutus/meetings/iacs/oiac/index.htm
14. Safety bulletin

https://www.hse.gov.uk/safetybulletins/index.htm

https://www.hse.gov.uk/offshore/notices/sn_04_05.htm 7/7

You might also like