Professional Documents
Culture Documents
The SPI and CPI are affected by the EV settings since the variables EV and PV take different values
depending on the EV setting that has been selected by the user in tandem with the status of the concerned
task(s) in the Baseline Programme that has been assigned to the Current programme. With regard to the
PV in particular, it appears to be different only for the tasks that were ‘In Progress’ in the BSL
programme.
The formula for calculating the PV in case the cost is distributed linearly along the duration of an activity
is:
a. PV = 0
(If DD < or = BSL Planned Start)
b. PV = [(DD – BSL Start) / BSL At Complete Duration] * BSL Budgeted Total Cost
(If Planned Start < DD < BSL Planned Finish)
So, excluding cases (a) & (c) where the value of PV is constant – depending on the condition in the
parenthesis, the only case where the PV depends upon other variables is case (b).
Let’s see what the effect of these variables to the SPI and CPI is separately.
SPI = EV / PV = [Activity (%) Complete * BAC / (DD – BSL Start) * BAC] * BSL At Complete
Duration →
→ SPI = [BSL At Complete Duration / (DD – BSL Start)] * Activity (%) Complete
Looking at the equality above the only variables that relate to the Baseline Programme and are affected by
the EV settings are:
In conclusion, the ‘Budgeted values with planned dates’ might be used only when the BSL Programme
refers to the originally planned and approved programme wherein no actuals are apparent. In all other
cases one of the other two options must be used, depending on whether the ‘At completion cost’ of the ‘In
Progress’ tasks in the assigned BSL programme has been updated or not.