You are on page 1of 95

MAHANAGAR SEVA SADAN

“SARDAR PATEL BHAVAN”, Danapith, Ahmedabad – 380 001


Ph. No. (079) 25391811, 25391830 Fax No. (079) 25350926
Web site: www.ahmedabadcity.gov.in Email: info@ahmedabadcity.gov.in

========================================================================
Tender No:

Construction of RCC Retaining Wall at Mithakhali Underpass on


Mithakhali side only.

VOLUME – I

CONDITIONS OF CONTRACT
AND
TECHNICAL INFORMATION

SEPTEMBER 2021
Ahmedabad Municipal Corporation Contents

AHMEDABAD MUNICIPAL CORPORATION


MAHANAGAR SEVA SADAN

NAME OF WORK: CONSTRUCTION OF RCC RETAINING WALL AT MITHAKHALI


UNDERPASS ON MITHAKHALI SIDE ONLY.

C O N T E N T SVOLUME – I

Sr. Page
Particulars
No No.
Invitation for Bid 1
Information for Bidders 2
Tender Declaration Form 7
Section-I INSTRUCTIONS TO BIDDERS
A General 9
1 Scope of Bid 9
2 Source of Funds 9
3 Eligible Bidders 9
4 Qualification of the Bidder 9
5 One Bid per Bidder 10
6 Cost of Bidding 10
7 Site Visit 10
B Bidding Documents 11
8 Content of Bidding Documents 11
9 Clarification of Bidding Documents 11
10 Corrigendum of Bidding Documents 11
C Preparation of Bids 12
11 Language of the Bid 12
12 Documents comprising the Bid 12
13 Bid Prices 12
14 Currencies of Bid and Payment 12
15 Bid Validity 13
16 Bid Security 13
17 Alternate Proposals by Bidder 13
18 Format and Signing of Bid 13
D Submission of Bids 14
19 Sealing and Marking of Bids 14
20 Deadline for Submission of the Bids 14
21 Late Bids 14
22 Modification and Withdrawal of Bids 15
E Bid Opening & Evaluation 16
23 Bid Opening 16
24 Deleted 16
25 Clarification of Bids 16
26 Examination of Bids and Determination of Responsiveness 16
27 Correction of Errors 17
28 Employer’s Rights 17
Ahmedabad Municipal Corporation Contents

Sr. Page
Particulars
No No.
29 Evaluation and Comparison of Bids 17
30 Requirement 17
F Award of Contract 18
31 Award Criteria 18
32 Employer's Right to Accept any Bid and to Reject any or all Bids 18
33 Notification of Award and Signing of Agreement 18
34 Security Deposit 18
35 Advance Payment and Security 18
36 Dispute Review Expert /Arbitration 19
37 Corrupt or Fraudulent Practices 19
Section-II ANNEXURES
Annexure-I Affidavit 20
Annexure-II Undertaking 21
Annexure-III Letter of Acceptance 22
Annexure-IV Agreement Form 23
Annexure-V Issue of Notice to Proceed with the work 24
Annexure-VI Bank Guarantee for Bid Security 25
Annexure-VII Bank Guarantee for Security Deposit 26
Annexure- VIII List of Approved Banks 27
Annexure- IX ( Deleted) 28

Section-III GENERAL CONDITIONS OF CONTRACT AND SPECIAL


CONDITIONS OF CONTRACT
A General 29
1 Definitions 29
2 Interpretation 30
3 Language and Law 31
4 Engineer's Decisions 31
5 Delegation 31
6 Communications 31
7 Deleted 31
8 Subcontracting 32
9 Personnel 32
10 Employer’s and Contractor's Risks 32
11 Employer's Risks 32
12 Contractor’s Risks 33
13 Insurance 33
14 Site Investigation Reports 34
15 Queries about the Contract Data 34
16 Contractor to Construct the Works 34
17 The Works to be completed by the Completion Date 35
18 Approval by the Engineer 35
19 Safety 36
20 Discoveries 36
21 Possession of the Site 36
22 Access to the Site 36
Ahmedabad Municipal Corporation Contents

Sr. Page
Particulars
No No.
23 Instructions 37
24 Deleted 37
25 Settlement of Disputes 37
26 Deleted 37
B Time Control 38
27 Program 38
28 Extension of the Intended Completion date 38
29 Deleted 38
30 Delay order by the Engineer 38
31 Management Meetings 39
32 Early Warning 39
C Quality Control 40
33 Identifying Defects 40
34 Tests 40
35 Correction of Defects 40
36 Uncorrected Defects during defect liability period 40
D Cost Control 41
37 Schedule-B ( Volume-3 Financial Bid) 41
38 Deleted 41
39 Variations (Excess, saving or Non Tender Item) 41
40 Payment for Variations (Excess, saving or Non Tender Item) 41
41 Deleted 42
42 Payment Certificates 42
43 Payments 42
44 Deleted 43
45 Taxes, cess & duties 43
46 Currencies 43
47 Price Variation for Bitumen brought by Contractor 43
48 Retain from Each Interim Payment Certificate (R A Bill) 43
49 Liquidated Damages 45
50 Deleted 45
51 Advance Payment 45
52 Securities Deposit 45
53 Deleted 45
54 Cost of Repairs 45
E Finishing the contract 46
55 Completion 46
56 Taking Over 46
57 Final account 46
58 As-built Drawings 46
59 Termination 46
60 Payment upon Termination 47
61 Property 47
62 Release from Performance 47
62.2 Defect Liability Period 48
Ahmedabad Municipal Corporation Contents

Sr. Page
Particulars
No No.
F General Description & Scope of Work 49
63 Scope of work 49
64 Climatic Conditions 50
65 Marketing Centres 50
66 Housing, Water Supply and Drainage etc. 50
67 Facilities 50
68 Materials, plant and workmanship 51
69 Personnel and Labour Employment 52
70 Program Through Net Work Technique 52
71 Foreign Exchange Requirement 53
72 Relation with Public Authorities 53
73 Register to be Maintained 53
74 Equipment and Accessories 54
75 Patent rights 54
76 Royalties 55
77 Urgent remedial works 55
78 Special risks 55
79 Force Majeure 56
80 Changes in cost & legislation 56
81 Safety aspects 56
82 Drawings and contract documents 57
82.3 Photographs of the work 57
G Special Conditions of Contract 58
83 Special Conditions of Contract 58
84 Labour 58
85 Compliance with labour regulations 58
Salient features of some major laws applicable to establishments
86 59
engaged in building and other construction work.
87 Minimum Requirement of Equipments for the work 60
88 Avoidance of damage of roads 61
89 Transports of Contractor’s Equipment 61
90 Contractor to keep site clean 61
91 Defaults by Contractor 61
92 Maintaining Public Traffic 61
93 Prevention of nuisance and pollution 62
94 Fencing and Lighting 62
95 Action where no Specifications 62
96 Decision of the Client to be final 62
97 Damage by storms, Fire, rains or accidents 62
98 Batch Mix Plant 63
99 Providing transportation facility for AMC staff 63
100 Tax, Duties on Materials 63
101 Submission of project schedule: 63
102 Testing charge 63
103 Bitumen 63
104 Production of Hot mix material 64
Ahmedabad Municipal Corporation Contents

Sr. Page
Particulars
No No.
105 Laboratory at Plant 64
106 Payment of Bituminous work 64
107 Transportation of Bitumen 64
Section-IV CONTRACT DATA 66
Section-V WORK PLAN AND TECHNICAL SPECIFICATIONS 70
A Project Features and Work Planning 70
B Technical Specifications 73
C Additional Specifications 76
Amendments / Modifications / Additional to Existing clauses of General
D 85
Technical Specifications

E Item wise technical specifications – Civil works 89


Ahmedabad Municipal Corporation Bid Information

INVITATION FOR BID

Ahmedabad Municipal Corporation


Sardar Patel Bhavan, Danapith, Ahmedabad - 380 001
Website:www.ahmedabadcity.gov.in

NAME OF WORK: CONSTRUCTION OF RCC RETAINING WALL AT MITHAKHALI


UNDERPASS ON MITHAKHALI SIDE ONLY.

1. The Municipal Commissioner, Ahmedabad Municipal Corporation invites bids for the
construction of works detailed in the Table below from the bidders meeting Eligibility
Criteria & qualifying criteria.

Sr. Name of Work Estimated Bid Security Cost of Period of


No. Amount put to (Rs.) Bid Completion
tender(Rs.) Document
(Rs.)
1 2 3 4 5 6
1 Construction of RCC Retaining Rs. Rs. 2,36,674/- 3,600/- Total time limit
Wall at Mithakhali Underpass 2,36,67,389.39 In form as is 9 months
on Mithakhali side only. stipulated in (Excluding
tender. monsoon)
Tobe enclosed
along with the
technical bid.

2. The tender can be downloaded from the website www.nprocure.com from 3/9/2021 to
239/2021 upto 18:00 hour.
3. Bids must be accompanied by security of the amount specified for the work in the table,
payable at Ahmedabad and drawn in favour of Municipal Commissioner, Ahmedabad.
Bid security will have to be in any one of the forms as specified in the bidding document
and shall have to be valid for 30 days beyond the validity of the bid.
4. E-tender must be submitted on line on or before 23/9/2021 upto18:00 hours.
Submission of hard copy of bid security, Tender fee, tender volume and other
documents in two copies (original & duplicate) in sealed cover in person to office of
AMC as mentioned in bid information on or before 16:00 hours on 24/09/2021.Technical
bid will be opened on 24/09/2021 at 17:00 hours in the office of the City Engineer, in the
presence of the bidders who wish to remain present. If the office happens to be closed
on the date of receipt of the bids as specified, the hard copy of bids will be received and
opened on the next working day at the same time and venue.
Financial bid–Volume-3 shall be submitted online only.
Un priced BOQ duly signed and stamped by tenderer in hard copy (original
+ duplicate) to be submitted along with volume 1 & 2.
5. If any clarifications are required, regarding the bidding document the same can be
th
obtained from the City Engineer, Ahmedabad Municipal Corporation, 5 Floor, Sardar
Patel Bhavan, Dana pith, Ahemdabad on any working day or during pre-bid meeting.
6. Other details can be seen in the bidding documents.
7. Conditional tender will not be accepted. Municipal Commissioner reserves the right to
reject any or all of the tenders without assigning any reason thereof.

Municipal Commissioner
Ahmedabad Municipal Corporation
Ahmedabad

Signature of Bidder 7 AMC


Ahmedabad Municipal Corporation Bid Information

AHMEDABAD MUNICIPAL CORPORATION

INFORMATION FOR BIDDERS

Municipal Commissioner of A.M.C. invites percentage rate sealed tenders from interested
contractors forthe following work at different locations within the limit of A.M.C.

1 Name of work Construction of RCC Retaining Wall at Mithakhali Underpass on


Mithakhali side only.
2 Amount put to Tender Rs. 2,36,67,389.39
3 Time Limit Total time limit is 9 months (Excluding monsoon)
4 Download of e-tender E-Tender shall be downloaded from the website www.nprocure.com from
Documents date 3/9/2021 to 23/9/2021 upto 18:00 hour.
5 Required registration Contractor registered with Ahmedabad Municipal Corporation or
Government of Gujarat in Class ‘B’ Category or contractors registered in
similar class with other state government, semi government bodies or with
Central PWD.
If Successful bidder is not registered with AMC, they will have to apply
within one month from date of receiving of letter of intent.
6 Preliminary Average annual financial turnover during the Last 3 years, ending 31st
prequalification criteria March 2021 of the previous financial year, should be at least 30% of the
of bidding firm estimated cost of work put to tender, i.e. Rs. 71,00,217/- for this work.
(detailed criterias are Experience of having successfully completed similar works during last 7
given in the Bid years should be either of the following.
Document)
a. Three Similar completed works costing not less than the amount equal
to of Rs. 94,66,956/- (40 % of Estimated cost of work put to tender)
OR
b. Two Similar completed works costing not less than the amount equal
to of Rs. 1,18,33,695/- (50 % of Estimated cost of work put to tender)
OR
c. One Similar completed work costing not less than the amount equal to
of Rs. 1,89,33,912/- (80 % of Estimated cost of work put to tender)

Similar work shall mean construction of any type of RCC Civil Concrete
structure work carried out for structures like retaining wall, water retained
structure, RCC box, RCC culverts, Jetty, bridge, flyover, PQC / RCC
Road, etc.
7 Solvency certificate
The bidder has to submit solvency certificate for any approved bank of
AMC as per Annexure IX of Volume-1 having an amount equal to 20% of
amount of the estimated cost put to tender. If he fails to produce such
certificate his bid will not be considered. The solvency should be duly valid
at the time of submission.
8. Tender Fee (Non Rs.3,600(Demand Draft in favour of Municipal Commissioner, Ahmedabad
refundable) payable at Ahmedabad).

9. Bid Security (EMD) Rs.2,36,674/- (in the form of Demand draft/ Bank Guarantee/Pay Order
of banks as mentioned in Annexure-VIII in favour of Municipal
Commissioner, Ahmedabad valid for 150 days(120+30) from last date of
submission of Hard copy of tender. Bid submitted without bid security
shall be treated as non responsive and shall be summarily rejected.
10. Pre-bid Meeting Due to Pandemic situation no physical pre-bid meeting shall be held.
If any clarifications are required, regarding the bidding document the same
can be raised by email on ceamc@ahmedbadcity.gov.in before
09/09/2021 up to 12:00 pm. If any query is raised after 09/09/2021 up to
12:00 pm shall not be considered.
11. Last Date of online 23/9/2021 upto 18:00 Hours
submission
Signature of Bidder 8 AMC
Ahmedabad Municipal Corporation Bid Information

12. Last Date of Date:-24/9/2021 up to 16:00 hours at


submission of hard Office of The Assistant Manager (Project), PWA Department, B-Wing , 2nd
copy Floor, Sardar Patel Bhavan, Danapith, Ahmedabad Municipal Corporation,
Ahmedabad – 380 001.The hard copy of tenders received after this date
and time shall not be entertained under any circumstances. Tender shall
be submitted in two copies (Original & Duplicate).
Financial bid – volume-3 to be submitted online only.
Unpriced BOQ duly signed & stamp by tenderer in hard copy (Original +
Duplicate) to be submitted.
13. Opening of Technical Date:24/9//2021 Time: 17:00 Hours
Bids Place: Office of The Assistant Manager (Project),PWA Department, B-
Wing , 2nd Floor, Sardar Patel Bhavan, Danapith, Ahmedabad
Municipal Corporation, Ahmedabad – 380 001.
14. Opening of Financial Shall be intimated later.
Bids
15. Tender (Bid) Validity 180 days from the date of submission of the tender.
Period
16 Defect Liability Period Defect liability period from the date of completion (as per completion
certificate, which shall be issued by AMC) of work shall be as follows:
(a) One year or one completed monsoon whichever is later for
approaches & allied civil works.
(b) Three year for wearing surface (Bituminous work)
17 Liquidated Damages 100% of work by end of time limit.
i.) If the contractor fails to complete the work under contract by the
stipulated date, he shall pay liquidated damages of at the rate of
0.1 percentage of the contract value per day from the date of
delay the said work up to the date of completion and handing over
the Government.
ii.) However also if the contractor fails to complete any part of the
work as designed in Schedule (c) by the time indicated against
such part, he shall pay Liquidated damages per day from the date
of delaying the said part of the work up to the date of completion
of the said designed part at the rates shown in the said schedule
of the contract value of such part for such failure till the said
designed part is completed.
iii.) The aggregate maximum of liquidated damages payable under
tender clause shall not exceed 0.10 Percentages of contract value
per day and shall be subject to the maximum amount of ten(10)
percentage of the estimated amount put to tender.
iv.) Delay requiring payment of ten percentage liquidated damages of
the amount put to tender for performance shall be sufficient
causes for termination of contract and for forfeiture of security
deposit including amount of performance bond in respect of works
estimated to cost more than Rs. 15 Lakh, for performance and
registration of the contract shall also be kept in abeyance for three
years from the date as fixed in all cases.
18 Security Deposit In the form of Bank Guarantee of bank as mentioned in Annexure-VII in
favour of Municipal Commissioner, Ahmedabad amount equal to 3%
amount of Contract Price valid till 90 days beyond Date of completion
work. The Security Deposit shall be payable in 15 days from date of
receipt of LOA failing which interest @4% per annum will be charged by
AMC.(As per M.C. circular 24 date 10.08.2021)
19. Money Retention Money -1: @2% of the value of work done will be deducted
and Performance from each RA Bill. It will be released along with the release of Payment of
Security Final Bill.
Retention Money-2 Performance security for Defect Liability:
(a) For Approaches and Allied works other then bituminous work
@ 3% of the value of each Running Bill will be deducted including
amount of extra items.
The defect liability period shall be calculated from the date of completion
mentioned in the Completion Certificate of Approaches and allied works
Signature of Bidder 9 AMC
Ahmedabad Municipal Corporation Bid Information

other than bituminous work. This retention money-2 (a) will be released
as per Contract Data.
(b) For Bituminous work:
@ 10% amount of bituminous work including price escalation shall be
deducted from the running bill against Defect Liability /Performance
Guarantee.
The defect liability period shall be calculated from the date of completion
mentioned in the Completion Certificate of bituminous work.
This retention money-2 (b) will be released as per Contract Data.
20. Labour Welfare Cess Labour Welfare Cess as per the Act, 1996 (non refundable) shall be
deducted from each running bill on prevailing rate. Present rate is 1 % of
value of bill amount.
21 Material Testing 0.5% of value of work done shall be deducted from each running bill as
charges testing charges for testing to be carried out at AMC test lab. With final bill,
actual charges of testing shall be adjusted.
22 Income tax & other Income tax & other taxes shall be deducted as per government rules and
taxes circulars.
23 Performance Bond As per Clause 29 of contract data.
The Municipal Commissioner,
24 Officer Inviting Bids Ahmedabad Municipal Corporation,
Ahmedabad.

Appendix-A
List of Approved Make for Materials (Civil works)

Cement : The contractor shall procure cement from reputed manufactures of


cement having a production capacity of one single plant not less than
one million tonnes per annum and holding license to use ISI
certification mark for their product.
Mid Steel : Mild steel for dowel bar shall confirm to IS 432 Grade-2
Reinforcement Steel : Clause no 1009.3.1 of ministry's specifications for road and bridge
works shall be amended as per superintending Engineer-S&R
(bridges) for Director General (Road development) &SS.
"All steel shall be procured from producers who manufacture billets
directly from iron ores and roll the billets to produce steel conforming
to IS: 1786. No re-rolled steel shall be incorporated in the works. The
steel shall also be procured from other producers provided it is
manufactured from the billets made directly from iron ores and not
from shredded scrap and sponge iron as basic feedstock. In such
cases, the other producers will have to submit the proof of purchase
such as GST, Invoice etc from the billet producers to establish that
billets are made directly from iron ores and have been procured from
them. The steel shall be got tested by the Engineer in the NABL
affiliated laboratories only as a third party check. It shall be ensured
that all the test results conform to IS: 1786."
"For the steel procured from producers who manufacture billets
directly from iron ores also, the Engineer / Employer may carry out
checks on materials through third party as mentioned above, for
conforming to the test results shown in the certificates so as to
ensure the quality of steel supplied."
Structural Steel : SAIL, TATA, Essar, Jindal (JSW), Surya
Epoxy Paint : Pidilite, Fair mate, Fosroc, Berger, MSC-Bauchemie, Asian Paint,
Nerolac, Sunanda ,
Coal Tar Epoxy Paint : Pidilite, Fair mate, Fosrock, BASF, Berger, MC-Bauchemie, Shalimar,
Asian Paint, Nerolac ,Sunanda
Paint & Distempers : Asian, Berger. Nerolac, Fosrock, MC-Bauchemie, BASF, Sunanda

Signature of Bidder 10 AMC


Ahmedabad Municipal Corporation Bid Information

Note:

1) Conditional tenders will not be accepted in any case. Municipal Commissioner reserves the
rights to reject any or all the tenders without assigning any reasons thereof.

2) The authorized signatory holding Power of Attorney shall only be the Digital Signatory. In
case authorized signatory holding Power of Attorney and Digital Signatory are not the same,
the bid shall be considered non-responsive.

Seal and Signature of the Bidder City Engineer


Date: Ahmedabad Municipal Corporation
Ahmedabad

Signature of Bidder 11 AMC


Ahmedabad Municipal Corporation Bid Information

SCHEDULE OF BIDDING PROCESS

Sr.
Event Description Date
No.

1 Bid Documents available online from 3/9/2021

2 Last date of online submission 23/9/2021 up to 18:00 Hours

3 Last date of physical submission Date: 24/9/2021 up to 16:00 hours

Due to Pandemic situation no physical


4 Pre bid meeting
pre-bid meeting shall be held.

5 Opening of Technical Bid Date: 24/9/2021 Time: 17:00 Hours

6 Opening Of Price Bid Shall be intimated.

7 Validity of Bid 180 days

Seal and Signature of the Bidder City Engineer


Date: Ahmedabad Municipal Corporation
Ahmedabad

Signature of Bidder 12 AMC


Ahmedabad Municipal Corporation Bid Information

INFORMATION TO TENDERERS

1. Water, Electricity:- Contractor shall have to make his own arrangements for water and
electricity for the construction work at site at his own expense.

2. Tender which do not fulfil all or any of condition or are submitted incomplete in any
respect or are conditional tenders, will be rejected. Municipal Commissioner reserves
the rights to reduce / increase the Scope of Work to any extent without assigning any
reason thereof.

3. No price escalation shall be paid/ recovered for the works mentioned in the tender for
work done, cement and steel (Reinforcement as per IS 1786) except bitumen (VG-30).

4. Machinery advance or materials advance will not be given.

5. Mobilization advance will not be given.

6. For item requiring bitumen consumption, the contractor shall have to procure the
bitumen of required grade and quantity from the approved Oil company of AMC i.e.
either from IOCL / BPCL / HPCL. only. In case approved oil company of AMC is failed
to Supply required bitumen within stipulated time frame and if progress of work is
hampered due to non-availability of bitumen, the Contractor is bound to purchase
bitumen directly from IOCL / BPCL / HPCL and liable to complete the work within time
limit. Contractor shall have to submit original bill to AMC. Measurement of the bitumen
or the bitumen item will not be written in MB, if original bills are not submitted for the
quantity consumed.

7. The Engineer-in-charge of the entire work will be the City Engineer, AMC, Ahmedabad
and or his representative who will be operating the tender.

8. Conditional tenders will not be accepted.

9. The sequence of operation shall be decided in consultation with the Engineer-in-charge.


The contractor shall prepare the detail program of work in Bar Chart form and get the
approval from the City Engineer, AMC, Ahmedabad before start of work.

10. For all other information refer tender document.

11. Batch mix plant will be used for bituminous items.

Signature of bidder: City Engineer


Date: Ahmedabad Municipal Corporation
Ahmedabad

Signature of Bidder 13 AMC


Ahmedabad Municipal Corporation Bid Information

TENDER DECLARATION FORM

To,
City Engineer
Bridge& Road Project
Ahmedabad Municipal Corporation
Ahmedabad.

Name of work: Construction of RCC Retaining Wall at Mithakhali Underpass on Mithakhali side
only.

Dear Sir,

I/We the undersigned have carefully gone through and clearly understood the Tender
documents of above mentioned project comprising of Notice Inviting tenders, Articles of
Agreement, Scope of work, Definition of terms, notes Instructions/Information to Bidder,
Condition of Contract, special condition of contract, Appendices, Specifications, schedule-B
(Volume-3 Financial Bid) furnished by AHMEDABAD MUNICIPAL CORPORATION.

I/We do hereby offer to execute and complete the whole of the work within the time specified all
in accordance with the specification, designs, drawing and instruction in writing referred to in the
said document and with such materials as mentioned for, at the respective rates which I/we have
quoted in the financial bid or at such other rates as maybe fixed under the provisions of these
conditions.

In the event of this tender being accepted I/We agree to enter into an agreement and when
required, execute the contract, according to your form 1 of agreement as or in default where of
I/we bound myself/ourselves to forfeit the "Bid Security."

I/We understand that if I/We shall not enter in agreement within fifteen days or as decided by
AMC from the date of receipt of letter of acceptance, you will forfeit the Bid Security paid by
me/us and take necessary action as deemed fit.

I/We have enclosed a Demand Draft / Bank Guarantee as an “Bid Security", for the sum as
mentioned in NIT, the full value of which is to be absolutely forfeited to the Employer If I/We fail
to commence the work specified. Otherwise the Employer shall retain the said sum, as on
account of such Security Deposit as provided for in the aforesaid documents.

I/We agree not to employ sub-contractors other than those that may be approved in accordance
with conditions in the aforesaid documents.

I/We understand that Municipal Commissioner is not bound to accept the lowest or any tender,
which are received. I / We also understand & agree that Municipal Commissioner Reserves the
right to allot number of tenders to successful bidders at his sole discretion in case if I / We
am/are lowest in more than one tender.

I/We am/are bound to execute the job if the work order is issued within 120 days from the date of
opening of the tender.

I am bound to execute the work by maintaining all Quality aspects/parameters mentioned in the
tender terms and conditions. I am also bound to submit all supporting Genuine Original
documents as and when asked and if any discrepancy found in such documents as well as in
the executed Work with respect to Quality/Quantity at any stage of work or even after completion
of work, it will be solely my Responsibility. I am bound to prove originality of all documents
submitted by me and if any Documents found false/fake then Municipal Commissioner/AMC has
right to take any action/penalty/punishment against me.

Signature of Bidder 14 AMC


Ahmedabad Municipal Corporation Bid Information

I am also bound that if I/we, indulged into any malpractice and/or used any inferior quality and/or
the construction of road is found to be of an inferior quality under this contract than in such case
Municipal Commissioner/AMC has right to debar/blacklist permanently.

I/We agree to pay the Government income-Tax, GST, Royalty on material (i.e. Aggregate, Sand
etc.) And any other taxes prevailing and from time to time on such items on which the same are
liveable and the rates quoted by me/us are inclusive of the same.

Yours faithfully

Date:
Seal and Sign of the Bidder

Signature of Bidder 15 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

Section I: Instructions to Bidders


A. General

1.0 Scope of Bid

1.1 The Municipal Commissioner, Ahmedabad Municipal Corporation (referred to as Employer in


these documents) invites sealed bids for the construction of works (as defined in these
documents and referred to as “the work”) detailed in the table given in the Invitation for Bid
(hereinafter called as IFB.) from competent bidders The bidders may submit bids for the works
detailed in the table given in IFB.

1.2 The Successful Bidder will be expected to complete the works within intended completion
period specified in the Contract data.

1.3 Throughout these bidding documents, the terms; bid’ and ‘tender’ and their derivatives (bidder/
tenderer, bidding/tendering etc.) are synonymous.

1.4 Blank bidding documents are to be downloaded from website of or www.nprocure.com

1.5 Bidders shall not have any dispute or claim for any kind of compensation,

i) If the quantity stipulated in the tender items varies or the scope of work changes and
thereby total amount of work increases / decreases up to any extent.

ii) If the works gets delayed / postponed for some administrative / technical decision
whatsoever.

iii) If the items stipulated in the tender shall not be executed as per site condition/
requirements. No claim shall be entertained for the same.

iv) No idle charges shall be paid to contractor for machinery and man power if remains idle
and no claim shall be entertained for the same.

2.0 Source of Funds

For this project, the Employer has arranged funds from own resources.

3.0 Eligible Bidders

3.1 This Invitation for Bids is open to all bidders having/meeting eligibility Criteria mentioned in the
bid information.

4.0 Qualification of the Bidder

4.1 The Bidder is required to show his capability to execute the job within the specified time frame
and up to the required quality standards. To do so, the bidder is encouraged to go through
volume–II. Qualification Document and furnish necessary data in respect of plant and
machinery, manpower experience and financial resources to demonstrate his eligibility for
successful implementation of the project.

The bidders should, however, undertake their own studies and furnish with their Bid, a detailed
construction planning and methodology supported with necessary drawings and calculations
to allow the Employer to review their proposals. The numbers, types and capacities of each
plant/equipment shall be shown in the proposals along with the cycle time for each operation
for the given production capacity to match the requirements.

The bidder shall ensure the availability of minimum key personnel for this project. Detailed
bio-data of Project Manager and Materials & Quality Control engineer shall be
submitted as part of Technical Bid. The bidder, however, can make its own assessment

Signature of Bidder 16 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

and is free to propose his/her own site organisation.

4.2 Dis-qualification

Even though the bidders meet the above qualifying criteria, they are subject to be disqualified
if they have,

a. Made misleading or false representations in the forms, statements, affidavits and attachments
submitted in proof of the qualification requirements; and/or
b. Record of poor performance such as abandoning the works, not properly completing the
contract, inordinate delays in completion, litigation history, or financial failures etc. etc.
c. Colluded with other prospective bidders for this work to arrive at quoted prices for the purpose
of restricting competition.
d. Indulged in inducement of any official of AMC and/or their consulting engineer and other
advisors in any manner whatsoever.
e. Not submitted anti black listing affidavit as per Annexure-I.
f. Not submitted tender documents volume-I and volume-II in original and duplicate copy
physically
g. Not submitted Notarized Undertaking By The Bidder On Rs 300 Stamp as per Form J(vol-II)
h. not submitted a safety manual
i. not submitted pert chart /Construction Programme.
j. not submitted proposed site organization chart

5.0 One Bid per Bidder

Each bidder shall submit only one bid. The bidder who submits or participates in more than
one Bid will cause all the proposals with the Bidder’s participation to be disqualified.

6.0 Cost of Bidding

The bidder shall bear all costs associated with the preparation and submission of his Bid, and
the Employer will in no case be responsible and liable for those costs.

7.0 Site Visit

The Bidder, at the Bidder’s own responsibility and risk is deemed to have inspected and
examined the site and its surroundings after visit to site of Works and its surroundings and
obtain all information that may be necessary for preparing the Bid and entering into a contract
for construction of the Works. The costs of visiting the Site shall be at the Bidder’s own
expense. Particular attention of bidders, besides other aspects, is invited to:

The form and nature of work and subsurface conditions


The climatic conditions
The extent and nature of work and materials necessary for the execution and
completion of the Works
The means of access to the site and the accommodation he may require and
All other information as to risks, contingencies and circumstances which may influence
or affect his bid.
Structures to be dismantled.

Signature of Bidder 17 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

B. Bidding Documents

8.0 Content of Bidding Documents

8.1 The set of bidding documents comprises the documents listed below and addendam issued in
accordance with Clause 10:

Volume 1: Condition of Contract, Technical Information and Drawings.


Volume 2: Documents to be furnished by bidder for Qualification.
Volume 3: Financial bid. (to be submitted online only).Unpriced BOQ duly signed and
stamped by tenderer in hard copy (original + duplicate) to be submitted along with
volume 1 & 2.

8.2 The bidder is expected to examine carefully all instructions, conditions of contract, contract
data, forms, terms, technical specifications, Schedule B, Annexes and drawings in the Bid
Document. Failure to comply with the requirements of Bid Documents shall be at the bidder’s
own risk. Bids which are not substantially responsive to the requirements of the Bid
Documents shall be rejected.

9.0 Clarification of Bidding Documents

9.1 A prospective bidder requiring any clarification of the bidding documents may notify the
Employer in writing or by letter or E-mail to ceamc@ahmedabadcity.gov.in at the Employer’s
address indicated in the invitation for bid. Copies of Employer’s response, if any, will be
uploaded to the website www.nprocure.com.

9.2 Pre-bid meeting

9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting which will take
online only, time and date as indicated in the Bid Information.

9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter
that may be raised at that stage.

9.2.3 The bidder is requested to submit any questions in writing or by letter or Email to reach the
Employer not later than 24 hours before the meeting.

9.2.4 Minutes of the meeting, including the text of the questions that are raised during the meeting
(without identifying the source of enquiry) and the responses given will be uploaded on
website of www.nprocure.com. Any modification of the bidding documents which may
become necessary as a result of the pre-bid meeting shall be made by the Employer
exclusively through the issue of an Addendum pursuant to clause 10 and not through the
minutes of the pre-bid meeting.

9.2.5 Non-attendance at the pre-bid meeting will not be cause for disqualification of a bidder.

10.0 Corrigendum of Bidding Documents


10.1 Before the deadline for online submission of bids, the Employer may modify the bidding
documents by issuing addenda.
10.2 Any Corrigendum thus issued shall be part of the bidding documents and shall be placed on
website www.nprocure.com. The prospective bidders shall refer to the website to check any
addendum before 48 hours of online submission of bids. AMC will not give any advertisement
for the same.
10.3 To give prospective bidders reasonable time in which to take an addendum into account in
preparing their bids, the Employer may, at his desecration, extend as necessary the deadline
for submission of bids, in accordance with Sub-Clause 20.2 below.
10.4 All bidders are requested to see the website www.nprocure.com for corrigendum for the
Bid.

Signature of Bidder 18 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

C. Preparation of Bids

11.0 Language of the Bid

All documents relating to the bid shall be in the English language.

12.0 Documents comprising the Bid

12.1 The bid to be submitted by the Bidder as bid document shall comprise the following and in two
copies (Original & Duplicate).

(i) Bid Security & tender fee.


(ii) Qualification Information forms and documents as per Volume-II
(iii) Undertaking that the bid shall remain valid for the period specified in bid information.
(iv) Affidavit as per format provided in Annexure – I
(v) Undertaking in form given in Annexure - II
(vi) Volume-I & II
(vii) Volume III (Unpriced BOQ Volume III duly stamped and signed.)

Each copy (Original & Duplicate) will be separately sealed and marked in accordance with
the Sealing and Marking Instructions as per clause no. 19.0. And Volume – III Financial Bid
to be submitted online only.

12.2 The bidder shall prepare and submit two copies of the bid, marking them “Original” and
“Duplicate” respectively. The copies of bid security and tender fee shall also be enclosed
in the “duplicate” of bid.

12.3 The Bidder will be required to sign each page of these documents.

12.4 These signed documents along with the documents of accepted bid, shall form a part of the
contract agreement between the Employer and the successful bidder.

13.0 Bid Prices

13.1 The contract shall be for the whole works as described in various documents as listed in Sub-
Clause 12.1.

13.2 The bidder shall quote his percentage rate in figures online only.

13.3 All duties, taxes, (GST & other) and other levies payable by the contractor under the contract,
or for any other cause shall be included in the rates, prices and total Bid Price submitted by
the Bidder. Employer will not compensate the bidder (contractor) for any change in duties,
taxes and other levies payable by the contractor under the contract and any other reasons.
13.4 The percentage rate and bid price quoted by the bidder shall be fixed for the duration of the
Contract and shall not be subject to adjustment on any account, except where expressly
specified, otherwise, in the contract.

14.0 Currencies of Bid and Payment

14.1 The unit rates and the price of schedule B are in Indian Rupees. All payments shall be made
in Indian Rupees.

Signature of Bidder 19 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

15.0 Bid Validity

15.1 Bids shall remain valid for a period not less than 180 days after the deadline date for bid
submission (hard copy) specified in Clause 20.0. A bid valid for a shorter period shall be
rejected by the Employer as non-responsive.
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may
request that the bidders may extend the period of validity for a specified additional period. The
request and the bidders' responses shall be made in writing or by cable. A bidder may refuse
the request without forfeiting his bid security. A bidder agreeing to the request will not be
required or permitted to modify his bid, but will be required to extend the validity of his bid
security for a period of the extension, and in compliance with Clause 16.0 in all respects.

16.0 Bid Security

16.1 The Bidder shall furnish, as part of his Bid, a Bid Security of the amount as shown in para 6 of
Bid information for this particular work.

16.2 Any bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-
Clauses 16.1 above shall be rejected by the Employer as non-responsive.

16.3 The bid security of the unsuccessful bidders, except for L1, L2 and L3 bidders, will be returned
as promptly as possible.

16.4 The Bid Security of the L1, L2 and L3 will be discharged when Successful Bidder has signed
the Agreement and furnished the required Performance Security (Security deposit).

16.5 The Bid Security may be forfeited, if

a) the Bidder withdraws the Bid after Bid opening during the period of Bid validity;
b) the Bidder does not accept the correction of the Bid Price, pursuant to Clause 27; or
c) the successful Bidder fails within the specified time limit to
(i) sign the Agreement; or
(ii) Furnish the required Performance Security.

17.0 Alternative Proposals by Bidder

Bidders shall submit offers that comply with the requirements of the bidding documents,
including the basic technical design as indicated in the drawing and specifications.
Alternatives will not be considered.

18.0 Format and Signing of Bid

18.1 The Bidder shall prepare one original and one duplicate of the documents comprising the bid
as described in Clause 12 of these Instructions to Bidders, bound with the volume containing
the ‘Technical Bid’ in separate copies and clearly marked "ORIGINAL" and "DUPLICATE" as
appropriate. In the event of discrepancy between them, the original shall prevail.

18.2 The original and duplicate of the Bid shall be typed or written in indelible ink and shall be
signed by a person or persons duly authorized to sign on behalf of the Bidder. All pages of the
Bid where entries or amendments have been made shall be initialled by the person or persons
signing the bid.

18.3 The Bid shall contain no alterations or additions, except those to comply with instructions
issued by the Employer, or as necessary to correct errors made by the bidder, in which case
such corrections shall be initialled by the person or persons signing the bid.

18.4 Sufficiency of bid: The bidder shall be deemed to have satisfied himself as to the correctness
and sufficiency of the bid and of the rates and prices stated in the schedule B, all of which
shall, cover all his obligations under the contract and all matters and things necessary for the
proper execution and completion of Works and the remedying of the defects therein.

Signature of Bidder 20 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

D. Submission of Bids

19.0 Sealing and Marking of Bids

(A) Technical Bid


The bid shall be submitted in hard copies of document. (Except financial bid which shall be
submitted online only)

Cover – I
(1) Volume –I : Condition of Contract & Technical Information
(2) Volume –II : Qualification document with other documents
(3) Volume –III : Unpriced BOQ

Cover – II Tender fee & Bid security

Above documents shall be submitted in separate sealed envelope duly marked as


“ORIGINAL” and “DUPLICATE”. These two envelopes called as inner envelopes shall then be
put inside one outer sealed envelope and will be submitted under formal forwarding letter
address to the Employer inter alia containing an undertaking that the bid documents does not
contain any amendment, modification or change of any type whatsoever in the bid documents
and to any amendment issued.

(B) Price Bid- Vol -III


The bid shall be submitted online only as described in bid information.

19.1 The each envelope shall be addressed to Employer as mentioned in Bid Information bearing
the following Identification.
Bid for ___________ (name of work)
Bid reference No. ____________
DO NOT OPEN BEFORE __________ ( time & date for bid opening)
ORIGINAL / Duplicate
Name and address of the Bidder.

19.2 If the outer envelopes are not sealed and marked as above, the Employer will assume no
responsibility for the misplacement or premature opening of the Bid.

20.0 Deadline for Submission of the Bids

20.1 Online Bids must be submitted on or before time & date specified in Bid Information and
Hard copies of the Bid must be received by the Employer at the address specified in bid
information not later than the date indicated in the Bid Information of the document. In the
event of the specified date for the submission of bids being declared a holiday for the
Employer, the Bids will be received up to the appointed time on the next working day.

20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in
accordance with Clause 10, in which case all rights and obligations of the Employer and the
bidders previously subject to the original deadline will then be subject to the new deadline.

21.0 Late Bids

21.1 Any Bid received by the Employer after the deadline of submission prescribed in Clause 20
and Bid Information will be rejected and returned unopened to the bidder.

Signature of Bidder 21 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

22.0 Modification and Withdrawal of Bids

22.1 After submitting online, no modification shall be done by the bidder. However bidder may
withdraw their bids by giving notice in writing before the deadline date of submission of hard
copy.

22.2 Each Bidder's withdrawal notice shall be prepared, sealed, marked, and delivered in
accordance with Clause 18& 19, with the outer and inner envelopes additionally marked
"WITHDRAWAL" as appropriate.

22.3 No bid may be modified after the on line submission of Bids.

22.4 Withdrawal of a Bid between the deadline for submission of hard copy of bids and the
expiration of the original period of bid validity specified in Clause 15.1 above or as extended
pursuant to Clause 15.2 shall result in the forfeiture of the Bid security pursuant to Clause 16.

Signature of Bidder 22 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

E.Bid Opening and Evaluation

23.0 Bid Opening

23.1 On the due date and appointed time as specified in the Bid information, the Employer will
open envelopes of all Bids received (except those received late) in the presence of the
Bidders or their representative who choose to attend. In the event of the specified date of Bid
opening being declared a holiday by the Employer, the Bids will be opened at the appointed
time and location on the next working day.

23.2 Envelopes marked “WITHDRAWAL” shall be opened and read out first. Bids for which an
acceptable notice of withdrawal has been submitted pursuant to Clause 22 shall not be
opened.

23.3 If all Bidders have submitted unconditional Bids together with requisite Bid security, then all
Bidders will be so informed then and there. If any Bid contains any deviation from the Bids
documents and /or if the same does not contain Bid security in the manner prescribed in the
Bid documents, then that Bid will be rejected and the Bidder informed accordingly.

23.4 At the time of opening of “Financial Bid”, the names of the bidders who were qualified to open
financial bid and found responsive in accordance with Clause 23.2 will be announced. The
financial bids of these bidders only will be opened online. The responsive Bidders’ names, the
Bid prices, the total amount of each bid, any discounts and such other details as the Employer
may consider appropriate, will be announced by the Employer at the opening. Any bid price or
discount, which is not read out and recorded, will not be taken into account in Bid Evaluation.

23.5 The Employer shall prepare minutes of the Bid opening, including the information disclosed to
those present in accordance with Sub-Clause 23.3 and minutes shall form part contract.

23.6 The bidder shall abide by the provision of the minutes.

24.0 Deleted

25.0 Clarification of Bids

25.1 To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his
discretion, ask any Bidder for clarification of his Bid, including breakdowns of% above or
below estimated rates. The request for clarification and the response shall be in writing or fax
or e-mail, but no change in the price or substance of the Bid shall be sought, offered, or
permitted except as required to confirm the correction of arithmetic errors discovered by the
Employer in the evaluation of the Bids in accordance with Clause 27.

25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to his
bid from the time of the bid opening to the time the contract is awarded. If the Bidder wishes to
bring additional information to the notice of the Employer, he should do so in writing.

25.3 Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid
comparison or contract award decisions may result in the rejection of his bid.

26.0 Examination of Bids and Determination of Responsiveness

26.1 Prior to detailed evaluation of Bids, the Employer will determine whether each bid :-
a. meets the eligibility criteria defined in Clauses 3,
b. has been properly signed by an authorised signatory (accredited representative) holding
Power of Attorney in his favour. The Power of Attorney shall inter alia include a provision,
c. is accompanied by required Bid securities and,
d. is substantially responsive to the requirements of the Bidding Documents.

Signature of Bidder 23 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

26.2 A responsive Bid is one of which conforms to all the terms, conditions, and specifications of the
Bidding documents, without material deviation or reservation. A material deviation or
reservation is one (a) which affects in any substantial way the scope, quality, or performance
of the Works; (b) which limits in any substantial way, the Employer’s rights or the Bidder’s
obligations under the Contract; or (c) whose rectification would affect unfairly the competitive
position of other Bidders presenting substantially responsive Bids.

26.3 If a Bid is not substantially responsive, it will be rejected by the Employer, and may not
subsequently be made responsive by correction or withdrawal of the non-conforming deviation
or reservation.

27.0 Correction of Errors

27.1 Financial Bids determined to be responsive will be checked by the Employer for any arithmetic
errors. Errors will be corrected by the Employer.

27.2 The amount stated in the Financial Bid will be adjusted by the Employer in accordance with
the above procedure for the correction of errors and, with the concurrence of the Bidder, shall
be considered as binding upon the bidder. If the Bidder does not accept the corrected amount
the bid will be rejected, and the Bid security may be forfeited in accordance with Sub-clause
16.5(b).

28.0 Employer’s Rights

Municipal Commissioner Reserves right,


(1) To waive any qualifying criteria or information in any tender as a special case and to
reject any or all tenders without assigning any reason thereof.
(2) To increase / decrease the scope of work & also split the tender in two or more contracts
without assigning any reason even after the work is awarded.
(3) To allot number of tenders to successful bidders, in case if any contractor is lowest in
more than one tender.
(4) To collect any required documents after bid opening and also reserves the right for
rejection/acceptance of any tender.

29.0 Evaluation and Comparison of Bids

29.1 The Employer will evaluate and compare only the Bids determined to be responsive in
accordance with Clause 26.

29.2 In evaluating the Bids, the Employer will determine for each Bid the evaluated Bid Price by
adjusting the Bid Price as follows:

a) Making any correction for errors pursuant to Clause 27; or


b) Making an appropriate adjustments for any other acceptable variations, deviations; and

29.3 The Employer reserves the right to accept or reject any variation or deviation and other
factors, which are in excess of the requirements of the Bidding documents or otherwise result
in unsolicited benefits for the Employer. However the same shall not be taken into account in
Bid evaluation.

29.4 If the Bid of the Successful Bidder is seriously unbalanced in relation to the cost estimate of
work to be performed under the contract, the Employer may require the Bidder to produce
detailed price analyses for any or all items of the schedule B, to demonstrate the internal
consistency of those prices with the implementation/construction methods and schedule
proposed.

30.0 Requirement of submission of analyses by the contractor should be complied and submitted to
the Employer within the stipulated time fixed by the Employer failing which the bid would be
treated as non responsive.

Signature of Bidder 24 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

F.Award of Contract
31.0 Award Criteria

31.1 The Employer will award the Contract to the Bidder whose Bid has been determined to be
responsive to the Bidding documents and who has offered the lowest evaluated Bid Price,
provided that such Bidder has been determined to be (a) eligible in accordance with the
provisions of Clause 3, and (b) qualified in accordance with the provisions of Clause 4 &
Volume-II.

32.0 Employer's Right to Accept any Bid and to Reject any or all Bids

32.1 Notwithstanding anything contained in this Bid, the Authority reserves the right to accept or
reject any Application and to annul the Bidding Process and reject all Applications/ Bids, at
any time without any liability or any obligation for such acceptance, rejection or annulment,
and without assigning any reasons therefore. In the event that the Authority rejects or annuls
all the Bids, it may, in its discretion, invite all eligible Bidders to submit fresh Bids hereunder.

33.0 Notification of Award and Signing of Agreement


33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior
to expiration of the Bid validity period by writing, facsimile or e-mail confirmed by registered
letter. This letter (hereinafter and in the Conditions of Contract called the "Letter of
Acceptance" as per format given in Annexure - III) will state the sum that the Employer will
pay the Contractor in consideration of the execution, completion, and maintenance of the
Works by the Contractor as prescribed by the Contract (hereinafter and in the Contract called
the "Contract Price").

33.2 The notification of award will constitute the formation of the Contract, subject only to the
furnishing of a Performance Security in accordance with the provisions of Clause 34.

33.3 The agreement will incorporate all correspondences between the Employer and the
Successful Bidder. Tthe Employer will issue Letter of Acceptance (LOA) to the successful
Bidder. Within 21 days of receipt of LOA the successful Bidder will furnish the performance
security and sign the Agreement with the Employer.

33.4 Upon the furnishing by the Successful Bidder of the Performance Security, the Employer will
promptly notify the other Bidders that their Bids have been unsuccessful and release their Bid
Security.

34.0 Security Deposit


34.1 Within 15 days of receipt of the Letter of Acceptance, the Successful Bidder shall deliver to the
Employer a Performance Security in the form of Bank Guarantee in favour of Municipal
Commissioner, Ahmedabad payable at Ahmedabad as per Annexure-VII.

34.2 Failure of the Successful Bidder to comply with the requirements of Sub-Clause 34.1 shall
constitute sufficient grounds for cancellation of the award and forfeiture of the Bid Security.

34.3 The Security Deposit shall be valid till 90days beyond Date of completion.

34.4 Prior to making a claim under the Security Deposit the Employer shall, in every case, notify
the Contractor stating the nature of default in respect of which the claim is to be made.

34.5 In case of failure to pay the Security Deposit in the stipulate time, a interest of 4% per annum
shall be payable by the contractor.

35.0 Advance Payment and Security

35.1 The Employer will not provide any advance payment.

36.0 Dispute Review Expert /Arbitration

Signature of Bidder 25 AMC


Ahmedabad Municipal Corporation Section – I: Instruction to Bidders

36.1 In case of all the disputes, decision of the Municipal Commissioner, Ahmedabad shall be final
and binding to the bidder. Municipal Commissioner shall be the sole Arbitrator.

37.0 Corrupt or Fraudulent Practices


37.1 The Employer will reject a proposal for award if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in competing for the contract in question
and will declare the firm ineligible, either indefinitely or for a stated period of time.
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub-Clause 23.2 & 59.2 of the
Conditions of Contract.

City Engineer
Ahmedabad Municipal Corporation
Ahmedabad
Seal and Signature of the Bidder
Date:

Signature of Bidder 26 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

To be notarized by Notary

Annexure - I

Affidavit
1. I, the undersigned, do hereby certify that all the statements made in the required attachments
are true and correct.

2. I / We hereby declared that our firm M/s ________________________________has not been


blacklisted or debarred in any Central, railway, state and any other Local Government
Authority from participation in tenders/contract since last five years before date of submission
of the online tender.

3. I / We hereby declared that our firm M/s ________________________________ is not


blacklisted or debarred in any Central, railway, state and any other Local Government
Authority from participation in tenders/contract on date of submission of online-tender.

4. The I / We also hereby certifies that our firm M/s ________________________________has


neither abandon any work in India nor rescinded any contract awarded to us since last five
years before date of submission of the online tender.

5. The I / We undersigned hereby authorise(s) and request(s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by the
Department to verify this statement or regarding my (our) competence and general reputation.

6. I /We hereby declare that I / We understand and agree that further qualifying information may
be requested, and I / We also agree to furnish any such information at the request of the AMC
within the prescribed time.

7. I / We further declare that my / our near relatives are not working in AMC as city Engineer, an
Additional City Engineer, Deputy City Engineer, Assistant City Engineer, Assistant Engineer
and technical supervisor as on today.

8. I / We M/s ________________________________ hereby declared that the bid submitted by


us will remain valid for a period of 120 days after last date submission of hard copy.

9. I / We M/s ________________________________ hereby certifies that in case of all the


disputes, decision of the Municipal Commissioner, Ahmedabad shall be final and binding to
us. Municipal Commissioner shall be the sole Arbitrator.

(Signed by an Authorized Representative of the Firm)

_____________________

Name of the Representative

______________________

Name of Firm
______________________

Date:__________________

Signature of Bidder 27 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

To be notarized by Notary

Annexure-II

UNDERTAKING

I/we, the undersigned do hereby undertake that our firm M/s___________________________ will
invest minimum cash of 15% of the value of the work or as required for implementation of this
Contract.

(Signed by an Authorized Representative of the Firm)

_____________________

Name of the Representative

______________________

Name of Firm
______________________

Date:__________________

Signature of Bidder 28 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

Annexure-III

Letter of Acceptance
(Letterhead paper of the Employer)
_____________________ [date]
To:______________
[name and address of the Contractor]

Dear Sirs,

This is to notify you that your Bid dated___________________ for execution of the
_______________[name of the contract and identification number, as given in the Instructions to
Bidders] for the Contract Price of Rupees_____________________ (amount in words and figures, as
corrected and modified in accordance with the Instructions to Bidders) is hereby accepted by
competent Authority.

We note that as per bid, you do not intend to subcontract any component of work.

You are hereby requested to furnish Performance Security in the form detailed in Clause 34.1 of ITB
for amount of Rs. ______________ within 15 days of the receipt of this letter of acceptance, valid up
to 90 days from the date of completion i.e. up to __________ and sign the contract, failing which
action as stated in Clause34.3 of ITB will be taken.

Yours faithfully,

Authorised Signatory

Name and Title of Signatory

Signature of Bidder 29 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

Annexure-IV
Agreement Form
Agreement
This agreement, made the _________day of _______2019, between ________________[name and
address of Employer] (hereinafter called “the Employer”) of the one part and _____________[name
and address of Contractor] (hereinafter called “the Contractor” of the other part).

Whereas the Employer is desirous that the Contractor executes ________________ [name and
identification number of Contract] (hereinafter called “the Works”) and the Employer has accepted the
Bid by the Contractor for the execution and completion of such Works and the remedying of any
defects therein, at a Contract Price of Rs. ___________.

NOW THIS AGREEMENT WITNESSETH as follows:


1. In this Agreement, words and expression shall have the same meanings as are respectively
assigned to them in the Conditions of Contract hereinafter referred to, and they shall be
deemed to form and be read and construed as part of this Agreement.
2. In consideration of the payments to be made by the Employer to the Contractor as hereinafter
mentioned, the Contractor hereby covenants with the Employer to execute and complete the
Works and remedy any defects therein in conformity in all aspects with the provisions of the
Contract.
3. The Employer hereby covenants to pay the Contractor in consideration of the execution and
completion of the Works and the remedying the defects wherein the Contract Price or such
other sum as may become payable under the provisions of the Contract at the times and in
the manner prescribed by the Contract.
4. The following documents shall be deemed to form and be read and construed as part of this
Agreement, viz.:
i) The notice inviting bids
ii) The Contract Agreement
iii) The instructions to Bidders
iv) The Bid Information
v) The Letter of Acceptance and notice to proceed with the works
vi) The accepted Contractor’s Bid after amendments, addenda.
vii) The Contract Data
viii) The General Conditions of Contract and special conditions of contract
ix) The Technical Specifications
x) The Drawings
xi) The Schedule B (Volume-3 Financial Bid)
xii) Any other document listed in the Contract Data as forming part of the Contract.
xiii) Submission made by contractor as per qualification document (Volume-2)

In witness whereof the parties thereto have caused this Agreement to be executed the day and year
first before written.
The Common Seal of__________________ was hereunto affixed in the presence of:

Signed, Sealed and Delivered by the said ____________________

Binding Signature of Employer _____________________________

Binding Signature of Contractor_____________________________

In the presence of ______________________

Signature of Bidder 30 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

Annexure-V
Issue of Notice to Proceed with the Work
(Letterhead of the Employer)

_____________________ [date]

To:
_________________________________ [name and address of the Contractor]
_________________________________
_________________________________

Dear Sirs,

Pursuant to your furnishing the Performance Security as stipulated in Information to bidders (ITB)
clause 34.1 and signing of the contract agreement for the construction of (Name of Work) at the
accepted Bid Price of Rs. ___________ ( In words ), you are hereby instructed to proceed with the
execution of the said works in accordance with the contract documents.

Yours faithfully,

(Signature, name and title of signatory


authorised to sign on behalf of Employer)

Signature of Bidder 31 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

Annexure-VI
BANK GUARANTEE FOR BID SECURITY
(EARNEST MONEY DEPOSIT)

WHEREAS,______________________[Name of Bidder] (hereinafter called “the Bidder”) is submitting


his bid for the construction of ______________ [name of Contract] (hereinafter called “the Bid”).

KNOW ALL PEOPLE by these presents that We_____________________________[name of bank] of


_____________________(name of country) having our registered office at
_______________(hereinafter called “the Bank”) are bound unto _________________________
[name of Employer] (hereinafter called “the Employer”) in the sum of____________________ for
which payment well and truly to be made to the said Employer the Bank binds itself, his successors
and assigns by these presents.

SEALED with the Common Seal of the said Bank this ______day of_________2019

THE CONDITIONS of this obligations are:

(1) If after Bid opening the Bidder withdraws his Bid during the period of bid validity specified in the
Form of Bid; or

(2) If the Bidder having been notified of the acceptance of his Bid by the Employer during the period
of bid validity:

(a) Fails or refuses to execute the Form of Agreement in accordance with the Instructions to
Bidders, if required; or

(b) Fails or refuses to furnish the Performance Security, in accordance with the Instructions to
Bidders, or

(c) Does not accept the correction of the Bid Price pursuant to Clause 27.

We undertake to pay to the Employer up to the above amount upon receipt of his first written demand,
without the Employer having to substantiate his demand, provided that in his demand the Employer
will note that the amount claimed by him is due to him owing to the occurrence of one or any of the
three conditions, specifying the occurred condition or conditions.

This Guarantee will remain in force up to 150 days after the deadline for submission of Bids. Deadline
is stated in the Instructions to Bidders which may be extended by the Employer, notice of which
extension(s) to the Bank is hereby waived. Any demand in respect of this Guarantee should reach the
Bank not later than the above date.

DATE____________________ SIGNATURE OF THE BANK_______________________


WITNESS______________________________SEAL____________________________
___________________________
_________________________
[Signature, name and address]
_____________________________________________

Signature of Bidder 32 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

Annexure-VII
BANK GUARANTEE FOR SECURITY DEPOSIT

To: ____________________________ [name of Employer]


____________________________[address of Employer]

WHEREAS _______________________________ [name and address of Contractor] (here-in after


called “the Contractor") has undertaken, in
pursuance of Contract No. __________ dated ______________ to execute
___________________________ [name of Contract and brief description of Works] (hereinafter called
“the Contract");

AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you
with a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance
with his obligations in accordance with the Contract;

AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;

NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of
the Contractor, up to a total of ____________________________________________ [amount of
Guarantee]1 _______________________________[in words], such sum being payable in the types
and proportions of currencies in which the Contract Price is payable, and we undertake to pay you,
upon your first written demand and without cavil or argument, any sum or sums within the limits of
_____________________________ [amount of Guarantee] as afore-said without your needing to
prove or to show grounds or reasons for your demand for the sum specified therein.

We hereby waive the necessity of your demanding the said debt from the Contractor before presenting
us with the demand.

We further agree that no change or addition to or other modification of the terms of the Contract or of
the Works to be performed there under or of any of the Contract documents which may be made
between you and the Contractor shall in any way release us from any liability under this guarantee,
and we hereby waive notice of any such change, addition or modification.

This guarantee shall be valid until the date of issue of the completion Certificate plus 90 days.

SIGNATURE AND SEAL OF THE GUARANTOR_____________________


Name of Bank ___________________________
Address ___________________________
Date ___________________________

Signature of Bidder 33 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

Annexure-VIII

LIST OF APPROVED BANKS

yt&e <btb Ft<tlt yr^fthe©eytu/yuftWLx©e <&t rcjfjtfo©elu sKtJJtbtk ytJu Au fu, htsg
mhfth©e îtht rmfgwrhxe zevtuÍex <ubs yluoMxble zevtuÍex btxu bksqh &guj cukftule gtœe btk ltKtk
rJCtdlt S.yth. lk.EMD/10/2021/7729/DMO Dt. 12/04/2021 bwsc mw^thtu
fhe lJe gtœe cnth vtzJtbtk ytJuj Au. <u bwsc bnu.zu.Bgwrl. frbNlh©e X.lk. 35 <t. 09/06/2021
&e y.Bgwrl.ftuvtuo. îtht <ultu rMJfth fhe <ubtk sKtÔgt bwscle s cukftule cukfduhkxe mefgwhexe zevtuÍex <&t
R.yub.ze. MJYvbtk MJefthJtbtk ytJNu.xuLzhekd ytu&tuhexe îtht cukf duhkxele ytu&uLxemexele aftmKe fhe
sYhegt< bwsclt fLx[tuj «tumesh muxyv fhJtlt hnuNu. <ubs mhfth©elt S.yth yLJgu
bnu.zu.Bgwrlrmvj frbNh©ele b¤uj bksqhe bwsc btºt ybœtJtœ Nnuhle leau sKtJuj cukftule c{tLatule
cukf duhkxe MJefthJtbtk ytJNu. ltKtk Ft<tlt mhfgwjhlk. 48 <t.29/01/2012, mhfgwjhlk. 58 <t.
16/03/2012, mhfgwjhlk. 14 <t. 04/06/2013, mhfgwjhlk. 3 <t.13/05/2014 <&t mhfgwjh
lk. 21 <t. 29/05/2015 <&t mhfgwjhlk. 56 <t. 19/09/2016 , mhfgwjhlk. 18 <t.
23/05/2017, mhfgwjhlk. 18 <t. 29/05/2018 <ubs mhfgwjh lk. 12 <t. 22/07/2019 ,
mhfgwjh lk.26 <t.25.11.2019,mhfgwjh lk.21 <t.19.06.2020 ,mhfgwjh lk.40
<t.05.11.2020 mhfgwjh bwscle yLg Nh<tu g&tJ< hnuNu

The Bidder shall furnish, a Bid Security of the amount as shown in para 6
of the Table of IFB as part of his bid, in the form of D.D. or pay order or
Bank Guarantee in favour of Municipal Commissioner, Ahmedabad valid
for 120 days.
ANNEXURE–I
(A) Guarantee issued by following banks will be accepted as SD/EMD on permanent
basis.
1) All nationalized banks
(B) Guarantee issued by following banks will be accepted as SD/EMD for the period up to
March 31,2022. The validity cut-off date in the GR is with respect to the date of issue of
Bank Guarantee irrespective of the date of termination of Bank Guarantee
1. Commercial Banks :-
1.RBL Bank
2. Axis Bank
3. ICICI Bank
4. HDFC Bank
5. Kotak Mahindra Bank
6. IndusInd Bank
7. DCB Bank
8. Tamilnadu Mercantile Bank
9. Ujjivan Small Finance Bank
10. A U Small Finance Bank
11. Federal Bank
12. Equitas Small Finance Bank
13. Bandhan Bank
14. Standard Chartered Bank
15. City Union Bank

Signature of Bidder 34 AMC


Ahmedabad Municipal Corporation Section – II: Annexure

2. Co-operative and Rural Banks Of Gujarat :-


1 The Mehsana Urban Co-operative Bank Ltd
2. The Ahmedabad Mercantile Co-Operative Bank Ltd
3. Nutan nagrik Sahakari Bank Ltd
4. The Kalupur Commerical Co-operative Bank Ltd
5. Rajkot Nagarik Sahakari Bank Limited
6. The Gujarat State Co-Operative Bank
7. Sarswat Bank
8. Saurashtra Gramin Bank

Signature of Bidder 35 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

Section III: General Conditions of Contract and Special Conditions of Contract

A. General

1.0 Definitions

1.1 In the contract (as hereinafter defined) the following words and expressions shall have the
meaning hereby assigned to them, except where the context otherwise requires.

1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of
Contract but keep their defined meanings. Capital initials are used to identify defined terms.

“Commencement Date” means the date on which the Contractor receives from the Engineer
the notice to proceed with works.

“Time for completion” means the time for completing the execution of the works and passing
the tests on completion of the works calculated from the commencement date.

“Contract” means the contract agreement between the Employer and the Contractor to
execute, complete and maintain the Works as described in details in various documents listed
in clause 4 of “ The Contract Agreement “.

“Specifications” means the specification of the works included in Contract and/or


modifications/alterations made thereto by Contractor and approved by the Engineer.

“Drawings” means all drawings, calculations and technical information of a like nature
provided by the Engineer to the Contractor.

“Contract Data” means the documents and other information which comprise the Contract.

“Contractor” means a person / corporate body / registered company / consortium of


companies whose Bid to carry out the Works has been accepted by the Employer and the
legal successors in title to such person / corporate body / registered company / consortium of
companies.

“Sub contractor” means any person/corporate body/ registered company/ a consortium of


companies to whom a part of the works have been subcontracted with the consent of the
Engineer.

“Contractor's Bid’ means the priced offer to the Employer for the execution of the works and
remedying defects therein in accordance with various terms and conditions set out in the
Contract as accepted by “ Letter of Acceptance.”.

Contract Price means the price stated in the Letter of Acceptance and thereafter as adjusted
in accordance with the provisions of the Contract.

“Retention money” means the aggregate of all monies retained by Employer pursuant to
clause 48 of these Conditions of Contract.

“Interim Payment Certificate” means any payment certificate issued by the Engineer other
than the final payment certificate.

“Final Payment Certificate” means the certificate of payment issued by the Engineer
pursuant to clause 43.1 gof these Conditions of Contract.

Days means calendar days; months mean calendar months.

“Defect” means any part of the Works not completed in accordance with the Contract.

“Employer” means The Ahmedabad Municipal Corporation and is the party who will employ
the Contractor to carry out the Works.
Signature of Bidder 36 AMC
Ahemdabad Municipal Corporation Section – III: General Condition of Contract

“Engineer” means the person named in the Contract Data (or any other competent person
appointed and notified to the contractor to act in replacement of the Engineer or his nominee)
who is responsible for supervising the Contractor, administering the Contract, certifying
payments due to the Contractor, issuing and valuing Variations to the Contract, awarding
extensions of time and valuing the Compensation Events.

“Engineer’s Representative” means the person appointed by the Engineer for carrying out
such duties and exercising such authority as delegated to him from time to time by the
Engineer with written intimation to the Employer and the Contractor.

“Equipment” means the Contractor's machinery and vehicles brought temporarily to the Site
to construct the Works.

“Completion Date” means the date arrived at by counting the Contract period(inclusive of
any time extensions granted by the Engineer from time to time) after the commencement date.

“Plant” means any integral part of the Works, which is to have a mechanical, electrical,
electronic or chemical or biological function.

“Site” means the places provided by the Employer where the works are to be executed and
any other places as may be specifically designated in the contract as forming part of the site.

“Specification” means the Specification of the Works included in the Contract and any
modification or addition made or approved by the Engineer.

“Works” means permanent works and/or temporary works.

“Permanent works” means the permanent works to be executed in accordance with the
Contract.

“Temporary Works” are works of every kind in or about the permanent works designed,
constructed, installed, and removed by the Contractor, which are needed for construction or
installation of the Works.

“Cost” means all expenditure on or off site properly accounted and incurred or to be incurred
including all overheads.

“Writing” means all handwritten or typewritten or printed communication including cable,


facsimile or e mail communication.

1.2 Wherever in the contract provision is made for the giving of notice, consent, approval,
certificate or determination by any person such notice consent, approval, certificate or
determination by any person shall be given in writing unless otherwise specified in the
contract. Any such consent, approval, certificate or determination shall not be unreasonably
delayed or withheld.

2.0 Interpretation

2.1 In interpreting these Conditions of Contract, singular also means plural, male also means
female or neuter, and the other way around. Headings and marginal notes have no
significance. Words have their normal meaning under the language of the Contract unless
specifically defined. The Employer will provide instruction clarifying queries about the
Conditions of Contract.

2.2 If sectional completion is specified in the Contract Data, the completion date for each section
of work is arrived at by counting the period of completion assigned for that section of work
from the date of commencement assigned to that section of the work.

2.3 The several documents forming the Contract are to be taken as mutually explanatory to one
another, but in case of ambiguities and/or discrepancies the same shall be explained and
adjusted by the Engineer who shall thereupon issue to the contractor instructions thereon and
Signature of Bidder 37 AMC
Ahemdabad Municipal Corporation Section – III: General Condition of Contract

in such event unless otherwise provided in the contract, the priority of the documents forming
the Contract shall be as follows:

(1) The notice inviting bids


(2) The Contract Agreement
(3) The instructions to Bidders
(4) The Bid Information
(5) The Letter of Acceptance and notice to proceed with the works
(6) The accepted Contractor’s Bid after amendments, addenda.
(7) The Contract Data
(8) The General Conditions of Contract and special conditions of contract
(9) The Technical Specifications
(10) The Drawings
(11) The Schedule B
(12) Any other document listed in the Contract Data as forming part of the Contract.
(13) Submission made by contractor as per qualification document (Volume-2)

3.0 Language and Law

3.1 The language of the Contract shall be English and the law governing the Contract shall be the
Law as prevailing in India.

4.0 Engineer's Decisions

4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters
between the Employer and the Contractor in the role representing the Employer.

4.2 Except as expressly stated in the contract, the Engineer shall have no authority to relieve the
contractor of any of his obligations under the contract.

5.0 Delegation

5.1 The Engineer or any person authorized by the Engineer may delegate any of the duties and
responsibilities to other people after notifying the Contractor and may cancel any delegation
after notifying the Contractor.

6.0 Communications

6.1 Communications between parties which are referred to in the conditions are effective only
when in writing. A notice shall be effective only when it is delivered (in terms of the Indian
Contract Act 1872).

6.2 All the notices, consents, approvals, certificates, decisions, determinations to be given under
this contract by all the concerned parties (Employer, Engineer and Contractor) shall be given
in writing only.

6.3 All communications from Engineer’s Representative shall have the same effect as though
given by the Engineer. The Engineer shall however retain the authority to disapprove any
work, materials or Plant in the event of the Engineer’s Representative failing to do so or
revoke the decisions/instructions issued by the Engineer’s Representative.

6.4 All certificates, notices or instructions to be given to the Contractor by the Employer or the
Engineer under the terms of Contract shall be sent by post, fax, e-mail to or placed at the
Contractor’s principal place of business or such other address as the Contractor shall
nominate for that purpose.

6.5 Any notice to be given to Employer or to the Engineer under the terms of the Contract shall be
sent by post, courier or fax at the respective addresses nominated for that purpose given in
contract data.

6.6 Change of address shall be informed to respective parties well in advance.

7.0 Deleted
Signature of Bidder 38 AMC
Ahemdabad Municipal Corporation Section – III: General Condition of Contract

8.0 Subcontracting

8.1 The contractor shall not subcontract the whole of the works. Part of the works may be
subcontracted after obtaining the Engineer’s prior approval. Any such consent shall not relieve
the Contractor from any liability or obligation under the contract. The Contractor shall remain
responsible for all the acts, defaults and/or neglect of the contractual requirements and
obligations by any Subcontractor

8.2 Other Contractors

The Contractor shall co-operate and share the Site with other contractors, public authorities,
utilities, and the Employer as and when required without prejudice to any of his contractual
obligations. The Contractor shall as referred to in the Contract Data, also provide facilities and
services for them as described in the Schedule. The Employer may modify the schedule of
other contractors and shall notify the contractor of any such modification.

The Contractor shall afford all reasonable opportunities and facilities to


a. any other contractor and his workmen engaged by the Employer
b. the Workmen of the Employer
c. Workmen of any other agency permitted by the Employer to work in or around the site of
works.
d. Make available any roads or ways for the maintenance of which the Contractor is
responsible.
e. Permit the use of any temporary works or Contractors Equipment on site. (to be charged
wherever applicable).
f. Provide any other services of whatsoever nature (to be chargeable wherever applicable.)

9.0 Personnel

9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as
referred to in the Bid document to carry out the functions stated in the Schedule or other
personnel approved by the Engineer. The Engineer will approve any proposed replacement of
key personnel only if their qualifications, abilities, and relevant experience are substantially
equal to or better than those of the personnel listed in the Schedule.

9.2 If the Engineer asks the Contractor to remove a person, without assigning reasons thereof for
his misconduct or inadequacy of technical skills and experience, who is a member of the
Contractor’s staff or his work force; the Contractor shall ensure that the person leaves the Site
within seven days and has no further connection with the work in the Contract.

10.0 Employer’s and Contractor's Risks

10.1 The Employer carries the risks which this Contract states are Employer’s risks and the
Contractor carries the risks which this Contract states are Contractor’s risks.

11.0 Employer's Risks

11.1 The Employers risks are


a. in so far as they directly affect the execution of the Works in the country where the
Permanent Works are to be executed :

i. war and hostilities (whether war be declared or not), invasion, act of foreign enemies;

ii. rebellion, revolution, insurrection, or military or usurped power, or civil war;

iii. ionizing radiations, or contamination by radioactivity from any nuclear fuel, or from any
nuclear waste, from the combustion of nuclear fuel, radioactive toxic explosive or
other hazardous properties of any explosive nuclear assembly or nuclear component
thereof;

iv. pressure waves caused by aircraft or other aerial devices travelling at sonic or
supersonic speeds; and

Signature of Bidder 39 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

v. riot, commotion or disorder, unless solely restricted to the employees of the


Contractor or of his Subcontractors and arising from the conduct of the Works;

vi. floods, tornadoes, earthquakes and landslides

b. loss or damage due to the use or occupation by the Employer of any Section or part of
the Permanent Works, except as may be provided for in the Contract;

c. loss or damage to the extent that it is due to the design of the Works, other than any part
of the design provided by the Contractor or for which the Contractor is responsible; and

d. any operation of the forces of nature (in so far as it occurs on the Site) which an
experienced contractor:
i. could not have reasonably foreseen, or

ii. could reasonably have foreseen, but against which he could not reasonably have
taken at least one of the following measures:

(A) prevent loss or damage to physical property from occurring by taking appropriate
measures, or

(B) Insure against.

12.0 Contractor’s Risks

12.1 All risks of loss or damage to physical property and of personal injury death which arise during
and in consequence of the performance of the Contract other than excepted risks are the
responsibility of the contractor.

12.2 The contractor shall assume all liability, financial or otherwise in connection with his contract
and shall protect and indemnify the Employer from any and all damages and claims that may
arise on any account. The Contractor shall indemnify the Employer against all claims in
respect of patent rights, royalties, damages to adjacent buildings, roads or members of public
in course of execution of work or any other reason whatsoever and shall himself defend all
actions arising from such claims and shall keep the Employer saved harmless and indemnified
in all respect from such actions, costs and expenses. The contractor shall be liable for any
loss or damage to the Works occasioned by him in the course of operations carried out by
him. All such damage (except that arising out of excepted risks defined in clause 11 above) to
works will be rectified by contractor at his own cost.

13.0 Insurance

13.1 The Contractor shall provide in the joint names of the Employer and the Contractor, insurance
cover from the Commencement Date to the end of the Defects Liability Period, in the amounts
and deductibles as stated below, for the following events which are due to the Contactor’s
risks.

(a) Loss of or damage to the Works, Plant and Materials.


(b) Loss of or damage to Equipment
(c) Loss of or damage of property (Except the Works, Plant, Materials and Equipment) in
connection with the Contract; and
(d) Personal injury or death to any person.

13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for
the Engineer’s approval before the Commencement Date. All such insurance shall provide for
compensation to be payable in the types and proportions of currencies required to rectify the
loss or damage incurred.

13.3 If contractor does not provide any of policies and certificates required, the Employer does not
issue letter to proceed with the work.

13.4 Alterations to the terms of insurance shall not be made without the approval of the Engineer.

Signature of Bidder 40 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

13.5 Both parties shall comply with all conditions of the insurance policies.

14.0 Site Investigation Reports

14.1 The Employer has issued to the bidder all the details of the data regarding site conditions,
subsurface conditions as available.

14.2 The bidder is advised to inspect and examine the site and its surroundings and satisfy himself
with the nature and extent of site and work, the hydrological and climatic conditions the means
of access to the site, the constraints of space for stacking material/machinery, labour etc. he
requires, if any, weather conditions at site, general ground/subsoil conditions, underground
utilities, etc. or any other circumstances which may affect or influence their bid. No claim,
whatsoever, shall be entertained from the bidder, on the plea that the information supplied by
the Employer Is insufficient or is at variance to the actual site conditions.

14.3 The information and site data shown in the drawings and mentioned in the tender documents
have been furnished, in good faith, for general information and guidance only. The
Employer/Engineer in no case shall be held responsible for the accuracy thereof and/or
deductions, interpretations or conclusions drawn therefrom by the contractor and all
consequences shall be borne by the contractor and no claim, whatsoever, shall be entertained
from the contractor. It is presumed that the contractor has satisfied himself for all possible
contingencies, situations, bottlenecks and acts of coordination which may be required
between different agencies.

15.0 Queries about the Contract Data

15.1 The Employer / Engineer will clarify queries on the Contract Data. These clarifications shall
form a part of the Contract and shall be binding on both the Employer and the Contractor.

16.0 Contractor to Construct the Works

16.1 The Contractor shall, with due care and diligence design (to the extent as provided for in the
contract), execute and complete the works and remedy the defects if any in accordance with
the provisions of the contract, detailed design and drawing shall be made available by AMC
for permanent works.

16.2 Contractor shall provide all superintendence, labour, materials, plant, contractor’s equipment
and all other things as may be required to design, execute, complete and maintain during
defects liability period the works. (refer clause 16.1 above).

16.3 Any defect, error, omission, fault shall be immediately brought to the notice of the Engineer
before or during the execution of the works.

16.4 The Contractor shall take full responsibility for the adequacy, stability, safety of all site
operations and methods of construction. Contractor shall not be responsible for the design
and specifications of the Permanent Works not designed by him.

16.5 The Contractor shall be responsible for:


• The accurate setting out of the Works in relation to original lines, levels and points of
reference given by the Engineer in writing.
• The correctness of all positions, levels, dimensions and alignment of all parts of the
Works, and
• The provision of all necessary instruments, appliances and labour in connection with the
foregoing responsibilities.
• Contractor shall rectify all errors during execution of works at his cost except for the
errors that occur due to supply of incorrect drawings or instructions by the Engineer.

16.6 The checking and approval by the Engineer of any alignments, levels and setting out shall not
relieve the Contractor of his responsibility for accuracy thereof.

16.7 The Contractor shall establish site office. The latest configuration Laptop ( 1 No. – for AMC
Staff) with required software and internet facility, printers,Tables for engineers, chairs, safety
equipment,etc. all for the Engineers of AMC and their nominees for the complete duration of
Signature of Bidder 41 AMC
Ahemdabad Municipal Corporation Section – III: General Condition of Contract

the contract along with properly maintained clean, toilet facility and mineral water for drinking
facility at no cost to the Employer. If not provided, then penalized as decided by engineer in
charge.

17.0 The Works to be Completed by the Completion Date

17.1 The Contractor may commence execution of the Works on the Commencement Date and
shall carry out the Works in accordance with the program submitted by the Contractor as
updated with the approval of the Engineer and complete them by the Completion Date.

17.2 The Contractor shall afford every facility for and every assistance in obtaining the right to
access for the Engineer or any of his representative at all reasonable times to the Site and to
all workshops, places where materials or plant are being manufactured, fabricated or
prepared. If materials, plant or parts of works are manufactured, fabricated or prepared in
places not belonging to the Contractor, the Contractor shall organise necessary permissions
from the Employer of such facilities for the Engineer to inspect such where materials or plant.

17.3 Suspension of work

The Contractor shall, on the instructions of the Engineer, suspend the progress of the works or
part thereof for such time and in such manner as the Engineer may consider necessary and
shall, during such suspension, properly protect and secure the works or any part thereof so far
as is necessary in the opinion of the Engineer. Unless such a suspension is :
i. otherwise provided in the contract,
ii. necessary by reason of some default or breach of contract by the Contractor or for which
he is responsible,
iii. necessary by reason of climatic conditions on site or
iv. necessary for the proper execution of the work or for safety of the works or any part
thereof,

Following sub clause shall apply.

17.4 Effect of suspension.

With reference to clause 17.5 the Engineer shall after due consultations with the Employer
and the Contractor determine

a. The time effect of such suspension on the contract period and


b. The cost effect of such suspension on the Contract Price.
and shall notify the Contractor with a copy to the Employer.

18.0 Approval by the Engineer

18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary
Works to the Engineer, who shall approve them if they comply with the Specifications and
Drawings.

18.2 The Contractor shall be responsible for design of Temporary Works. Design of the temporary
works shall be got proof checked from the agency approved by AMC and the cost of the same
shall be borne by the Contractor.

18.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the
Temporary Works.

18.4 All Drawings prepared by the Contractor for the execution of the temporary or Permanent
Works, are subject to prior approval by the Engineer before their use.

19.0 Safety
19.1 The contractor shall be responsible for the safety of all activities on the site.

Signature of Bidder 42 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

19.2 The Contractor shall have full regard throughout execution, completion and defects liability
period to following safety aspects and shall take all necessary steps to ensure that danger to
safety is avoided all the time in respect of
a. Safety of the works
b. Safety of the Contractor’s employees and all the persons directly or indirectly engaged by
him for the works
c. Safety of all the employees including persons working on other contracts of Employer at
the same site of the Employer and Engineers employees engaged at work site.
d. Any authorised third party persons on the site.
e. Contractor’s plant and equipment

19.3 The Contractor shall provide and maintain at his costs all lights, guards, fencing, warning
signs, watching when and where necessary or required by Engineer or by any duly constituted
authority for the protection of the works or for the safety and convenience of the public or
others.

19.4 No inflammable materials including P.O.L. shall be allowed to be stored in huge quantity at
site. However, reasonable quantity may be permitted for storage, subject to the compliance of
all rules & instructions issued by the relevant authorities and as per the direction of Engineer -
in- Charge in this regard.

19.5 The Contractor shall save harmless and indemnify the Employer in respect of all claims,
proceedings, damages, costs, charges and expenses whatsoever arising out of, or in relation
to, any such matters in so far as the Contractor is responsible thereof.

19.6 Contractor shall be fully responsible for any person’s injury or death which arise during and in
consequence of the performance of the contract. Employer, Engineer, Engineer’s
representative shall not be responsible for the same.

20.0 Discoveries

20.1 Anything of geological or archaeological or other interest or articles of value or antiquity


discovered on the Site shall be the absolute property of the Employer. The Contractor is to
notify the Engineer of such discoveries and carry out the Engineer's instructions for dealing
with them

21.0 Possession of the Site

21.1 The Employer shall give possession of all parts of the Site to the Contractor, free from
encumbrances. If possession of a part is not given by the date stated in the Contract Data the
Employer is deemed to have delayed the start of the relevant activities and this will be a
Compensation Event.

22.0 Access to the Site

22.1 Access to site shall also be provided by the Employer to the Contractor in order and manner
as set out in the contract to enable the Contractor to commence and proceed with the works in
accordance with his construction programme and method of construction.

22.2 The Contractor shall allow the Engineer and any person authorized by the Engineer access to
the Site, to any place where work in connection with the Contract is being carried out or is
intended to be carried out and to any place where materials or plant are being manufactured /
fabricated / assembled for the works.
23.0 Instructions

23.1 The Contractor shall carry out all instructions of the Engineer or any person authorized by the
Engineer which complies with the applicable laws where the Site is located.

23.2 The Contractor shall, unless it is legally or physically impossible, execute and complete the
works and remedy defects therein in strict accordance with the contract to the satisfaction of
the Engineer. The Contractor shall comply and adhere to the Engineer’s instructions on any
matter, whether mentioned in the contract or not, concerning the works

Signature of Bidder 43 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

23.3 Contractor shall have to co-operate with all respect to TPI / PMC agency if appointed by the
Employer.

24.0 Deleted

25.0 Settlement of Disputes

25.1 If a dispute of any kind whatsoever arises between the Employer and the Contractor in
connection with, or arising out of the Contract or the execution of the Works, whether during
the execution of the Works or after their completion and whether before or after repudiation or
after termination of the Contract, including any disagreement by either party with any action,
inaction, opinion, instruction, determination, certificate or valuation of the Engineer or any
person authorized by the Engineer , the matter in dispute shall be referred to the Municipal
Commissioner, Ahmedabad Municipal Corporation (AMC) who will hear both the Parties and
decision of the Municipal Commissioner, AMC shall be final and binding to the bidder.
Municipal Commissioner shall be the sole Arbitrator.

Unless the Contract has already been repudiated or terminated or frustrated the Contractor
shall in every case, continue to proceed with the Works with all due diligence and the
Contractor and the Employer shall give effect forthwith to every decision of the Engineer or
any person authorized by the Engineer unless and until the same is resolved.

26.0 Deleted

Signature of Bidder 44 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

B. Time Control

27.0 Program
27.1 Within the time stated in the Contract Data the Contractor shall submit to
the Engineer a Program showing the general methods, arrangements, order, and timing for all
the activities.

27.2 Then after contractor shall submit work plan as and when required by the
Employer.

27.3 The Engineer shall monitor the rate of progress of work. In case the
Engineer finds that the rate of progress of work is too slow to comply with the Time for
completion, he shall notify the Contractor who shall thereupon take necessary steps to
expedite progress. No extra payments on account of such actions shall be due to the
Contractor.

28.0 Extension of Intended Completion date

28.1 The Engineer shall extend the Intended Completion Date if a


Compensation Event occurs or a Variation is issued which makes it impossible for Completion
to be achieved by the Intended Completion Date without the Contractor taking steps to
accelerate the remaining work and which would cause the Contractor to incur additional cost.

28.2 The Engineer shall decide whether and by how much to extend the
Intended Completion Date within 21 days of the Contractor asking the Engineer for a decision
upon the effect of a Compensation Event or Variation and submitting full supporting
information. If the Contractor has failed to give early warning of a delay or has failed to
cooperate in dealing with a delay, the delay by this failure shall not be considered in assessing
the new Intended Completion Date.

28.3 The whole of the works, and if applicable any section of the works
required to be completed within a particular time as stated in the Contract data, shall be
completed within the stipulated time for the whole of the works or the Section (as the case
may be) calculated from the Commencement Date, or such extended time as may be allowed
under following sub clauses.

28.4 The Engineer shall, after due consultation with the Employer and
Contractor, determine the amount of extension of time for completion to which the Contractor
becomes fairly entitled in the event of

i. Amount and nature of extra work


ii. Any cause of delay referred to in these conditions
iii. Exceptionally adverse climatic conditions
iv. Any delay, impediment or prevention by the Employer
v. Other special circumstances which may occur, other than through a default or breach of
contract by the contractor

The Engineer shall notify the Contractor about all such extension of time with a copy to the
Employer.

28.5 The Engineer shall however not be bound to make any determination
unless the Contractor

a. has notified the Engineer within 28 days of occurrence of event

b. Has furnished detailed particulars of the extension of time arising out of such an event
within 28 days of the issue of notice of occurrence of the event.

29.0 Deleted

Signature of Bidder 45 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

30.0 Delays Ordered by the Engineer

30.1 The Engineer may instruct the Contractor to delay the start or progress of
any activity within the Works. These delays shall be suitably compensated for time in
accordance with the provisions of the Contract.

31.0 Management Meetings

31.1 Either the Engineer or the Contractor may require the other to attend a
management meeting. The business of a management meeting shall be to review the plans
for remaining work and to deal with matters raised in accordance with the early warning
procedure.

31.2 The Engineer shall record the business of management meetings and is
to provide copies of his record to those attending the meeting and to the Employer. The
responsibility of the parties for actions to be taken is to be decided by the Engineer either at
the management meeting or after the management meeting and stated in writing to all who
attended the meeting.

32.0 Early Warning

32.1 The Contractor is to warn the Engineer at the earliest opportunity of


specific likely future events or circumstances that may adversely affect the quality of the work,
increase the Contract Price, or delay the execution of works. The Engineer may require the
Contractor to provide an estimate of the expected effect of the future event or circumstance on
the Contract Price and Completion Date. The estimate is to be provided by the Contractor as
soon as reasonably possible.

32.2 The Contractor shall cooperate with the Engineer in making and
considering proposals for how the effect of such an event or circumstance can be avoided or
reduced by anyone involved in the work and in carrying out any resulting instruction of the
Engineer.

Signature of Bidder 46 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

C. Quality Control

33.0 Identify Defects

33.1 The Engineer shall check the Contractor’s work and notify the Contractor
of any Defects that are found. Such checking shall not affect the Contractor’s responsibilities.
The Engineer may instruct the Contractor to search for a Defect and to uncover and test any
work that the Engineer considers may have a Defect.

34.0 Tests

34.1 If the Engineer instructs the Contractor to carry out a test not specified in
the Specification to check whether any work has a Defect and the test shows that it does the
Contractor shall pay for the test and any samples. If there is no Defect the test shall be a
Compensation Event.

34.2 As per standing committee’s resolution 0.5 % of value of work done shall
be deducted from each running bill as testing charges for testing to be carried out at AMC test
lab. With final bill, actual charges of testing shall be adjusted.

34.3 If the Engineer instructs the contractor to carry out a test not specified in
the specification to check whether any work has any defect or not, contractor shall perform the
same and submit the results to the Engineer at his own cost.

34.4 The contractor has to carry out the testes of all items as per the criteria
mentioned in Technical Specification, IS 456, etc.

35.0 Correction of Defects

35.1 The Engineer shall give notice to the Contractor of any Defects before the
end of the Defects Liability Period, which begins at Completion and is defined in the Contract
Data. The Defects Liability Period shall be extended for as long as Defects remain to be
corrected.

35.2 Every time notice of a Defect is given the Contractor shall correct the
notified Defect within the length of time specified by the Engineer’s notice.

36.0 Uncorrected Defects during Defects liability period

36.1 If the Contractor does not rectify or correct a defect within the time
specified in the engineer’s notice, the engineer will assess the cost of having the defect
corrected, and the contractor will bear the costs of such defective work as well as all works
carried out over such defective work until the defect is removed to the satisfaction of the
Engineer. The cost of such defective work will be recovered from the bank guarantee
submitted against performance for defect liability period.

36.2 Only the defects liability certificate referred to in following clause shall be deemed to constitute
the approval of the works.

36.3 Defects Liability Certificate: The Defects liability certificate shall be given by the Engineer in
Charge to the Employer, with a copy to the Contractor, within 28 days of the expiry of the
Defects Liability Period. The Contract shall remain incomplete until issue of the Defects
Liability Certificate.

36.4 The defects Liability Certificate shall mention clearly that the Contractor has completed his
obligations to execute and complete the works and remedy defects therein to the satisfaction
of the Engineer.

36.5 Unfulfilled obligations: Despite issuance of the Defects Liability Certificate, the contract
between the Employer and the Contractor shall remain in force in respect of unperformed
obligations incurred under the provisions of the Contract prior to the issue of the Defects
Liability Certificate.

Signature of Bidder 47 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

D. Cost Control

37.0 Schedule-B( Volume-3 Financial Bid)

37.1 The schedule-B shall contain Memorandum showing items for the construction, supply,
installation, testing, and commissioning work to be done by the Contractor.

37.2 The quantities stated in the schedule B are estimated quantities. The Contractor shall be paid
only quantities calculated after taking measurements of executed work. The rate stated in the
schedule B for each item of work shall apply

38.0 Deleted

39.0 Variations(Excess, saving or Non Tender Item)

39.1 All Variations shall be included in updated Programs produced by the Contractor.

39.2 The Engineer shall make any variation of form, quality or quantity of the Works or any part
thereof that may, in his opinion, be necessary and for that purpose, or if for any other reason it
shall, in his opinion, be appropriate, he shall have the authority to instruct the Contractor to do
and the Contractor shall do any of the following upto any extent:
• Increase or decrease the quantity of any work up to any extent included in the contract,
• Omit any such work,
• Change the character or quality or kind of any such work,
• Execute additional work of any kind necessary for the completion of the Works or
• Change any specified sequence or timing of construction of any part of work.

No such variation shall in any way vitiate or invalidate the contract, but the effects, if any, of all
such variations shall be valued in accordance with the following sub clauses. Provided that
where the issue of an instruction to vary the Works is necessitated by some default or breach
of contract by contractor or for which he is responsible, any additional cost attributable to such
default shall be borne by the Contractor.

39.3 The Contractor shall not make any such variation without an instruction of the Engineer. No
instruction is required for quantities varying from those provided for the items in the contract
schedule B.

40.0 Payment of Variations(Excess, saving or Non Tender Item)

40.1 The basis for the valuation of variations for addition to the Contract Price shall be as follows
in the same order of priority.

40.2 Contract unit rates for individual items shall apply to varied quantities where there is a
quantity variation.

40.3 Non Tender Items (Extra Items)

If any extra item crops up during the progress of work the same shall be carried out by the
Contractor and he shall be paid at the rate fixed by Employer which shall be fixed as lowest of
the rates derived by rate analysis based on the following three methods. , the priority of the
documents forming the Contract shall be as follows:

For items not existing in the Schedule-B or substitution to items in the Schedule-B, rate
payable shall be lowest of the rate determined by methods given below.

(i) Rate and price in the schedule of Rate (SOR) applicable to contract plus/minus
contractor’s tender premium or rebate as the case may be.

(ii) Rate analysis based on current schedule of rates (SOR) of Government.

(iii) Rate analysis based on current market rates. This shall be based on

Signature of Bidder 48 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

• The market rate of materials and labours, hire charges of plant and machinery,
temporary works if any, plus 15 % for contractor’s overhead, incidental works and
profit

40.4 In the event of disagreement the Engineer shall fix such rates and prices as are, in his opinion
appropriate and shall notify the Contractor accordingly with a copy to the Employer.

40.5 The Engineer shall determine provisional rates and prices to enable on account payments to
be included in the Interim Payment Certificates, until rates and prices are agreed as final by
the Employer, the Contractor and the Engineer.

40.6 The Contractor shall not be entitled to additional payment for costs, which could have been
avoided by giving early warning.

41.0 Deleted

42.0 Payment Certificates

42.1 The Contractor shall submit to the Engineer a monthly statement in three hard copies along
with soft copies The Monthly Statement shall contain
• The estimated value of work completed less the cumulative amount certified previously.
• Any other sums to which the Contractor may consider himself entitled.

42.2 The Engineer shall check the Contractor's monthly statement within 14 days and certify the
amount to be paid to the Contractor after taking into account any credit or debit for the month
in respect of materials for the works in the relevant amounts and under various conditions set
forth in sub-clause 51.3.

42.3 The value of work executed shall be determined by the Engineer.

43.0 Payments

43.1 Bills shall be prepared and submitted by the Contractor. Joint measurements shall be taken
continuously and need not be connected with billing stage. System of four copies of
measurements, three for Engineer & one for the Contractor and signed by both Contractor and
the Engineer shall be followed.

43.2 Payments shall be adjusted for deductions for retention, other recoveries in terms of the
contract and taxes at source, as applicable under the law. The Employer shall pay the
Contractor the amounts certified by the Engineer

43.3 No payment of interest shall be made to the Contractor for delayed payment if any.If an
amount certified is increased in a later date certificate due to corrections in previous
certificates or as a result of an award from disputes review experts, Contractor shall be paid
such amount only. The Contractor shall not be paid any interest upon such delayed payment.

43.4 Contractor shall submit final Bill within 60 days of issue of completion certificate. The Engineer
shall check the bill within 60 days after its receipt and return the bill to the Contractor for
corrections, if any. 50% of undisputed amount shall be paid to the Contractor at the stage of
returning the bill.

43.5 The contractor should re-submit the bill, with corrections within 30 days of its return by the
Engineer. The re-submitted bill shall be checked and paid within 60 days of its receipt.

43.6 Deleted

43.7 If an amount certified is increased in a later certificate as a result of an award by the


Conciliator or an Arbitrator, the Contractor shall be paid interest upon the delayed payment as
set out in this clause. Interest shall be calculated from the date upon which the increased
amount would have been certified in the absence of dispute.

Signature of Bidder 49 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

43.8 Items of the Works for which no rate or price has been entered in will not be paid for by the
Employer and shall be deemed covered by other rates and prices in the Contract.

43.9 All payments shall be made in Ahmedabad.

44.0 Deleted

45.0 Taxes, cess and duties

45.1 The rates quoted by the Contractor shall be deemed to be inclusive of the sales and other
prevailing taxes of Central and state government and local authorise that the Contractor will
have to pay for the performance of this Contract. The Employer will perform such duties in
regard to the deduction of such taxes at sources as per applicable law.

45.2 Labour Welfare Cess: As per circular No. GHR/2005/04/CWA/2004/841/M-3 dt. 3/1/05 and
G.R. No. CWA/2004-1831-M(3) dt. 9/12/05 issued by G.O.G. 1 % cess tax (non-refundable)
shall be deducted from every bill which shall be deposited to Govt. Labour Department for
Labour welfare fund.

46.0 Currencies

All payments shall be made in Indian Rupees.

47.0 Price Variation for Bitumen brought by Contractor

47.1 The basic rates for Bitumen shall be considered Ex-supply Depot / refinery are as under:

Sr. No. Material Rate 2015-2016

1 Bitumen in bulk 60/70 Grade (VG-30) 35973.00 per MT

47.2 Price Variation only for VG-30 grade Bitumen shall be paid to the contractor up to the expiry of
original and extended time limit. No Price Variation shall be paid for labour, material i.e.
Cement, Steel, Aggregate, diesel, emulsion, or any other material to be used in this work.

47.3 Difference between purchase rate of bitumen (mentioned in the Invoice) and the basic rate
mentioned in the clause no. 47.1 for actually consumed bitumen for this work shall be paid or
recovered.

47.4 The difference will be payable / recoverable from the date of issue of work order and this price
variation will be subject to approval of competent authority.

47.5 Price Variation shall be paid to the contractor from the date of issue of work order and up to
the expiry of original and extended time limit.

47.6 Contractor shall have to submit original purchase bills of Bitumen for verification at the time of
claiming for price escalation to AMC along with sign and certificate for the originality of the
Bills. If discrepancy found in such submitted bill then it will be Contractors responsibility.
Contractor shall have to provide such original bills as and when asked by AMC or Audit
Department of AMC for Audit Purpose. The same shall be returned to the contractor after
release of final bill.

48.0 Retain from Each Interim Payment Certificate (R A Bill).

Retention Money-1:@2% of the value of work done will be deducted from each RA Bill. It will
be released along with the release of Payment of Final Bill.
RetentionMoney-2: Performance security for Defect Liability:

Signature of Bidder 50 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

a) For approaches & Allied civil works other than Bituminous work;

Deduction:
Retention money @ 3% of the value of each Running Bill will be deducted including amount of
extra items, price escalation, excluding Cost of wearing surface of Bituminous work and
electrical fittings

Release:
The defect liability period shall be calculated from the date of completion mentioned in the
Completion Certificate of Approaches and allied works other than bituminous work. This
retention money-2 (a) will be released as follows:

Release of Remarks
Retention money-2(a)
It will be released to the contractor at the time of Final Bill
against submission of bank guarantee from approved banks
1.5%
valid up to 90 days beyond Defects liability period of this work
(one year).
It will be released on completion of Defects liability period of this
work and after engineer has certified that all defects notified by
1.5%
engineer to the contractor before the end of this period have
been corrected / rectified.

b) For Bituminous work:

Deduction:
Retention money @ 10 % of amount of bituminous work including price escalation in Running
Bill shall be deducted against Defect Liability / Performance Guarantee.

Release:
The defect liability period shall be calculated from the date of completion mentioned in the
Completion Certificate of Approaches and allied works other than bituminous work. This
retention money-2 (a) will be released as per Contract data.
.
48.1 Material Testing charges

The Employer shall deduct/retain, from each payment against Interim Payment Certificate
issued by the Engineer to the Contractor, 0.5 % amount of the sum of value of work done +
value of variations + value of Non tender Item as agreed for payment against performance of
work as testing charges for testing to be carried out at AMC test lab. This amount shall be
adjusted with final bill amount with actual charges of testing.

49.0 Liquidated Damages

100% of work by end of time limit.


i.) If the contractor fails to complete the work under contract by the stipulated
date, he shall pay liquidated damages of at the rate of 0.1 percentage of the
contract value per day from the date of delay the said work up to the date of
completion and handing over the Government.
ii.) However also if the contractor fails to complete any part of the work as
designed in Schedule (c) by the time indicated against such part, he shall pay
Liquidated damages per day from the date of delaying the said part of the work
up to the date of completion of the said designed part at the rates shown in the
said schedule of the contract value of such part for such failure till the said
designed part is completed.
iii.) The aggregate maximum of liquidated damages payable under tender clause
shall not exceed 0.10 Percentages of contract value per day and shall be
subject to the maximum amount of ten(10) percentage of the estimated amount
put to tender.
Delay requiring payment of ten percentage liquidated damages of the amount
put to tender for performance shall be sufficient causes for termination of
contract and for forfeiture of security deposit including amount of performance
Signature of Bidder 51 AMC
Ahemdabad Municipal Corporation Section – III: General Condition of Contract

bond in respect of works estimated to cost more than Rs. 15 Lakh, for
performance and registration of the contract shall also be kept in abeyance for
three years from the date as fixed in all cases.

50.0 Deleted

51.0 Advance Payment

51.1 Any type advance payment will not be paid/given.

52.0 Securities Deposit

52.1 The Security deposit 3% of the Contract amount shall be provided by the Contractor to the
Employer not later than 15 days from the letter of acceptance and shall be issued in the said
amount and on approved form and by a bank or surety approved by the Employer and
denominated in Indian Rupees. The Security deposit shall be valid until a date 90 days from the
day of expiry of taking over certificate. The security deposit shall be refunded within 90 days of
taking over certificate with list of defects.

The standard form of Security Deposit acceptable to the Employer shall be an unconditional
Bank Guarantee in favour of Municipal Commissioner, Ahmedabad, payable at Ahmedabad
from approved bank as per Annexure–VIII valid till 90 days beyond Date of completion of
work.

The Security Deposit shall be payable in 15 days from date of receipt of LOA failing which
interest @4% per annum will be charged by AMC.

53.0 Deleted

54.0 Cost of Repairs

Loss or damage to the Works or Materials to be incorporated in the Works between the Start
Date and the end of the Defects Correction periods shall be remedied by the Contractor at the
Contractor's cost if the loss or damage arises from the Contractor's acts or omissions.

Signature of Bidder 52 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

E. Finishing the Contract


55.0 Completion

55.1 After completion of the work, the contractor will serve a written notice to the Engineer /
Employer to this effect. The Engineer / Employer upon receipt of this notice shall conduct a
complete joint survey of the work within 7 days and prepare a defects list jointly. The defects
pointed out by the Engineer / Employer would be rectified by the contractor within 14 days and
thereafter acceptance report be signed jointly by the contractor and the Employer. This joint
acceptance report shall be treated as ‘Completion Certificate’.

56.0 Taking Over

The Employer shall take over the Site and the Works within seven days of the Engineer
issuing a certificate of Completion.

57.0 Final Account

57.1 The Contractor shall submit to the Engineer a detailed account of the total amount that the
Contractor considers payable under the Contract within 60 days of issue of completion
certificate. The Engineer shall check the bill and certify any final payment that is due to the
Contractor within 60 days of receiving the Contractor’s account if it is correct and complete. If
it is not, the Engineer shall issue within 15 days a schedule that states the scope of the
corrections or additions that are necessary for the correction and certify payment of 50% of
the undisputed amount to the contractor. If the Final Account is still unsatisfactory after it has
been resubmitted the Engineer shall decide on the amount payable to the Contractor and
issue a payment certificate, within 60 days of receiving the Contractor’s revised account.

57.2 The Contract shall remain active until issue of the Defects Liability Certificate.

57.3 Despite issuance of the Defects Liability Certificate, the contract between the Employer and
the Contractor shall remain in force in respect of unperformed obligations incurred under the
provisions of the Contract prior to the issue of the Defects Liability Certificate

58.0 As-built Drawings

58.1 Contractor shall supply “As built” Drawings after completion of work.

58.2 If the Contractor does not supply the As built Drawings by the dates stated in the sub-clause
58.1, or they do not receive the Engineer’s approval, the Engineer shall withhold the amount
stated in the Contract Data from the any payments due to the Contractor.

59.0 Termination

59.1 The Employer or the Contractor may terminate the Contract if the other party causes a
fundamental breach of the Contract.

59.2 Fundamental breaches of Contract include, but shall not be limited to the following:

i. The Contractor stops work for 28 days when no stoppage of work is shown on the current
Program and the stoppage has not been authorised by the Engineer:

ii. The Engineer instructs the Contractor to delay the progress of the Works and the
instruction is not withdrawn within 28 days.

iii. The Employer or the Contractor becomes bankrupt or goes into liquidation other than for
a reconstruction restructure or amalgamation.

iv. A payment certified by the Engineer is not paid by the Employer to the Contractor within
50 days of the date of the Engineer’s certificate:

Signature of Bidder 53 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

v. The Engineer gives Notice that failure to correct a particular Defect is a fundamental
breach of Contract and the Contractor fails to correct it within a reasonable period of time
determined by the Engineer.
vi. The Contractor does not maintain a security which is required.

vii. The Contractor has delayed the completion of works by the number days for which the
maximum amount of liquidated damages can be paid as defined in the Contract data and

viii. If the Contractor, in the judgement of the Employer has engaged in corrupt or fraudulent
practices in competing for or in the executing the Contract.

ix. “ corrupt practice” means the offering, giving, receiving or soliciting of anything of value
to influence the action of a public official in the procurement process or in contract
execution. “Fraudulent practice” means a misrepresentation of facts in order to influence
a procurement process or the execution of a contract to the detriment of the Employer,
and includes collusive practice. Bidders (prior to or after bid submission) designed to
establish bid prices at artificial non-competitive levels and to deprive the Employer of the
benefits of free and open competition.”

59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for a
cause other than those listed under Sub Clause 59.2 above, the Engineer shall decide
whether the breach is fundamental or not.

59.4 Notwithstanding the above, the Employer may terminate the Contract for convenience subject
to payment of compensation to the contractor. Loss of profit shall be calculated on the same
basis as adopted for calculation of extra/additional items.

59.5 If the Contract is terminated the Contractor shall stop work immediately, make the Site safe
and secure and leave the Site as soon as reasonably possible.

60.0 Payment upon Termination

60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor,
the Engineer shall issue a certificate for the value of the work done less other recoveries due
in terms of the contract, less taxes due to be deducted at source as per applicable law and
less the percentage to apply to the work not completed as indicated in the Contract Data.
Additional Liquidated Damages shall not apply. If the total amount due to the Employer
exceeds any payment due to the Contractor, the difference shall be a debt payable to the
Employer.

60.2 If the Contract is terminated at the Employer’s convenience or because of a fundamental


breach of Contract by the Employer, the Engineer shall issue a certificate for the value of the
work done, the reasonable cost of removal of Equipment repatriation of the Contractor’s
personnel employed solely on the Works, and the Contractor’s costs of protecting and
securing the Works and loss of profit on uncompleted works less other recoveries due in terms
of the contract and less taxes due to be deducted at source as per applicable law.

61.0 Property

61.1 All materials on the Site, Plant, Equipment, Temporary Works and Works for which payment
has been made to the contractor by the Employer, are deemed to be the property of the
Employer, if the Contract is terminated because of a Contractor’s default.

62.0 Release from Performance

62.1 If the Contract is frustrated by the outbreak of war or by other event entirely outside the control
of either the Employer or the Contractor, the Engineer shall certify that the Contract has been
frustrated. The Contractor shall leave the Site and stop work as quickly as possible after
receiving this certificate and shall be paid for all work carried out before receiving it and for
any work carried out afterwards to which commitment was made

Signature of Bidder 54 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

62.2 Defect liability Period


62.1.1 “Defects Liability Period” as stated in the contract data means the period calculated from:
i. The date of completion of the work certified by the Engineer in accordance with Clause
55.1 and its sub clauses of these conditions of contract.
ii. The respective dates in case different dates of completion of the part works are certified
by the Engineer.
62.2.1 Completion of outstanding work and remedying defects:
a. The contractor shall complete the outstanding work with due diligence. All such work as
listed by the Engineer at the time of issue of “Taking over Certificate “and also.
b. The contractor shall execute all such work of amendment, reconstruction and remedying
defects, shrinkages or other faults as the Engineer may, during the defects liability period
or within 14 days of its expiration, as a result of an inspection made by or on behalf of the
Engineer, prior to its expiration, instruct the contractor to execute.
62.2.3 Costs of all works referred to in clause 62.2 above shall be borne by the contractor.
62.2.4 During the Defect Liability period, it shall appear to the Engineer-in-charge or his subordinates
that any work has been executed with unsound, imperfect, or unskilful workmanship or with
materials of inferior quality; or that any materials or articles provided by him for the execution of
the work are unsound, or of a inferior quality, or other- wise not in accordance with the contract,
it shall be lawful for the Engineer-in-charge to intimate this fact in writing to the contractor and
the contractor shall be bound forthwith to rectify, or remove and reconstruct the work so
specified in whole or in part as the case may be.
62.2.5 Failing which within a period to be specified by the Engineer-in-charge in the written intimation
aforesaid, the contractor shall be liable to pay compensation at the rate of one percent on the
amount of the tender for every day not exceeding ten days, in the event of any such failure as
aforesaid the Engineer-in-charge may rectify or remove and re-execute the work or remove
and replace the materials or articles complained or as the case may be at the risk and expense
in all respects of the contractor.
62.2.6 Engineer-in-charge consider that any such inferior work or materials as described above may
be accepted or made use of it; shall be within his discretion to accept the same at such
reduced rates along with the appropriate penalty as the Municipal Commissioner may deem fit.

Signature of Bidder 55 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

F. General Description and Scope of Work

63.0 Scope of work,

63.1 The scope of work and explanatory notes given are neither complete nor exhaustive but are
added to assist the Contractor to understand the project. The detail scope is as described in
the schedule B (Volume-3), technical specifications and tender drawings. However any item of
work required to be carried out for proper and satisfactory completion of work with the highest
standard of workmanship is deemed to be included in the scope of work whether or not it is
specifically included in the schedule B.

63.2 The Works consist of Construction of RCC Retaining Wall at Mithakhali Underpass on
Mithakhali side only..

63.3 Name of work which is to be Constructed under this tender is as under:

Sr. no. Name of Work


1 Construction of RCC Retaining Wall at Mithakhali Underpass on Mithakhali side
only..

* AMC has right to change/Modified/Add or cancel any type of BOQ item work from scope of
above work.

63.4 The works shall, inter alia, include the following, as specified or as directed.

i. Site clearance, removal of tree stumps and dismantling of obstructions, encroachments etc.
before commencement of the works;

ii. True and proper setting out and layout of the works as per the instruction of Engineer In
Charge at no extra cost, setting of bench marks, provisions of all necessary labours,
instruments, and appliances;

iii. Construction of Piling work, Pile cap, Retaining wall and other miscellaneous work as per
Drawings provided by Design consultant etc.;

iv. Providing necessary road markings, road signs for traffic diversions;

v. Provision of suitably designed protective works for Underpass;

vi. Environmental measures;

vii. Ensuring safe traffic movement at all times during construction work in progress;

viii. Any other item of work as may be required to be carried out for completing the Retaining wall
structure for RUB works in all respects in accordance with the provisions of the contract;

ix. During night work proper lighting arrangement should be provided by the contractor;

x. During the period of the contract, the right of way and all existing roads shall be kept open for
traffic as per site condition and maintained in a safe and usable condition. Residents along
and adjacent to the works are to be provided with safe convenient access to their
properties at all times. Traffic control and traffic diversions shall be used as necessary to
protect the work and maintain them as directed by the engineer and provided in the
contract;

xi. All aspects of quality assurance of various components of the work;

xii. Clearing of site and handing over of the works;

xiii. Rectification of the defects in the completed works during the defects liability period;
Signature of Bidder 56 AMC
Ahemdabad Municipal Corporation Section – III: General Condition of Contract

xiv. Submission of as-built drawings and other related documents.

63.5 Bench Mark

Standard Pucca RCC bench marks of required numbers shall have to be established by
contractor on both the ends on each bank sides before commencement of the work and
connected to the nearest GTS bench mark according to which, whole work shall be carried
out. The Contractor shall establish reference benchmark at intermediate suitable spots with
reference to these benchmarks or as may be directed. The maintenance of all these Bench
Marks up to till completion of the work shall be responsibility of the contractor.

Alignments for road and other components have not been fixed at site by the AMC. The
Contractor has to establish the correct position thereof precisely on site, with respect to the
co-ordinates given by AMC shown in the General Arrangement drawing and as may be
indicated by the Engineer.

The Contractor shall be solely responsible for the true and proper setting out of the alignments
and for the provision of all necessary instruments, at any time during the execution of the
work. In case of any error regarding location, levels, dimensions, or alignment of any part of
the work, the Contractor on being required to rectify such errors as may be pointed out by the
Engineer, shall at his own expense do so, to the satisfaction of the Engineer. The checking of
any setting out of any line or level by the Engineer or his representative shall not, in any way,
relieve the Contractor of his responsibilities for the correctness thereof. The Contractor shall
carefully protect and preserve all benchmarks, site nails, pegs, reference pillars and other
measures used in setting out of the work.

64.0 Climatic Conditions

It shall be deemed that the Contractor has satisfied himself to the nature and location of the
work, general and local conditions and particularly those pertaining to transport handling and
availability and storage of materials, availability of labour, weather conditions, that he has
estimated his cost accordingly and the client will bear no responsibility for the lack of such
knowledge of site conditions and also consequences thereof, to the bidder. The information
and the data shown in the drawings and mentioned herein and elsewhere under the contract
are furnished for general information only and the client in no case will be held responsible for
the strict accuracy thereof or any deductions, interpretations or conclusion drawn there from
by the contractor.

The climate in this region is moderately hot. The monsoon depends upon the advent of the
south west wind but the normal rainy season commences from early June and lasts up to
early October in this region. Occasionally, shower may be expected even earlier. There is
generally no rain beyond October though some stray showers may be experienced. The
yearly average rainfall in the area is about 30” (750 mm).

65.0 Marketing Centres

Nearest marketing centres for daily necessity situated near the work site.

66.0 Housing, Water Supply and Drainage etc.

Housing accommodation on hire is likely to be available in this area around the site. The
Contractor has to make his own arrangements for the housing of labourers and other staff.
The land required for setting up batching plant, stacking of materials, site office, labour
quarters, testing laboratory, etc. will be arranged by contractor.
Water Supply for drinking purposes and construction purpose at the site shall also have to be
arranged by the Contractor at his own cost as may be required.

67.0 Facilities

Nearest major railway Station is Ahemdabad from the work site. A post office is also available.
The nearest airport is Ahmedabad Airport.

Signature of Bidder 57 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

68.0 Materials, Plant and Workmanship

68.1 All materials, plant and workmanship shall be:

a. Of the respective kinds and quality as described in the contract and in accordance with
the Engineers instructions and subject to tests as the Engineer may require at any or all
places, such as manufacturers facility, site, during fabrication, preparation etc, as
specified in the contract.

b. The Contractor shall provide all assistance required by Engineer for carrying out the tests.
Costs of tests are covered by the contractor’s quoted rates for the works.

68.2 The Engineer and his personnel shall have access to all locations of work all the time for
inspection of work. Contractor shall provide all necessary assistance to the Engineer and his
personnel for this at no extra costs.

68.3 On inspection, if the Engineer finds that certain works, materials and/or plant are defective
and/or not in accordance with the Contract, he shall notify the Contractor thereof immediately
with his objections and reasons. The Contractor shall then promptly make good the defect or
remove defective materials, plant from site.

68.4 All work or any part of shall be covered up only after approval of the Engineer in respect of the
quality of materials used and workmanship.

68.5 The Contractor shall uncover any part of the work or make openings in or through as required
by Engineer from time to time for inspection and shall make good such part only after approval
of the Engineer to such covered up work.

68.6 In case of default on the part of the Contractor in removal and making good of any defective
materials, workmanship and/or plant, the Employer shall engage another agency to carry out
the same at the Contractors risks and costs.

68.7 All Contractors materials, plant, machinery and equipment shall be deemed to have been
exclusively brought to site for the execution of the works and shall not be removed from site
without the consent of the Engineer.

68.8 Employer shall not be liable for damage to Contractors equipment at any time unless
otherwise expressly stated in the contract.

68.9 All the above sub clauses 68.7and 68.8 do not in any way imply approval to any kind of
materials used in the works.

68.10 All test samples shall be supplied and tested by the Contractor at his own cost.

68.11 The cost of all tests shall be borne by the Contractor except the tests that are required by the
Engineer are clearly beyond the Contractors obligations of proving the quality and
workmanship standards of all materials, equipment, plants and Works. The Engineer shall
determine the costs and time effects of such tests that are not a part of the Contractors
obligations.

68.12 The Contractor will have to make his own arrangement for plants, equipments, and machinery
to be used in the execution of this work well in time after award of the contract and as per
work program given by him.

68.13 Contractor shall give Engineer a 24 hours notice for inspection of works or witnessing of test.
The Contractor shall proceed with the works or tests in case the Engineer does not attend.
Such tests and shall be deemed to have been carried out in the presence of the Engineer.

Signature of Bidder 58 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

68.14 The Engineer may reject such material, plant, part of the works which are defective and/ or
otherwise not in accordance with the contract and notify the Contractor. The notice shall state
the Engineers objections and reasons. The Contractor shall then promptly rectify the defect or
ensure that rejected materials or plant are not used in the Works. In case the Contractor
wishes to retest such materials, plant or works declared defective by the Engineer, he has to
bear the time and cost effects of such retests as mutually agreed with the Employer in
consultation with the Engineer.

68.15 The Contractor shall have to make his own arrangement to get the power supply from
concerned electric authority. The costs of electrical charges are to be borne by contractor.

69.0 Personnel and Labour Employment


69.1 A Project Manager who is a graduate civil engineer having a minimum 10 years of experience
in similar nature work shall be deputed at site. The Project Manager shall always be available
at the site during the actual execution of the work. This is in addition to the number of
graduate engineers (of civil and other disciplines as required) who shall be appointed by
contractor to execute the work.

69.2 Contractor shall make his own arrangements for the engagement of all staff and labour, local
or other, and their payment, housing, feeding and transport.

69.3 Contractor shall furnish the Engineer every week during the progress of the works, classified
weekly returns of the number of the people employed on the work during the week. The report
of skilled and unskilled labour shall be given in the prescribed form.
The Contractor shall strictly observe all the requirements laid down in the contract labour
(Regulation and Abolition) Act, 1979 and the contract labour (Regulation and Abolition)
(Gujarat) Rules, 1972 and other acts as amended from time to time so far as applicable from
time to time.
The contractor, if directed by the Engineer shall increase or decrease the strength of the
labour both skilled and unskilled required for the work. The Contractor shall also furnish the
following returns.

a) A report of any accident, which may have occurred, within 24 hours of its occurrence.
b) To maintain hygienic condition in labour camp and construction site as per the rules and
regulation of authority and health department.
c) Accident reports within 24 hours of occurrence of each accident. The Contractor shall
d) Not import, sell give or barter alcoholic liquor or drugs.
e) Not import, sell give or barter arms and ammunition.

70.0 Program Through Net WorkTechnique

70.1 The Contractor shall furnish a complete Bar Chart considering all activities right from the
award of work to mobilisation at site, procurement of materials, machinery’s / equipments/
labour etc. for completion of the work in all respects and get it approved from the Engineer,
latest within two weeks after issue of notice to proceed with work. This shall form part of the
contract agreement. This program will be reviewed by the Engineer, in consultation with the
Contractor every month to assess the shortfall and to decide actions to be taken.

70.2 The Contractor shall further abide by the following instruction:

a) The Contractor shall cooperate fully for clarifying or evaluating schedule and also for
ensuring control or monitoring the progress of the work, as per approved schedule from
time to time.

b) The Contractor shall endeavour to minimise revision of the program as far as possible
after the work gets into the construction.

c) The Contractor shall immediately inform the Engineer whenever there is or there is likely
to be, any change in his schedule.

Signature of Bidder 59 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

d) In case of a schedule slippage due to the contractor’s inability to perform as contracted,


the Contractor shall immediately take such action as may be necessary to bring back his
work to schedule without additional cost to the Client, either by employing over time
operations, increasing the number of shifts, capacity of equipments etc. or as directed by
the Engineer.

71.0 Foreign Exchange Requirement

It should be clearly understood that no foreign exchange sanction would be made available for
either purchase of equipments, plants, machinery’s, material of any kind or any other thing,
required for execution of the work. It should also be clearly understood that no request for
importing equipments, materials, plants, etc. that may be required in carrying out the work
shall be entertained.

72.0 Relation with Public Authorities

The Contractor shall comply with all obligations arising out of legal orders and directions that
may be given to him from time to time, by any local or public authorities and shall pay out of
his own money, all charges becoming payable to such authorities. He shall co-ordinate his
activities during execution, with all agencies including AMC, Design Consultants, construction
management consultants, agencies like AEC (Ahmedabad Electricity Company), GEB
(Gujarat Electricity Board), AMC (Ahmedabad Municipal Corporation), AUDA (Ahmedabad
Urban Development Authority), Government of India, Railway Department, Government of
Gujarat Ahmedabad Telephones and their representatives without any dispute.

73.0 Register to be Maintained

73.1 Cement Register

A register in prescribed form, giving details regarding day to day receipts of cement as
procured by the contractor, consumption in work and balance available on the site, will be
maintained at the work site by the contractor. This register shall invariably be signed daily by
the Contractor or his authorized representative in token of its correctness and shall be made
available to Engineer whenever asked, for his verification of every entry made, regarding
procurement by the Contractor and consumption of these materials in execution.

73.2 Inspection Records and Registers

The Contractor/s shall maintain accurate records, plans and charts shows the dates and
progress of all main operations and the Engineer shall have access to this information at all
reasonable times. Records of tests made shall be handed over to the Engineer after carrying
out the tests.

73.3 Site Order Register

The Contractor/s shall promptly acknowledge and note by signing in the register the orders
given in Site Order Register by the Engineer or his representative or his superior officers and
comply with them. The Contractor/s shall report the compliance to the Engineer within
reasonable time so that it can be checked.

73.4 Steel Register


This register will record the receipts of steel items and details of reinforcement and members
wherever steel is used.

73.5 Labour Register

This register will be maintained to show daily strength of labour in different categories
employed by the Contractor/s.

Signature of Bidder 60 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

73.6 Log Book of Events

All events are required to be chronologically logged in this book shift wise and date wise. The
representative of the Engineer will sign and the Contractor will have to sign. The register
Performa, charts, etc. will be property of the AMC.

73.7 Any other register considered necessary by the Engineer shall be maintained at site in which
the representative to the Engineer and the Contractor/s will have to sign. All registers,
program, charts etc. will be the property of the AMC.

73.8 Sampling and Testing

73.8.1 Contractor shall make all arrangements for collection & transportation from site and testing of
samples in sufficient quantities as required and provided in relevant IS codes at the laboratory
approved by the Engineer. All these will be at no extra cost to the client.
73.8.2 A register in prescribed Performa showing test results of materials and work tests will be
maintained at the site of work by the Contractor and every entry thereof shall invariably be
signed by the Contractor or his representative and also by Engineer or his authorized
representative in token of its correctness.

73.9 The Contractor Shall Further Abide by the Following Instructions

73.9.1 Soon after receipt of work order awarding the contract, the Contractor for all purposes
connected with the execution of work, shall immediately make his own arrangements for
obtaining Electricity supply and required supply of water in such quantity and of such quality at
such places on the work as may be necessary, by paying charges to the authorities supplying
the same after completing all formal procedures as may be required as per the rules with
them. The rates quoted in the tender are for completed items of work and shall cover cost of
water and electricity as aforesaid. Water for drinking purposes for labourers etc. shall also
have to be arranged by the Contractor at his own cost. No cost shall be borne by Employer on
this account. Employer shall not be responsible in any way for this purpose. However, the
contractor shall be given all possible assistance in the procurement of these requirements but
no assurance can be given by Employer.

73.9.2 The bidder must clearly understand that the rates quoted are for completed items of work and
as such includes all costs associated with labour, materials, Wastage if any, scaffoldings,
plants, equipments, supervision, survey works, power, water., sales tax / income tax, and
other taxes in force and may be imposed by competent authority after wards including turn
over work tax, duties and any other requirements contingent upon and needed to carry out the
construction. The income tax will be deducted from the running account bill as per rules.

73.9.3 No claim by the Contractor for additional payment will be allowed on the ground of any
misunderstanding or misapprehension in respect of technical interpretations of conditions or
any such matter or otherwise on the ground of any allegation of fact that incorrect information
was given to him in the tender or by any person, whether in the employment of the client or
consultant or of the failure on his part, to obtain correct information. The bidder shall not be
relieved of any risks or obligations imposed upon or undertaken by him, under the contract, or
any such ground or on the ground that he did not or could not foresee any matter, which may
in fact, affect or have affected the execution of the work.

74.0 Equipment and Accessories

74.1 The Contractor shall provide all the equipments and accessories for execution of work.

75.0 Patent rights

The Contractor shall save harmless and indemnify the Employer from and against all claims
and proceedings for or on account of infringement of any patent rights, design trademark or
name or protected rights in respect of Contractors equipment, material or Plant used for or in
connection with incorporation in the Works.

Signature of Bidder 61 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

76.0 Royalties

The Contractor shall pay all royalties for getting construction materials required for the Works.

77.0 Urgent Remedial work:

If, by reason of any accident, or failure, or other event occurring to, in, or in connection with
the Works, or any part thereof, either during the execution of the Works, or during defects
liability period, any remedial or other work is, in the opinion of the Engineer, urgently
necessary for the safety of the Works and the Contractor is unable or unwilling at once to do
such work, the Employer shall be entitled to employ and pay other persons to carry out such
work as the Engineer may consider necessary. If the work or repair so done by the Employer
is work which, in the opinion of the Engineer, the Contractor was liable to do at his own cost
under the Contract, then all costs consequent thereon or incidental thereto shall, after due
consultation with the Employer and the Contractor, be determined by the Engineer and shall
be recoverable by the Employer from the Contractor, and may be deducted by the Employer
from any monies due or to become due to the Contractor and the Engineer shall notify the
Contractor accordingly, with a copy to the Employer. Provided that the Engineer shall, as soon
after the occurrence of emergency as may be reasonably practicable, notify the Contractor
thereof.

78.0 Special Risks :

78.1 The Contractor shall be under no liability whatsoever in consequence of any of the special
risks referred to in sub clause 78.5 whether by way of indemnity or other wise,for or in respect
of :

78.2 Destruction or damage to work, except defective works to be removed and rectified, prior to
the occurrence of the said special risks.

78.3 Destruction of or damage to property, whether of the Employer or third parties or Injury or loss
of life, not caused by negligence of the Contractor and even after following all the safety
norms by the Contractor.

78.4 The special risks are as defined in sub clause 78.1 of these conditions. Destruction caused by
a projectile, missile or bomb is also included in special risks.

78.5 The Contractor shall be entitled to payment in accordance with the Contract on account of
damages covered under special risks as stated in clause 78.1 and 78.2 for any permanent
work executed and for any material or plant so destroyed or damaged as required by the
Engineer or as necessary for the completion of the works. The payment shall be for

1. rectifying any such destruction or damage to works


2. replacing or rectifying such materials or Contractor’s Equipment.

78.6 The Contractor shall inform by giving notice to the Engineer with a copy to Employer, as soon
as events covered by special risks occur and the cost implications of these.

78.7 The Contractor shall use his best endeavours to complete the execution of Works in the event
of outbreak of war in any part of the world.

78.8 In case the Employer chooses to terminate the contract on account of the outbreak of war, the
Contractor shall remove his plant and machinery from site diligently. Similar facility shall be
extended to the sub contractors.

78.9 In the event of termination of contract on account of outbreak of war, the Contractor shall be
entitled to payment towards the following items apart from other payments due as per
conditions of contract

78.10 Sum being the amount of any expenditure reasonably incurred by the Contractor, in the
expectation of completing the whole of the works, in so far as such expenditure has not been
covered by any other payments.

Signature of Bidder 62 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

78.11 Proportionate demobilisation costs towards manpower and machinery and plant.

79.0 Force Majeure

Neither party shall be to liable to the other for any loss of damage occasioned by or arising out
of acts of god, and in particulars, unprecedented Floods, volcanic eruption earth quake or
other convulsion of nature, and other acts such as but not restricted to general strike, invasion,
the act of foreign countries, hostilities or war like operations before or after declaration of war,
rebellion, military or usurped power which prevent performance
of the contract and which could not have been for seen or avoided by a prudent person.

80.0 Changes in Cost and Legislation

There shall be no addition or deduction from the Contract Price due to changes to any
National or State Statute, Ordinance, Decree, Law, Regulation or byelaw. The adjustment to
Contract Price affected under various sub clauses detailed in clause 40 shall be deemed to
cover such costs.

81.0 Safety aspects

81.1 The Contractor shall take all reasonable steps to protect the environment on and off the site
and avoid damage or nuisance to persons or property of the public and others arising as a
consequence of his method of operation.

81.2 The Contractor shall maintain in good condition all work throughout execution, completion and
defects liability period. The contractor shall be responsible for and to make good all injuries,
damages and repairs, rendered necessary by fire, rain, traffic, floods or other causes

81.3 The Contractor shall be responsible for maintenance and watch and ward of the complete
installation and shall also be responsible for any pilferage, theft, damage, penalty etc. in this
regard. The Contractor shall indemnify the Engineer against any claim arising out of pilferage /
theft, damage, penalty etc. whatsoever on this account. Security deposit for the work shall be
released only after the clearance is obtained from the local authorities from whom temporary
electric/ water I telephone connection have been obtained by the contractor.

81.4 The Contractor shall depute Engineers& skilled workers as required for the work. Necessary
protective and safety equipments shall be provided to them by the Contractor at his own cost
and used at site.

81.5 Security & Traffic Arrangements

In event of any restriction being imposed by the Security Staff of The Employer, Ahmedabad
Municipal Corporation traffic or any other local governing body having control over the project,
on the working or movement of labour, materials, the Contractor shall strictly follow all such
restrictions or instructions issued regarding the same and nothing extra shall be payable to the
Contractor on account of such restrictions or instructions. In case of loss of time on this
account if any, shall have to be made up by generating additional resources etc.

General security restrictions are given as under:


ii. The movement of trucks and vehicles shall be regulated in accordance with rules and
regulations as approved by competent authorities.
iii. The Contractor shall inform in advance, if required, the truck registration numbers
ownership of the trucks, names and addresses of the drivers for necessary action by the
security agency.
iv. As and when there will be security requirements, certain additional restrictions can be
imposed as per the requirement of the situation.
v. No claim whatsoever will be entertained by the Employer on account of any restriction that
can be imposed as per the requirement of the situation.

Signature of Bidder 63 AMC


Ahemdabad Municipal Corporation Section – III: General Condition of Contract

82.0 Drawings and contract documents :

82.1 The drawings shall remain in the sole custody of the Engineer, but two copies thereof shall be
provided to the Contractor free of cost. The drawings shall be provided as per program
submitted & approved by the Engineer and prior to start of respective activity. The Contractor
can avail a soft copy in PDF from the Engineer for making further copies at his cost. Drawings
can be provided by the Engineer or his representative to the contractor through e-mail. All the
contractual documents and drawings shall not be given to a third party or used for any other
purpose than contractual work. On receipt of the Defects Liability Certificate, the Contractor
shall return all the drawings and the Contract documents including the drawings to the
Engineer.

82.2 Supplementary drawings and instructions: The Engineer shall have authority to issue
supplementary drawings and instructions to the Contractor. The Contractor shall carry out and
be bound by the same.

82.3 Photographs of the Works

82.3.1 The contractor shall do photography/ videography of the site as on quarterly basis and min 50
No's of Photographs should be submitted to AMC along with caption which is covered main
activity of the project .No separate payment will be made to the contractor for this. The
contractor shall have to submit the same in hard copy as well as soft copy on quarterly basis
to AMC.

82.3.2 No photograph of the works or any part thereof or plant employed thereon, except those
permitted to be taken by the Contractor or by any of his employees or any employees of his
sub-Contractors without the prior approval of the Engineer in writing. No photographs/
videography shall be published or otherwise circulated without the approval of the Engineer in
writing.

Signature of Bidder 64 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

G. Special Conditions of Contract

83.0 Special Conditions of Contract

83.1 As the work is to be constructed in heavy traffic area, Employer will not be in a position to give
entire stretch of work at a time. No claim shall be entertained for the same.

83.2 If any underground utility fouls during execution, same shall be shifted by the contractor as
directed by Engineer-in-charge.

83.3 Contractor is required to use his own national / international practices of tracing out or locate
underground utilities below the ground at no cost to the Employer.

83.4 No claim shall be entertained if the items stipulated in the tender shall not be executed as per
site condition/ requirements.

83.5 No idle charges shall be paid to contractor ifany machinery and man power remain idle and no
claim shall be entertained for the same.

83.6 Municipal Commissioner reserve the rights to reduce / increase the scope of work up to any
extent without assigning reason thereof and the contractor has to execute the BOQ items at
his tender rate.

83.7 If any underground cables (electric, telephone, communication, etc.), Gasline foul during
execution contractor shall start work at other available work front until such cables / Gas line
are shifted. No claim for time extension shall be entertained for the same.

83.8 Employer may or may not ask bidder to execute the work of railway portion. No claim shall be
entertained for the same.

83.9 Concrete pavement shall be laid only with slip form paver with electronic sensors.

83.10 Conditions mentioned in the AMC Finance Department Circular No. 9 Dt. 18-05-2012,
Circular No. 18 Dt. 04-07-2012 & Circular No. 53 Dt. 20-11-2014 shall also be applicable.

83.11 The Contractor shall have to maintain all required registers for quality control, material
Management (For all the material on which price escalation clause is applicable.) and
progress of the work as per the AMC's prevailing circulars and as directed by engineer-in
charge on daily basis.

84.0 LABOUR

The Contractor shall make his own arrangements for the engagement of all staff and labour,
local or other, and for their payment, housing, feeding and transport.

The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail, in
such form and at such intervals as the Engineer may prescribe, showing the staff and the
numbers of the several classes of labour from time to time employed by the Contractor on the
Site and such other information as the Engineer may require.

85.0 COMPLIANCE WITH LABOUR REGULATIONS:

During continuance of the contract, the Contractor and his sub contractors shall abide at all
times by all existing labour enactment and rules made there under, regulations, notifications
and bye laws of the State or Central Government or local authority and any other labour law
(including rules) regulations, bye laws that may be passed or notification that may be issued
under any labour law in future either by the State or Central Government or the local authority.
Salient features of some of the major labour laws that are applicable to construction industry
are given below. The Contractor shall keep the Employer indemnified in case any action is
taken against the Employer by the competent authority on account of contravention of any of
the provisions of any Act or rules made there under, regulations or notifications including
amendments. If the Employer is caused to pay or reimburse such amounts as may be
necessary to cause or observe, or for non-observance of the provisions stipulated in the
Signature of Bidder 65 AMC
Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the part of the


Contractor the Engineer or any person authorized by the Engineer shall have the right to
deduct any money due to the Contractor including his amount of performance security. The
Engineer or his nominee shall also have right to recover from the Contractor any sum required
or estimated to be required for making good the loss or damage suffered by the Employer.

The employees of the Contractor and the Sub-Contractor in no case shall be treated as the
employees of the Employer at any point of time.

86.0 SALIENT FEATURES OF SOME MAJOR LAWS APPLICABLE TO ESTABLISHMENTS


ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK.

(a) Workmen Compensation Act 1923:- The Act provides for compensation in case of injury
by accident arising out of and during the course of employment.

b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under theAct on


satisfaction of certain conditions on separation if an employee has completed 5 years
service or more on death at the rate of 15 days wages for every completed year of
service. The Act is applicable to all establishments employing 10 or more employees.

c) Employees P.F and Miscellaneous Provision Act 1952: The Act Provides for monthly
contributions by the employer plus workers @ 12%/8.33%. The benefits payable under
the Act are:
(i) Pension to family pension on retirement or death, as the case may be.
(ii) Deposit linked insurance on the death in harness of the worker.
(iii) Payment of P.F accumulation on retirement/death etc.

d) Maternity Benefit Act 1951:- The Act provides for leave and some other benefits to
workmen/ employees in case of confinement or miscarriage etc.

e) Contract Labour (Regulation & Abolition) Act 1970:- The Act provides for certain welfare
measures to be provided by the Contractor to contract labour and in case the Contractor
fails to provide, the same are required to be provided, by the Principal Employer by Law.
The Principal Employer is required to- take Certificate of Registration and the Contractor
is required to take license from the designated Officer. The Act is applicable to the
establishments or Contractor of Principal Employer if they employ 20 or more contract
labour.

f) Minimum Wages Act 1948: The Employer is supposed to pay not less than the Minimum
Wages fixed by appropriate Government as per provisions of the Act if the employment
is a scheduled employment Construction of Buildings, Roads, Runways are scheduled
employment.

g) Payment of Wages Act 1936:- It lays down as to by what date the wages are to be paid
when it will be paid and what deductions can be made from the wages of the workers.

h) Equal Remuneration Act 1979:- The Act provides for payment of equal wages for work
of equal nature to Male and Female workers and for not making discrimination against
Female employees in the matters of transfers, training and promotions etc.

i) Payment of Bonus Act 1965: The Act is applicable to all establishments employing 20 or
more employees. The Act provides for payments of annual bonus subject to a minimum
of 8.33% of wages and maximum of 20% of wages to employees drawing Rs. 3500/-
per month or less. The bonus to be paid to employees getting Rs. 2500/- per month or
above up to Rs. 3500/- per month shall be worked out by taking wages as Rs. 2500/-
per month only. The Act does not apply to certain establishments. The newly set-up
establishments are exempted for five years in certain circumstances. Some of the State
Governments have reduced the employment size from 20 to 10 for the purpose of
applicability of this Act.

Signature of Bidder 66 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

j) Industrial Disputes Act 1947:- The Act lays down the machinery and procedure for
resolution of Industrial disputes, in what situations a strike or lock out becomes illegal
and what are the requirements for laying off or retrenching the employees or closing
down the establishment.

k) Industrial Employment’s (Standing Orders) Act 1946:- It is applicable to all


establishments employing 100 or more workmen (employment size reduced by some of
the States and Central Government to 50). The act provides for laying down rules
governing the conditions of employment by the Employer on matters provided in the Act
and get same certified by the designated Authority.

l) Trade Unions Act 1926:- The Act lays down the procedure for registration of trade union
of workmen and employers. The Trade Union registered under the Act has been given
certain immunities from civil and criminal liabilities.

m) Child Labour (Prohibition & Regulation) Act 1986:- The Act prohibits employment of
children below 14 years of age in certain occupations and processes and provides for
regulation of employment of Children in all other occupations and processes.
Employment of Child Labour is prohibited in Building and Construction Industry.

n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Service) Act


1979:-
The Act is applicable to an establishment which employs 5 or more inter-state migrant
workmen through an intermediary (who has recruited workmen in one state for
employment in the establishment situated in another state). The Inter-State migrant
workmen, in establishment to which this Act becomes applicable, are required to be
provided certain facilities such as housing, medical aid, travelling expenses from home
upon the establishment and back, etc.

o) The Building and Other Construction workers (Regulation of Employment and


Conditions of Service) Act 1996 and the Cess Act of 1996:- All the establishments who
carry on any building or other construction work and employ 10 or more workers are
covered under this Act. All such establishments are required to pay cess at the rate not
exceeding 2% of the cost of construction as may be modified by the Government. The
Employer of the establishment is required to provide safety measures at the Building or
Construction work and other welfare measures, such as Canteens, First-Aid facilities,
Ambulance, Housing accommodations for workers near the work place etc. The
Employer to whom the Act applies has to obtain a registration certificate from the
Registering Officer appointed by the Government.

p) Factories Act 1948:- The Act lays down the procedure for approval at plans before
setting up a factory, health and safety provisions, welfare provisions, working hours,
annual earned leave and rendering information regarding accidents or dangerous
occurrences to designated authorities. It is applicable to premises employing 10 persons
or more with aid of power or 20 more persons without the aid of power engaged in
manufacturing process.

87. Minimum requirement of Equipments for the work

87.1 The contractor should have minimum machinery as mentioned in Form 1 of Volume -II
(Qualification document) having of its own ownership or show MOU for hiring.

87.2 Contractor shall submit the list of above equipments along with indemnity bond of ownership
for above equipments.

87.3 If the same are to be procured on rental basis, than contractor shall submit the rental
agreement to AMC mentioning that all rental machineries shall be used exclusively for this
Tender work of AMC allotted to contractor.

87.4 Contractor shall submit a bond mentioning that he will deploy separate machineries for each
tender allotted to him.

Signature of Bidder 67 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

88. Avoidance to damage of roads.

The Contractor shall ensure that no damage to roads and bridges on the route to the sites
occurs due to him or his subcontractor’s traffic. He shall ensure minimum possible hindrance
to the traffic movements on public roads and bridges due to his materials, plant, temporary
works etc. No materials shall be stacked on public roads and thoroughfares. The
damaged/dug/excavated road shall be reinstating during construction within a period of 3 days
on completion of activity to its original condition.

89. Transport of Contractor’s equipment

The Contractor shall specifically notify the Employer and the Engineer in case he plans to
transport materials, equipment, plant etc. which might induce such loads on roads and bridges
route to site for which the roads and bridges are not designed. In every such case the
Contractor shall carry out all such strengthening works as may be necessary to ensure the
safety of the roads/ bridges. All such works should be approved by the Engineer in writing.
The Contractor, despite the strengthening measures and written approval by the Engineer,
shall be responsible for the safety of the roads and bridges as well as his own plant, materials
and Equipments.

90. Contractor to keep site clean:

During the execution of the work, the Contractor shall keep the site clean. All wreckage
rubbish, excess materials, temporary works no longer required will be removed from site
immediately.

90.1 Clearance of site on completion:

The Contractor shall clear away and remove all Contractors equipment, surplus materials,
rubbish, temporary works of every kind, except those Contractors equipment, surplus
materials, rubbish, temporary works that may be required by him during the Defects Liability
period and leave the site clean and in a workmanlike condition to the satisfaction of the
Engineer on issue of the Taking Over Certificate.

91. Defaults by Contractor:

If the contractor shall neglect or fail to proceed with the work with due diligence or if he
violates any of the provision of contract the Engineer-in-charge shall give notice to the
contractor, identifying deficiencies in performance and demanding corrective action. After
serving such notice, the contractor shall not remove any plant, equipment and material from
the site. The CLIENT shall have lien on such plant, equipment; materials from the date of
notice served until the said deficiencies have been corrected.

If contractor fails to take satisfactory corrective action within ten days of such notice, the E.I.C.
on behalf of A.M.C shall terminate the contract in whole. In case entire contract is terminated
the amount of security deposit and performance bond together with amount of work done but
not paid for shall be forfeited to the CLIENT. The Plant and equipment and materials held
under this clause shall then be at the disposal of the CLIENT to recover the amount equivalent
to liquidated damages.

92. Maintaining Public Traffic :

(1) The Contractor shall make all necessary provisions for diversions and maintaining the flow
of public traffic and conduct his operations for the construction of the works so as to offer the
least possible obstruction and inconvenience to public traffic. Temporary approaches to
crossings or intersecting roads shall be provided and kept in good condition. Public traffic shall
be permitted to cross over and pass through construction operations at all times with as little
inconvenience and delays as possible and the Contractor shall, when so directed, provide and
station competent flag man whose sole duties shall consist of directing and controlling the
movement of public traffic either through or around the work.

Signature of Bidder 68 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

(2) Where public traffic is required to cross over or pass through the work, construction
operation shall be so conducted as to provide a reasonably smooth, even, dustless and
unobstructed passage for traffic at all times. Water shall be sprinkled as directed for the
abatement of dust in connection with maintaining public traffic. The Contractor shall construct
temporary connection of sufficient width for traffic between the existing road way and new
construction where necessary. At any and all points along with the work where the nature of
the construction operations in progress and the equipment and machinery in use are of such
character as to endanger passing traffic, the Contractor shall provide such personnel as may
be necessary to safeguard against accident and avoid damage or injury to passing traffic.

93. Prevention of nuisance and pollution:

The contractor shall take all necessary precautions to prevent any nuisance or inconvenience
to the owners, tenants or occupations of adjacent properties and to the public generally and to
prevent any damage to such properties and any pollution. He shall make good at his own
expense and the satisfaction of the Engineer-in-charge, any damage to roads, paths, cross
drainage works or public or private property when-so-ever and whatsoever caused due to the
execution of the work or by traffic brought thereon by the contractor. All waste or superfluous
materials shall be cleaned away by the contractor.

94. Fencing and lighting:

(a) The contractor shall, unless otherwise specified, be responsible for the proper fencing,
lighting ,grading ,Traffic arrangement and taking of the necessary safety measures for all
works comprised in the contract and for the proper provision of temporary road, way, foot-way
,guards, fences, caution notices, etc. as far as the same may be rendered necessary by
reasons of the work for the accommodation of workmen, foot passengers or other traffic and of
owners and occupiers of adjacent property and the public and shall remain responsible for any
accident that may occur on account of his failure to take proper & timely precautions.

(b) All the arrangements made for fencing and lighting shall be maintained by the contractor
through the currency of the contract till the physical taking over of the work by department.

(c)Before or during execution, the management of traffic shall be maintained by contractor.


Contractor is fully responsible for taking of particular permission from concern departments of
traffic/police department/commissioner.

95. Action where no specifications

In case of any class of work for which there are no specifications, such work shall be carried
out in accordance with the AMC Prevailing SOR, State, P. W. D. specifications. In the event
there are no such specifications, the work shall be carried out in all respects in accordance
with the instructions and requirements of the Engineer-in-charge

96. Decision of the client to be final

Except where otherwise specified in the contract, the decision of the client shall be final,
conclusive and binding on all parties to the contract, upon all questions relating to the meaning
of the specifications, drawings and instructions herein before mentioned and as to the quality
of workmanship and or materials used in the work, or as to any other aspect whatsoever in
anyway arising, aloof, or relating to the contract, drawings, specifications, estimates,
instructions ,orders for the execution or failure to execute the same, whether arising, during
the progress of the work or after the completion or abandonment thereof if it be the case

97. Damage by storms, fire, rains or accidents:

The contractor shall take all precautions against damage by storms, fire or rains or from
accidents in protecting the works done and the materials, plants procured by him. No
compensation will be allowed to the contractor for damages to works or for his plant or
materials lost or damaged by storm, fire or rains or from any other causes. The contractor
shall be liable to make good any plant or materials of every description belonging to client loss
or damages by storm, fire, or rains or from any other causes while in charge of the Contractor.

Signature of Bidder 69 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

98. Batch Mix Plant

98.1 Bidder shall have own batch mix plant of minimum 100 to 120 TPH capacity in running and
good/operational condition within the limit of 25 km from the boundary of AMC.

98.2 Bidder shall submit health certificate of that plant from the Superintending Engineer,
(Mechanical), Road & Building Department, Gujarat at the time of commencement of Batch
Mix plant.

98.3 If the batch mix plant of bidder is situated anywhere in the country and not within the above
mentioned limit, Contractor shall submit a separate Bank Guarantee of Rs. 50 Lacs (Rupees
Fifty Lacs) (Other than EMD) & an undertaking on the Rs. 100 stamp paper that he will shift &
install Batch mix plant within the specified limit of this tender within the 45 days from date of
LOI. The same shall be released after establishment of Batch mix plant within 45 Days of work
order within the limit of 25 km from boundary of AMC.

98.4 In case of late installation of the batch mix plant, the release of this bank guarantee shall be as
per the sole discretion of Municipal Commissioner, AMC.

99. Providing transportation facility for AMC staff

If necessary and as & when asked by the engineer in charge, the contractor shall provide
transportation facility for AMC staff appointed on his Batch mix plant and road site. Vehicle
provided for this purpose shall be a Four Wheeler in good operational condition with Driver.
The contractor shall not be paid any extra for the same.

100. Tax, Duties on Materials

All charge on account of GST and other Govt. duties / tax or any tax levy etc. on material
procured for the works from any source shall be borne by the contractor. No (P) or "C" or "D"
form shall be supplied by AMC for this purpose.

101. Submission of project schedule:

Contractor has to submit his work plan and methodology to complete the work within the time
limit with the tender documents and also as and when demanded by the AMC during the
running project to monitoring the progress of the Project only.

102. Testing charge

As per St. Committee's resolution, 0.5% testing charges shall be deducted from each R.A. Bill
and the amount of actual testing charges shall be adjusted in the final bill.

103. Bitumen

1. To execute the bituminous items, the contractor shall have to purchase VG-30 grade
Bitumen from the approved Oil Company of AMC.

2. Contractor shall have to submit original purchase bills of Bitumen for verification at the time
of claiming for price escalation to AMC along with sign and certificate for the originality of
the Bills. If any discrepancy found in such submitted bills then it will be Contractors
responsibility. Contractor shall have to provide such original bills

3. Price Variation only for VG-30 grade Bitumen shall be paid to the contractor from the date
of issue of work order and up to the expiry of original and extended time limit.

4. Only the difference between actual rate of purchase mentioned in invoice and the basic
rate for bitumen mentioned in the tender, shall be payable to the contractor or recoverable
from the contractor. Price Variation shall be calculated on the basis of actually
consumption of Bitumen for the work.

Signature of Bidder 70 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

5. The difference will be payable / recoverable from the date of issue of work order and this
price variation will be subject to approval of competent authority.

6. Contractor will be fully responsible to verify the quality, quantity and all other aspects at
the time of receiving delivery of bitumen. No excuse in this regards will be considered
after the bitumen is received and contractor will be fully responsible for quality of work &
its performance etc.

7. In case approved oil company of AMC is failed to Supply required bitumen within
stipulated time frame and if progress of work is hampered due to non availability of
bitumen, the Contractor is bound to purchase bitumen directly from IOCL / BPCL / HPCL
Oil Ltd. only and liable to complete the work within time limit.

8. The VG-10 grade bitumen for tack coat shall be procured by the contractor. No price
Variation for that shall be given.

104. Production of Hot mix material

Productions of hot mix material shall be only from Batch Mix Plant of minimum 100-120 TPH
capacity for the entire work. The contractor shall procure raw materials (aggregates of
different sizes, bitumen, etc.) as required and can stock the material well in advance to
maintain the required progress of work with prior approval of such material from Engineer In
Charge.

All aggregates used in the Hot mix material should be confirmed to the relevant standards and
it should be procured from the approved source/region specifically from the Sevaliya /
Sathamba/ Othvad area only is compulsory and It should be confirmed to the all technical
requirements of the specific Item/Specifications.

Contractor shall have to submit his biding letter that he will supply all the aggregates from the
source finalized by Engineer in charge along with the Quarry names and locations. Contractor
is also bound to produce the All Genuine Original bills for the supply of Aggregates as and
when asked by AMC as well as Contractor is fully responsible for the Originality of the all such
Bills.

105. Laboratory at Plant

The Contractor shall setup a laboratory at plant along with all the calibrated equipments for
testing of asphalt, aggregates, and Hot Mix material with the Material Engineer in the
Laboratory having experience of not less than 3 years in Laboratory testing. The Contractor
has to prepare Quality Assurance Plan (QAP) as per tender terms & Conditions as well as he
has to do all testing as per approved QAP and all reports are submitted along with Running
Bills also to be verify as and when asked by Engineer in charge.

106. Payment of Bituminous work:

After completion of final layer of Bituminous work, only 90% amount of final layer work will
be released. Remaining 10% amount of final layer work will be released after satisfactorily
completion of raising of all Manholes & Catch pits up to finished road level. This remaining 10
% amount can be released for individual road after raising the manholes / catch pits up to
finished road levels.

107. Transportation of Bitumen

107.1 Approved oil company of AMC will supply bitumen from his any refinery in India.

107.2 The Contractor shall have to transport the required VG-30 grade bitumen from the refinery
outlet (for any lead) to his plant site.

104.3 Contractor shall not be entitled to get any payment regarding the transportation of Bitumen for
any lead.

Signature of Bidder 71 AMC


Ahmedabad Municipal Corporation Section – III: Special Condition of Contract

107.4 Transportation of bitumen includes,

1. Provision for the driver, cleaner & necessary reliever including their salary & other
emoluments.
2. Cost of Fuel & lubricating
3. Maintenance & repairs of the tank(s) lorry(s)
4. Road tax, route permit fee, vehicle tax, other taxes & toll charges.
5. Insurance
6. All other charges not specified herein relating to the operation &/or maintenance of the
said tank lorry(s) &/or other charges or costs incidental thereto &/or connected
therewith.
7. All idling charges, loss by delay in transport, transit, road stoppage, delay in time
consumed in loading or unloading of products or otherwise howsoever on account of
operation hereunder.

Seal and Signature of the Bidder City Engineer


Date: Ahmedabad Municipal Corporation
Ahmedabad

Signature of Bidder 72 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

Section – IV Contract Data


1. The Employer is

Ahmedabad Municipal Corporation


“Sardar Patel Bhavan”
Danapith, Ahmedabad – 380 001

2. The Engineer authorized Representative of Employer: The Municipal Commissioner, AMC,


Ahmedabad or his representative deputed by him.

3. The Design Consultant is: Multi Media Consultants Pvt. Ltd.

401, Shivalik Shilp, Nr. Iscon Cross Road,


S,G. Highway, Ahmedabad
Email: info@mmcpl.co.in
Phone: 079 40399079/40399233

4. Defect liability period from the date of completion (as per completion certificate, which shall be
issued by AMC) of work shall be as follows:

One year or one completed monsoon whichever is later for approaches & allied civil
works.
Three year for wearing surface (Bituminous work)

5. The Start Date shall be from the date of issue of notice to proceed with the work.

6. Deleted.

7. Total time limit is 9 months (Excluding monsoon)

8. The Site is located in Ahmedabad City.

9. Name of Work: Construction of RCC Retaining Wall at Mithakhali Underpass on Mithakhali


side only..

10. The following document also form part of the Contract: The notice inviting bids

The Contract Agreement


The instructions to Bidders
The Bid Information
The Letter of Acceptance and notice to proceed with the works
The accepted Contractor’s Bid after amendments, addenda.
The Contract Data
The General Conditions of Contract and special conditions of contract
The Technical Specifications
The Drawings
The Schedule B

Any other document listed in the Contract Data as forming part of the Contract. Submission
made by contractor as per qualification document (Volume-2)

11. The law which applies to the Contract is the law of India

12. The language of the contract document is English

13. Deleted
Signature of Bidder 73 AMC
Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

14. The Schedule of Other Contractors: Nil

15. The Schedule of Key Personnel As specified.

16. The minimum insurance cover for physical property, injury and death is Rs. 15 lacs per
occurrence with the number of occurrences limited to four. After each occurrence, contractor
will pay additional premium necessary to make insurance valid for four occurrences always,
up to expiry of defect liability period.

17. The Site Possession Date shall be the immediate next day on award of work. The
Employer will not be in a position to give entire stretch of work at a time. No claim shall be
entertained for the same.

18. Appointing Authority for the Dispute Review Expert - The Municipal Commissioner,
Ahmedabad Municipal Corporation

19. The period for submission of the program for approval of Engineer shall be 15 days from the
issue of work order / Notice Proceed.

20. The period between program updates shall be 1 Month.

21. Deleted

22. The following events shall not be compensated on any account: Contractor should make its
own assessment for the following aspects before bidding.

Substantially adverse ground conditions encountered during the course of execution of work
not provided for in the bidding document.

(i) Removal of underground utilities


(ii) Significant change in classification of soil requiring additional mobilization by the
contractor, e.g. ordinary soil to rock excavation,
(iii) Removal of unsuitable material like marsh, debris dumps, etc not caused by the
contractor
(iv) Artesian conditions
(v) Seepage, erosion, landslide
(vi) Presence of historical, archaeological or religious structures, monuments
interfering with the works
(vii) Restriction of access to ground imposed by civil, judicial, or military authority
(viii) Suitable arrangement for diversion of traffic.

23. The currency of the Contract is Indian Rupees.

24. Deleted.

25. Amount of Liquidated damages.

100% of work by end of time limit.


i.) If the contractor fails to complete the work under contract by the stipulated date, he
shall pay liquidated damages of at the rate of 0.1 percentage of the contract value per
day from the date of delay the said work upto the date of completion and handing
over the Government.
ii.) However also if the contractor fails to complete any part of the work as designed in
Schedule (c) by the time indicated against such part, he shall pay Liquidated
damages per day from the date of delaying the said part of the work upto the date of
completion of the said designed part at the rates shown in the said schedule of the
contract value of such part for such failure till the said designed part is completed.
iii.) The aggregate maximum of liquidated damages payable under tender clause shall
not exceed 0.10 Percentages of contract value per day and shall be subject to the
maximum amount of ten(10) percentage of the estimated amount put to tender.
iv.) Delay requiring payment of ten percentage liquidated damages of the amount put to
tender for performance shall be sufficient causes for termination of contract and for
Signature of Bidder 74 AMC
Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

forfeiture of security deposit including amount of performance bond in respect of


works estimated to cost more than Rs. 15 Lakh, for performance and registration of
the contract shall also be kept in abeyance for three years from the date as fixed in all
cases.

26. The amounts of the advance payment are:

Any type advance payment will not be given by AMC.

27. Deleted

28. Security Deposit

Security Deposit for 3 % Contract Price to be submitted at award of the work.


The standard form of Security Deposit acceptable to the Employer shall be an unconditional
Bank Guarantee in favors of Municipal Commissioner, Ahmedabad, payable at Ahmedabad
from approved bank as per Annexure–VIII valid till 90 days beyond Date of completion of
work.
The Security Deposit shall be payable in 15 days from date of receipt of LOA failing which
interest @4% per annum will be charged by AMC.

29. Retention Money and performance security:


Retention Money-1:@2% of the value of work done will be deducted from each RA Bill. It will
be released along with the release of Payment of Final Bill.
RetentionMoney-2: Performance security for Defect Liability:
a) For approaches & Allied works other than bituminous work;

Deduction:
Retention money @ 3% of the value of each Running Bill will be deducted including amount of
extra items, price escalation, excluding Cost of wearing surface of Bituminous work and
electrical fittings

Release:
The defect liability period shall be calculated from the date of completion mentioned in the
Completion Certificate of Approaches and allied works other than bituminous work. This
retention money-2 (a) will be released as follows:

Release of Remarks
Retention money-2(a)
It will be released to the contractor at the time of Final Bill
against submission of bank guarantee from approved banks
1.5%
valid up to 90daysbeyondDefects liability period of this work
(one year).
It will be released on completion of Defects liability period of this
work and after engineer has certified that all defects notified by
1.5%
engineer to the contractor before the end of this period have
been corrected / rectified.

b) For Bituminous work:

Deduction:
Retention money @ 10 % of amount of bituminous work including price escalation in Running
Bill shall be deducted against Defect Liability / Performance Guarantee.

Release:
The defect liability period shall be calculated from the date of completion mentioned in the
Completion Certificate of Approaches and allied works other than bituminous work. This
retention money-2 (a) will be released as per Contract data.

Signature of Bidder 75 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

30. Conditions mentioned in the AMC Finance Department Circular No. 9 Dt. 18-05-2012 and
Circular No. 18 Dt. 04-07-2012 and circular no. 53 dated 20/11/2014 and Circular No. 60
dated 24/9/2015 and prevailing circulars shall also be applicable.

31. The Contractor has to submit the “As built” Drawings along-with submission of final bill.

Seal and Signature of the Bidder


Date:
City Engineer
Ahmedabad Municipal Corporation

Signature of Bidder 76 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

SECTION – V: WORK PLAN AND TECHNICAL SPECIFICATIONS

A – PROJECT FEATURES AND WORK PLANNING

1.0 Description of the Project

Construction of RCC Retaining Wall at Mithakhali Underpass on Mithakhali side only..

2.0 Work plan

2.1 Traffic Management during Construction

Traffic management during construction period will be the responsibility of the contractor. In
order to have smooth flow of traffic on existing roads/adjoining service road , temporary
signalized system, adequate number of caution boards, temporary barricades,
delineators etc. will be needed to be provided. This will be treated as incidental to the work
and no extra payment will be made for the traffic management during construction stage.

2.2 Special Precautions to be taken regarding traffic.

Special precautions to safely divert the traffic with smooth movement of continuous traffic
should be taken up before commencing the work. Safety precaution shall be taken up as
required and as directed by the Engineer particularly at cross road junctions.

In addition to the normal barricading the diversion sign boards and signs showing directions
etc are required to be provided. The Contractor shall have to cater for following special safety
measures.

a)Blinking electric warning red coloured lights to warn the vehicular traffic of the obstruction on
the road during construction activities.

b)Strong barricading/fencing of approved design to keep pedestrians segregated from


foundation, superstructure equipment, material, etc.

c)Translucent reflectors, metallic or glass as directed by Engineer-in-Charge.

All schemes of providing safety measures shall be got approved from the Engineer-in-Charge
and the concerned traffic controlling authorities.

It is essential that the Contractor visits the site before submitting his offer to make himself fully
acquainted with the situation and to plan his activities accordingly. No subsequent claims on
this account will be entertained.

2.3 Environmental Safe Guards

All necessary precautions shall be taken by the contractor to avoid degradation of water
quality during excavation. Borrow pits and other scars created during the construction shall be
properly levelled and treated. All the work of excavation quarrying etc. shall be carried out to
minimize the adverse environmental impacts as stipulated in the specifications and as directed
by the Engineer. The rates quoted by the bidders for various items in the bill of quantities shall
be inclusive of all such measures and precautions.

2.4 Space required for casting, stacking etc.

The Contractor is advised to study the problems of stacking, storing, casting, working space,
etc. His construction methods, especially for following items should be carefully planned and
shown in the methodology.
a) Storing, stacking of materials like aggregates, steel, cement, shuttering, scaffolding
materials, dismantled material etc.
b) Planning of the equipments for batching plant, placement concreting etc.
c) Movement of trucks, transit mixture, cars etc.

Signature of Bidder 77 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

d) Location of the site office store etc.


e) Co-ordinating work activities with ongoing work

2.5 Field Investigation, Survey & Geotechnical Investigation:

The first and important activity to be taken-up for this project is to complete the survey and
Geotechnical Investigation work as required and make available the test results and report to
Employer’s Engineer / consultant for further detailed design of foundation and structure.

2.6 Concrete Mix Design:

It is brought to the notice of the Contractor that the concrete design mix for the PQC, Paver
block and other structure. This richer mix is necessary from technical considerations. The
Contractor should therefore, study all the possibilities of achieving the desired results for the
richer mix. He should collect the coarse and fine aggregates of the best quality. The cement
used for this type of concrete should be got tested periodically and should not be more than 3
months old. The Contractor may study the possibility should of adding the necessary
plasticizers and ad-mixtures to achieve this strength with desired workability and finishes
without affecting durability and damaging the reinforcement and high tensile steel. The cost for
any plasticizer admixtures required to add in concrete as per mix design shall be born by
contractor.
2.7 Setting out Works

The Contractor shall be responsible for the true and proper setting out of the works and for the
correctness of the positions levels, dimensions and alignment of all parts of the works and for
the provisions of all necessary instruments and appliances and labour in connection therewith.
If at any time during the progress of works any error shall appear or arise in the positions,
levels, dimensions or alignment of any part of the works, the Contractor on being required to
do so by the Engineer shall at his own expenses rectify such errors to the satisfaction of the
Engineer-in-Charge. The checking of any setting out or of any lines and levels by the
Engineer-in-Charge or his representative shall not in any way relieve the Contractor of his
responsibility for correctness thereof and the Contractor shall carefully protect, preserve and
maintain all bench marks, site rails, pegs etc. used in setting out the works. The costs of
providing, preserving, protecting and maintaining the site rails, pegs, benchmark etc. shall be
deemed to be included in the rate quoted for various items in the schedule B and no separate
payment will be made for the same.

The Contractor shall incorporate into the structure the fixtures for lighting, drainage, road
markers, signals etc. as may be given to him by the Engineer-in Charge, without claiming any
extra cost.

2.8 All temporary works shall conform to the latest specifications of Codes of Indian Road
Congress, IS Standards and other relevant codes and prevailing sound Engineering practices
as mentioned in the contract documents or approved by the competent authority as
applicable.

If necessary and as and when asked by the engineer in-charge, the contractor have to carry
out total station survey of each roads included in the tender showing central line of the road,
location of Manholes, Catch pits, Trees, Temples, Power Distribution Boards, Encroachments
etc. before starting the work on site. Contractor shall have to submit such survey report if it is
asked by Engineer in charge

Signature of Bidder 78 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

2.9 Drawings

The drawings shall be issued to the Contractor as and when necessary keeping in view that
the construction schedule of the project is not disturbed.

The bar bending schedule and shop drawings for structural steel work shall be prepared by
the Contractor and got approved from the Engineer-in-charge before planning of work,
fabrication, cutting or assembling.

All the dimensions shown on the tender drawings are tentative and subject to variation during
execution. Contractor cannot claim for any variation/change in the dimensions shown in the
tender drawings during execution.

Signature of Bidder 79 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

B. Technical Specification

PREAMBLE:

The Technical Specifications contained herein shall be read in conjunction with the other Bidding
stipulations.
3.0 TECHNICAL SPECIFICATIONS:

3.1 The Technical Specifications in accordance with which the entire work described hereinafter
shall be constructed and completed by the Contractor shall comprise of the following:
3.2 In the absence of any definite provisions on any particular issue in the aforesaid
Specifications, reference may be made to the latest codes and specifications of IRC and BIS
in that order. Where even these are silent, the construction and completion of the works shall
conform to sound engineering practice as approved by the Engineer and in case of any
dispute arising out of the interpretation of the above, the decision of the Engineer shall be final
and binding on the Contractor.
3.3 In the absence of any definite provisions on any particular issue in the aforesaid
Specifications, reference may be made to the latest codes and specifications of IRC and BIS
in that order. Where even these are silent, the construction and completion of the works shall
conform to sound engineering practice as approved by the Engineer and in case of any
dispute arising out of the interpretation of the above, the decision of the Engineer shall be final
and binding on the Contractor.

4.0 GENERAL SPECIFICATIONS


4.1 The details of reinforcement of RCC work shall be as per design and instructions of Authority
and his order will be considered final.
4.2 The Contractor shall have to maintain account of steel, cement and other materials that may
be brought by him on site. The account shall be regularly maintained and kept open for
inspection by Authority.
4.3 The Contractor shall remain responsible for workmen's compensation if any, when such case
occurs, the Contractor shall arrange for red lamps at night and fencing and pagi and shall be
responsible for any damage of life and lime or property if any happen, during the execution of
work. In case of dispute for unseen or overlooked items, the decision of Authority shall be
final. The Contractor shall have to give site clean of all rubbish on completion of work and
hand over the road with final finishing of the work as directed. All the rejected materials shall
be removed from site within 24 hours by contractor at his risk and cost.
4.4 For mixing mortar either for masonry or for plaster or for any other purpose contractor shall
have to prepare trough of bigger size and mix the mortar in required proportion. In no case he
shall be allowed to mix the mortar either on floor or any finished surfaces.
4.5 The Contractor shall have to make his own arrangement for water required for the work and
shall pay the water charges as per rules.
4.6 If in the interest of the Employer or site conditions it is necessary to change either any site or
the design of the proposed work the Contractor shall carry out the same at his quoted rates,
without charging any extra and he will be paid at the rates quoted by him and no claim for
extra charges made will be entertained.
4.7 Requisite staging arrangements and shuttering are to be organized so as to ensure smooth
flow of traffic on the roads underneath during the progress of all cast in situ work in
superstructure, piers, portals and foundations. Proper barricading with requisite lights need to
be provided to protect all work sites to avoid any mishaps. The scaffolding/staging system,
shuttering etc. should be conceived in such a way that it is sturdy and at the same time easy
to install and dismantle with minimum interference with running traffic.
Appropriate capacity cranes shall be used for launching of girders.

Signature of Bidder 80 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

4.8 "Cement and Steel will not be supplied by the Employer. The Contractors have to make their
own arrangements for procurement of OPC cement, HYSD TMT bars, Structural Steel and
M.S. Round Bars, etc. for the entire work. The contractors shall have to give necessary test
certificates as per relevant I.S Code before using the same in the work".
4.9 The Contractor will be fully responsible for compliance of the various provisions under
Contract Labour Act, 1970 and the Rules framed there under.
4.10 As per circular No. MGR 2176(96), 2418 (ii) dt. 31.8.77 issued by the Government of Gujarat
contractors are requested to procure their quarry materials required for construction work
through legal sources i.e. only from the quarry lease holders permit holders or middle man
who satisfies the Contractor as to the legality of the source of purchase by him of these
materials.
4.11 All defective works are liable to be demolished, rebuilt and defective materials replaced by the
Contractor at his own cost. In the event of such works being accepted by carrying out repairs
etc as specified by the Engineer in charge, the cost of repairs will be borne by the Contractor
and will be paid for the works actually carried out by him at reduced rates of the tendered
rates, as may be considered reasonable by the Engineer in charge in the preparation of final
or on account bills.
4.12 Clearance of site on completion:
The Contractor shall clear, remove and take away all Contractors equipment, surplus
materials, rubbish, temporary works of every kind and leave the site clean and in a workman
like condition to the satisfaction of the Engineer on issue of the Taking Over Certificate.
4.13 Contractor is required to use his own national/international practices of tracing out or locate
these utilities below the ground at no cost to the Employer.
For Torrent power cables, Gas pipe line, Telecom cables, Street Lighting Board, pole, Cables,
Signal pole,if required to be shifted, AMC shall bear the charges or reimburse the contractor in
case he markets the payment to utility provider against the original receipt submitted by the
contractor. The contractor shall obtain necessary approvals from such authorities and also in
case where payments are not required to be made for such shifting. In all other cases of utility
shifting provisions of bid documents shall prevail.
Contractor shall obtain necessary permits/approvals from the respective Utility Provider/Owner
well in advance of starting the shifting work. The shifting works shall be carried out through
the approved / authorized sub contractor’s of the Utility providers without causing any
inconvenience to the utility users at large.
4.13 PUBLIC UTILITIES:
(a) The contractor shall be responsible to coordinate with service provider / concerned
authorities for shifting of utilities and removal of encroachments etc. and making the site
unencumbered from the project construction area required for completion of work. This
shall include initial and frequent follow-up meetings / actions / discussion with each involved
service provider / concerned authorities. The contractor will not be entitled to any additional
compensation for the delay in shifting of utilities and removal of encroachments by the
service provider / concerned authorities.
(b) The contractor shall make payments to the respective service provider/authorities for
shifting of utilities, wherever required. The Contractor will obtain necessary approvals from
such authorities and also in cases where payments are not required to be made for such
shifting.
(c) Any utility likely to be affected by Contractor’s work should be brought to the notice of the
Engineer and such work shall be undertaken only after getting written clearance from the
Engineer.
(d) The Contractor may be required to carry out certain works for and on behalf of the various
bodies and the Contractor shall also provide, with the prior approval of the Engineer, such
assistance to the various bodies as may be authorized by the Engineer.

Signature of Bidder 81 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan and technical Specification

APPENDIX-A
List of Approved Make for Materials ( Civil Works)

Cement : The contractor shall procure cement from reputed manufacturers of Cement
having a production capacity of one single plant not less than one million
tonnes per annum and holding license to use ISI certification mark for their
product.
Mild Steel : Mild steel for dowel bar shall confirm to IS 432 grade-1.
Reinforcement Steel : Clause no 1009.3.1 of ministry's specifications for road and bridge works
shall be amended as per superintending Engineer-S&R (bridges) for
Director General (Road development) &SS.
"All steel shall be procured from producers who manufacture billets directly
from iron ores and roll the billets to produce steel conforming to IS: 1786. No
re-rolled steel shall be incorporated in the works. The steel shall also be
procured from other producers provided it is manufactured from the billets
made directly from iron ores and not from shredded scrap and sponge iron
as basic feedstock. In such cases, the other producers will have to submit
the proof of purchase such as GST, Invoice etc from the billet producers to
establish that billets are made directly from iron ores and have been
procured from them. The steel shall be got tested by the Engineer in the
NABL affiliated laboratories only as a third party check. It shall be ensured
that all the test results conform to IS: 1786."
"For the steel procured from producers who manufacture billets directly from
iron ores also, the Engineer / Employer may carry out checks on materials
through third party as mentioned above, for conforming to the test results
shown in the certificates so as to ensure the quality of steel supplied."
Structural steel : SAIL, TATA, Essar, JSW, Surya
Epoxy paint : Pidilite , Fair mate, Fosrock, Berger, MC-Bauchemie, Asian paint, Narolac,
Sunanda
Coal Tar Epoxy paint : Pidilite , Fair mate, Fosrock, BASF, Berger, MC-Bauchemie, Shalimar,
Asian paint, Narolac,Sunanda
Paints & Distempers : Asian, Berger, Nerolac, Fosrock, MC-Bauchemie,BASF, Sunanda
Plasticizer /Admixtures / : Asian, BASF, Pidilite , Fair mate, Fosrock, Sika, CICO, Sunanda or
joint filler equivalent
Thermo Plast : Asian paint, Berger Narolac, or equivalent
Bitumen : IOCL, BPCL, HPCL

City Engineer
Ahemdabad Municipal Corporation

Signature of Bidder 82 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

C. Additional Specifications

CLAUSE SP-1 REPAIR OF HONEYCOMBS AND SPALLING


The repair of spalled, honeycombed concrete shall be done by low permeability
polymer modified Cementitious repair mortar.

1.0 Materials

High early strength Portland cement conforming to IS: 8112 shall be used for
production of polymer modified cement repair mortar and polymer modified
Cementitious slurry, which is to be used as a bonding medium with concrete
substrate.

“ The polymer latex which is to be used should consist of water based acrylic
polymer and copolymer dispersion and special purpose chemicals. The polymer
solid contents shall be 29 to 31 percent. The particles shall be nearly spherical
shape with a diameter of 0.30 to 0.40 micrometer. The manufacturer shall certify
to the above requirements about solid content and grain size. In order to keep
control over the quality, the manufacturer shall provide infrared absorption
spectrum analysis for the materials (polymer latex) to be supplied by them. The
same material shall also be used for various purposes such as in a slurry form with cement to
form a bonding or priming medium, with sand and cement in proportions recommended by
manufacturer to form the repair mortar.

No additional water shall be used to prepare the Polymer Modified Concrete


(PMC) slurry or repair mortar as the water present in the latex is sufficient for
cement hydration. The cement/latex ratio shall remain constant for various uses. The
sand to be used for constituting the PMC repair mortar shall be silica sand.

The gradings of the sand shall follow the limits provided as below:

Percentage Passing by weight


IS Sieve No.
Coarse Fine Combined
10mm 100 100 100
4.75mm 95-100 100 98-100
2.36mm 90-100 100 80-100
1.18mm 40-60 100 70-80
600 micron 0-19 90-100 45-55
300 micron 0-4 40-60 20-30
150 micron 0-3 0-10 0-5
75 micron 3 max 0-3 3 max

2.0 Repairing Procedure


2.1 Preparation of Concrete substrata: All defective areas shall be delineated and
marked out on site in conformity with the supervising officer.

Concrete on the damaged, loose or honeycombed areas shall be chipped out up


to the reinforcement level or up to the level of good parent concrete or up to the
point on the reinforcement where the reinforcement is free from corrosion. The
chipping of concrete shall continue to expose the full circumference of the steel
and to a further depth of 10mm as directed by the supervising officer.

The chipped surface of concrete shall be thoroughly cleaned by wire brush and
compressed air to remove all dust and loose materials.

The exposed reinforcement shall be mechanically cleaned of all rust and mill
scale.

2.2 Priming of Concrete Surface and Reinforcement: Before commencing the


application of concrete repair mortar, the prepared concrete substrate shall be
thoroughly soaked with water and the free surface water shall be removed before
priming.

Signature of Bidder 83 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

The well mixed polymer cement slurry (Polymer to cement ratio 1:2) shall be
applied over the well soaked but surface dry concrete and steel bar for adhesion
of fresh cement and sand mortar as per specification and as directed by the
Engineer.

2.3 Cementitious Repair Mortar: The repair mortar of 1 cement : 3 smooth silica
sand shall be applied on the polymer cement slurry in layers of maximum 10mm
thickness each and up to a total thickness of 8-10mm short of outer surface.
The outer surface shall be scarified for good bonding with the next layer.

The polymer modified cement sand mortar in the proportion of 1 polymer: 2


cement: 6 sand shall be applied over the scarified cement sand mortar in
maximum 10mm thickness and finishing smooth up to the existing surface of
concrete as per specification and as directed by the Engineer.

Curing of the repaired areas with PMC mortar shall be done in accordance with
acceptable good practice. However, no curing compound or curing membrane
shall be used and curing shall only be done by spraying of water or by using wet
hessian cloth.

CLAUSE SP-2 FIXING DOWEL BARS IN CONCRETE

1 Scope

The work shall consist of fixing HYSD bars in the existing concrete deck
slab/other concrete components to facilitate bonding of a structural
component with an existing one.

At least 14 days before start of the work, the contractor shall furnish
detailed methodology of construction including sources of supply of
material, tools, equipment and appliances be used on work, details of
personnel and supervision.

The contractor’s personnel shall be qualified and experienced in repair and


rehabilitation work of such nature.

2 Materials

HYSD bars shall conform to Section 1000

The grout material used for fixing HYSD bars in drilled holes in concrete
shall be obtained from a reputed manufacturer and grout mix shall be
prepared in conformity with the manufacturer’s recommendations. The
material shall be either of the following:

(a) Two/three component low viscosity epoxy resin system, having


required characteristics of bonding with concrete and resistances to
moisture penetration (Resicrete 21 or Resicrete 212 of M/S Structural
Waterproofing Co. or SIKADUR BTP of M/S Sika Qualcrete or
equivalent).

(b) Cement grout in powder form consisting of cement, good quality sand
and admixtures when mixed with required amount of water forms a
pourable mix to be used for bonding HYSD bars in concrete (EXCEM
– E1 manufactured by M/S Structural Water Proofing Company or
M/S SIKADUR or equivalent).

The epoxy resin system shall conform to Clause 2803.

The cement grout shall basically be shrinkage compensated, chloride free


and of very high strength (50 MPa at 28 days). The mix should be capable
of pumping or pouring and shall have excellent bond strength with
concrete and steel (bond strength of 15 MPa with HYSD bars at 28 days).

Signature of Bidder 84 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

3 Construction Operations

The construction operation shall be in the following sequence, and shall be


supervised by the Contractor’s Engineer well experienced in such works:

(i) Drill holes of required diameter and depth at desired locations as


shown on drawings.

(ii) Clean the hole with air blast through air nozzle of 6-mm dia
connected to air compressor to remove the drilled powder, which may
remain inside the drilled hole.

(iii) Mix the required quantity of grout so that the work could be completed
within the normal setting time as specified by the manufacturers.

(iv) Pour required quantity of mixed grout in the holes.

(v) Insert the dowel rod in the hole where grout has been placed. Move the
rod up and down several times to drive out entrapped air, if any.

(vi) Allow the curing time as per manufacturers specifications.

(vii) Inclined dowels shall be straightened to match their intended profile


only after the grout has finally set and required strength has been
achieved.

4 Measurements for Payment


Measurement for fixing HYSD bars in concrete involving drilling in
concrete and fixing HYSD bar with suitable fixing agent shall be measured
in number of such HYSD bars fixed in position.

5 Rate
The contract unit rate for fixing of HYSD bars in existing concrete
slab/other components shall include cost of all material, labour, tools and
plants, drilling required diameter hole in concrete, placing in position,
temporary works, testing and curing and other incidental expenses for the
satisfactory completion of the work as per the specifications.

CLAUSE SP-3 PLANT AND EQUIPMENT FOR AGGREGATES AND CONCRETE

1.0 AGGREGATE PROCESSING PLANT

Aggregate processing plant to be provided by the Contractor shall conform to


the following:

1.1 TYPE OF PLANT

Except where aggregates are supplied from commercial sources, a modern


and dependable aggregate plant capable of producing satisfactory concrete
aggregates in sufficient quantities and the rate necessary to met the
requirements of the construction schedule shall be provided at a location
acceptable to the Engineer. Complete facilities shall be provided for proper
crushing, washing, classifying, storing, reclaiming and delivering the
aggregates to the mixing plant.

1.2 SAMPLES AND TEST


The aggregate plant shall be operated for a sufficient time in advance of the
dates set for first placement of concrete to permit the development of
procedures which result in high capacity production of aggregates proven by
tests to meet all the requirements of this specification.

Signature of Bidder 85 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

1.3 FINES IN SAND


The facilitation for fine aggregate production shall be so designed and
operated as to retain the necessary quantity of finer fractions. An excess of
fines will not be permitted. All crushing, washing, screening, classifying,
blending, batching, or other properties of fine aggregate necessary to meet
these specifications shall be performed so as to produce acceptable gradation
complying with this specification.

1.4 DRAINAGE OF SAND

Aggregates shall not be removed directly from the washing or classifying


operations to the aggregate bins in the concrete mixing plant, but shall be
stored as required, to permit drainage of excess water and in such a manner
as to avoid contamination by foreign materials. Sand shall remain free-
draining storage for at least 48 hours prior to use.

1.5 SEGREGATION

The stock piles for aggregates shall be formed so as to prevent segregation,


and as approved by the Engineer. The deposition and removal therefrom
shall be done in a manner to maintain the uniformity of grading. The side
slopes of stock piled aggregates shall be kept flatter than the angle of repose
to prevent accumulation of coarser material at the bottom of the slope.

1.6 VOLUME OF STORAGE

Sufficient live storage of all size fractions of processed aggregates, shall be


maintained at all times, to permit continuous placing of concrete at the rates
so as to meet the Schedule requirements. If aggregates are stock piled on
the ground, the bottom portion of the stock pile within 30 cm of ground shall
not be used. The Contractor may also plan to store sufficient quantity of
coarse and fine aggregate so that concreting during monsoon can proceed
without hindrance as the collection of the same during monsoon may be
difficult.

1.7 APPROVAL OF AGGREGATE PLANT LAYOUT

Plans and written specifications for the aggregate processing plant including
description and capacity data on the processing equipment, and flow charts of
the whole processing operation which shall show rates of flow of material at
the various crushing and separation points in the processing, as well as the
volumes of the stock piles and the number and types of equipment to be used
in transporting the aggregates from aggregate plant to the mixing plant shall
be submitted to the Engineer in advance of plant erection for his approval.

2.0 CONCRETE PLANT

A modern dependable batch type automatic mixing plant capable of producing


concrete of specified quality and at the rate of output required to meet the
schedule requirements, and a balanced complement of transporting, handling
and placing equipment shall be provided at locations and in a manner
approved by the Engineer. The concrete mixing plant shall be completely
installed for a sufficient length of time prior to scheduled date for placement of
first concrete, to enable the Engineer to make the necessary physical tests
prior to use of the plant for the production of concrete.

2.1 STANDBY ARRANGEMENT

As a standby arrangement to the batching and mixing plant the stationary


mixer / mixers of capacity 700 litres of mixed concrete and other appropriate
equipment shall be provided.

Signature of Bidder 86 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

2.2 TYPE OF PLANT

The type of plant to be furnished shall be fully automatic.

The term “automatic” is used to define a plant in which :

i) Batch weights are set manually on a mix selector


ii) Mixes are charged automatically by mix selector
iii) Materials are batched automatically

Ice flaking machine of sufficient capacity shall be installed as a part of


batching plant.

2.3 BATCHERS

Individual weigh batchers shall be provided for all works, requiring the use of
more than two separate size groups of coarse aggregates. Cumulative
weight batchers may be used for work requiring the use of not more than two
separate size groups of coarse aggregates provided the cement is weighed
and batched separately from the aggregates. The batchers shall be arranged
to permit the convenient addition or removal of material. Batching equipment
shall be so constructed and arranged that the sequence and time of discharge
can be controlled to produce a re-blending and mixing of the aggregates and,
wherever possible, mixing of the cement with the aggregates as the materials
pass through the charging hopper in to the mixer. This control shall be
effected by the controls of the batcher discharge gates. Batcher controls
shall be so interlocked that a new batching cycle cannot be started until all
batchers are completely empty.

i) Weighing Units

Every delivering point of aggregates and cement in to the mixer, charging


hopper shall have a weighing unit and each weighing unit shall include a
visible, spring less direct reading dial which shall indicate the scale load at all
stages of the weighing operation from zero to full capacity. The scale dials
and the weighing equipment shall be in full view of the operator, so that he
may conveniently observe the operation of the batcher gates and the
discharge of the materials. Provision shall be made for adjustment and
change in weights of materials being charged in the hopper.

ii) Measuring Water & Ice

Water shall be measured by weight except in situations for which written


approval is given by the Engineer to measure by volume. The mechanism for
measuring and delivering water to the mixers shall not permit leakage when
the valves are closed. Ice shall be measured by weight. The filling and
discharge shall be measured by weight. The filling be capable of ready
adjustment to permit varying the quantity of the admixtures to be batched.
The equipment shall be kept in a clean and fully operating condition.

iii) Tolerance in Batching, Weight Errors

Weighing devices shall be capable of measuring the various ingredients of the


following accuracy.

Materials Percent

Cement 1 (by weight)


Water 1 (by weight)
Aggregate smaller than 40mm size 2 (by weight)
Admixture 1 (by weight or volume)

Signature of Bidder 87 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

iv) Records & Charts

An accurate record shall be maintained at the batching plant by the contractor


for the followings:

a) The weight of the cement, water and admixture.


b) The weight of the aggregate for each size shall be recorded
separately.
c) Temperature of the concrete immediately after mixing.
d) Mixing time of each batch when all the materials are loaded into the
mixer.
e) Time when the concrete is delivered from the mixer.
f) Ambient temperature.

v) Recorder Records & Charts

A recorder shall be provided for each set of units measuring each of the
materials delivered to the mixer. The recorder shall produce a continuous
visible record, on a single ruled chart, of the weight of the cement, water and
each size of aggregates, of the mixing time of each batch after all materials
are in the mixer, of the temperature of the concrete and of the time of day at
intervals of not more than fifteen (15) minutes. The recorder shall be
completely housed and shall be capable of being locked and shall be placed
in a position convenient for observation by the plant operator and the
Engineer. Each chart shall be so ruled and printed that it may be readily and
permanently identified, so that the quantities and time may be read directly
without scaling or calculation. A portion of the recorder chart equivalent to at
least thirty (30) minutes of plant operation shall be visible after recording.
This portion of the chart shall be supported over its entire width on a smooth,
firm backing so that notes can be made without puncturing the paper. The
recorders and scale dials shall be housed in a room, box or compartment
visible at all times and sufficiently tight to exclude objectionable dust coming
from the plant operation.

vi) Cement Weight Recorder

This shall be provided separate from and in addition to the autographic


recorder chart, an automatically printed record of the quantity of cement
discharged from the batobers for each batch of concrete. The weight of the
cement charged shall be recorded in kilograms, the recording shall be
continuous and each batch shall be recorded separately. The interconnecting
mechanism from the batcher to the recorder shall be locked and the key
thereafter turned over to the Engineer.

vii) Air Temperature Recorder

There shall be provided on autographic record of the air temperature. The


thermometer shall be placed at location so as to truly represent the outside air
temperature at the site. The recorder itself shall be properly housed.

2.4 Mixers may be stationery mixers of either the tilting or non-tilting type of
approved design.

i) Maintenance

The mixers shall be maintained in satisfactory operating condition, and mixer


drums shall be kept free of hardened concrete. Mixer blades shall be
replaced when worn down more than 10 percent of their depth. Should any
mixer at any time produce unsatisfactory results, leak mortar or cause
wastage of materials, its use shall be promptly discontinued until it is repaired.

Signature of Bidder 88 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

ii) Mixing Time

The mixing periods specified herein are to ensure proper quality control. The
mixing time will be increased when such increase is necessary to secure the
required uniformity and consistency of the concrete. Excessive overmixing
requiring additions of water will not be permitted. When stationary mixers are
used, the mixing time for each batch shall be as follows;

Time shall start when all solid materials are in the mixer drum, provided that
all of the mixing water shall be introduced before one-fourth of the mixing time
has elapsed. The Engineer, may, however, direct change in mixing time, if
he, in his opinion, considers such change necessary.

Capacity of Mixer (Cubic Metre) Time of Mixing (Min.)

Up to 2.00 Cubic Metre 1½


Up to 3.00 Cubic Metre 2
Up to 4.00 Cubic Metre 2½

Stationary mixers shall be provided with an acceptable device to lock the


discharge mechanism until the required mixing time has elapsed. Provision
also shall be made to assure that each batch is discharged completely before
the mixer is recharged.

2.5 PROVISION FOR INSPECTION

The complete plant assembly shall include provisions to facilitate the


inspection of all operations at all times.

2.6 MAINTENANCE OF RECORDS

All records and charts of the batching and mixing operations shall be
prepared as specified herein and promptly turned over to the Engineer.

2.7 SAMPLING FACILITIES

Suitable facilities shall be provided for readily obtaining representative


samples of aggregate from each of the batchers, and suitable devices for
obtaining representative samples of concrete for slump tests, unit weight, air
content, and uniformity tests to be made by the Engineer, shall be provided.
All necessary platforms, tools and equipment for obtaining samples shall be
furnished at the start of work.

2.8 CONCRETE SPECIMENS

Concrete specimens will be prepared from the mixes used in the work and
tested to determine the adequacy of control of the materials entering into the
concrete mix. Preparation, storage and testing of the specimens will be
performed by the Engineer. Suitable facilities when demanded shall be
provided within the plant for the Engineer and his assistants to carry out the
necessary control work.

2.9 TEST WEIGHTS

Standard test weights and any other auxiliary equipment required for checking
the operating performance of each scale or other measuring device shall be
provided. Periodic tests shall be made in the presence of the Engineer in
such a manner and at such intervals as may be directed by the Engineer.
Upon completion of each such test, and before further use of the measuring,
weighing or recording devices, such adjustments, repairs, or replacements
shall be made as may be required to secure satisfactory performance.

Signature of Bidder 89 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

2.10 APPROVAL OF CONCRETE PLANT LAYOUT

Plans and Technical data for the concrete plant proposed for use to produce
the quantities and quality of concrete for completion of the concrete works
under this specification shall be submitted to the Engineer alongwith the
tender.

CLAUSE SP-4 CURING USING LIQUID MEMBRANE FORMING COMPOUND

1.0 GENERAL

Liquid membrane forming compounds are sometimes permitted to be used by


the Engineer for curing concrete for part or whole of the total curing period as
specified in sections dealing with concrete construction. These membranes
reduce the loss of water from concrete during early hardening period and
some types of compounds also help in reducing the temperature-rise of
concrete exposed to the radiation from the sun. These specifications cover
the type and use of such compounds. However, the use of the same will
need specific permission from the Engineer, who may require a number of
tests to be carried out for establishing the conformity of the product to these
specifications and to establish that the curing compound and its method of
use does not have any unacceptable effect on the quality of concrete. The
cost of the initial acceptance testing and the quality control testing will be
borne by the Employer, if the Engineer has specified the method as a
requirement. If on the other hand, it is suggested by the Contractor as an
alternative to wet curing, the full cost of testing will be borne by him and
deemed to be included in his rates for concreting. The cost of curing in any
case will be deemed to be part of the concrete rates and will not be paid
extra.

All equipment, material etc. needed for curing and protection of concrete shall
be at hand and ready for installing before actual concrete begins. Detailed
plans, methods and procedures whereby the various phases of curing and
protection shall be firmly established, shall be settled and got approved in
writing from the Engineer-in-charge sufficiently in advance of the actual
concreting. The equipment and method proposed to be utilised shall provide
for adequate control and avoid interruption or damage to the work of other
agencies.

2.0 SUPPLY AND TESTING

2.1 ACCEPTANCE TESTING

Prior to the approval of the brand / trade name of compound and the source
of supply and manufacturer acceptance testing shall be carried out to
demonstrate the conformance of the compound to clause 2. In addition,
testing shall be performed to demonstrate that no adverse / undesirable
change in quality of concrete or concrete surface takes place as a result / by-
product of the use of the compound. These tests should be designed to
check properties such as loss of strength at 28 days of surface layer, or of
concrete cube, change in surface texture, change in adhesion to
subsequently applied layer like plaster, flooring, tiling etc. The type and
number of tests are to be as specified by the Engineer.

2.2 ROUTINE TESTING

1. The liquid membrane forming curing compound should be brought in the


manufacturer’s original clear containers. Each container shall be legibly
marked with the name of the manufacturer, the trade name of the compound,
the type of compound and class of vehicle / solids, the nominal percentage of
volatile material and batch or lot number. The lot numbers will be assigned to
the quantity of compound mixed, sampled and tested as single product. The

Signature of Bidder 90 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications
manufacturer shall exercise the care in filling the container so that all are
equally representative of the compound produced.
2. Curing compound to be used on site shall be got tested at least 14 days in
advance so that the result of water retention tests, reflectance test, drying etc,
are available before it can be permitted for use. All of the filled containers
represented by the approved sample shall then be sealed to prevent leakage,
substitution or dilution. The Engineer-in-charge or authorised representative
should mark each container represented by the samples with a suitable
identification mark for later identification and correlation and shall be kept in
store with double lock arrangements. One key shall be kept with the
Contractor and the other with Engineer. Random samples shall be collected
from every batch of the compound. Frequency of random sampling shall be
done as directed by the Engineer. The Contractor shall provide samples and
labour for collecting samples free of cost. Testing shall be carried out by
agency approved by the Engineer and in presence of his representative.

3.0 METHOD OF APPLICATION

The compound shall be sprayed using mechanical sprayer of approved


design to ensure uniform and continuous membrane on the concrete surface.
The coverage shall be at the rate specified by the manufacturer or at the rate
of 4 m2 per litre or as specified by the manufacturer and approved by the
Engineer. Field trials shall be conducted to decide effective coverage rate,
which depends upon surface finish. The Engineer after verification of the field
trials and based on the actual experience shall order the rate of application as
needed for achieving the proper curing. With a view to ensure thorough and
complete coverage, approximately one half of the compound for a given areas
should be applied by moving the spray gun back and forth in one direction
and the remaining half at right angles to this direction. In case the application
is still not found uniform, the Contractor shall have to apply the second coat
as an when directed by the Engineer. If a second coat is to be applied, it
should be applied approximately after an interval of one hour. The curing
compound shall generally be applied as soon as the bleeding water or shine
disappears, leaving dully appearance.

If surface treatment by roughing, hand brushing etc., is required (e.g. as in


case of road pavements) the curing compound should be applied immediately
after the same. Equipment for spraying curing compound shall be of pressure
2
tank type (5 to 7 kg/cm ) with provision of continuous agitation. A curing
jumbo with multiple travelling spray fans shall be provided for effective spray.
Spraying on concrete lining shall be done in such a way that the green
concrete is not disturbed or damaged or any foot impression left. Necessary
schemes or spraying by mechanised means shall be got approved by the
Engineer-in-charge. However, in emergency for very small areas / patches) it
can be applied with wire or bristled brush.

Signature of Bidder 91 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

D Amendments/Modifications/Additions to Existing Clauses of


General Technical Specifications(MORTH)

SECTION 1500 FORMWORK


CLAUSE 1503 DESIGN OF FORMWORK
Clause 1503.2 Add the following at the end of this Clause :

"For distribution of load and load transfer to the ground through staging, an
appropriately designed base plate must be provided which shall rest on firm
sub-stratum."

CLAUSE 1505 FORMED SURFACE AND FINISH


(Substitute
clause) Substitute the following clause in place of the existing clause:

Formed & Unformed Surface Finishes

The surface finishes for formed and unformed surfaces are classified and
defined as below. Surface irregularities permitted for the various classes of
finishes are termed either 'abrupt' or 'gradual'. Fins or offsets caused by
displaced or misplaced form sheeting, lining or form sections, by loose knots in
form lumber or by otherwise defective form lumber are considered abrupt
irregularities. All other cases are described as gradual irregularities. Gradual
irregularities will be measured with a template consisting of a straight edge for
plans surfaces or its equivalent for curved surfaces. The length of template for
testing gradual irregularities on formed surfaces shall be 1.5 m in length, the
permissible gradual irregularities being measured over this length of the
template.

Finish F1, F2 and F3 shall describe formed surfaces.


Finish U1, U2 and U3 shall describe unformed surfaces.

Class F1 Finish
This class of finish shall apply to all formed surfaces for which class F2 or F3 is
not specified. It shall generally be formed by sawn timber formwork/timber frame
or steel frame mounted with plywood or steel sheet. It shall be so constructed
that there shall be no loss of material from the concrete during placement and
compaction. After hardening, the concrete shall be in the required positions and
shall have the shape and dimensions called for in the drawings. Any abrupt
irregularities shall not exceed 10mm. All fins and drifts in excess of the above
limits shall be made good by chipping and grinding if required by the Engineer-
in-Charge. Small blemishes caused by entrapped air or water may be expected
but the surface shall be free from voids, honeycombing or other large
blemishes. Class F1 finish shall be generally specified for all surfaces buried in
ground or not visible during service or for surfaces that are to receive further
rendering treatment such as plastering etc. Unless otherwise specified in the
item of Bill of Quantity the surface finish shall be understood to be Class F1.

Class F2 Finish
Class F2 finish shall be obtained by the use of properly designed forms, either
close jointed wrought timber forms or with forms having plywood or steel sheet
lining. The abrupt irregularities shall not exceed 5mm and gradual irregularities
shall be less than 8mm. Small blemishes caused by entrapped air or water may
be permitted but the surface shall be generally free from honeycombing, voids
and large blemishes. Surface irregularities in excess of those stipulated shall
be removed by chipping or rubbing with abrasive stone.

Class F3 Finish
Class F3 finish shall be formed by specially designed close jointed rigid forms
having lining of high quality form plywood. The surface irregularities shall be
limited to nil for abrupt irregularities and 3 mm for gradual irregularities. Class
F3 finish may be obtained from class F2 finish by carefully removing all abrupt

Signature of Bidder 92 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications
irregularities including fins and projections by rubbing/grinding. If steel forms are
used they shall have steel sheet backing faced with plywood.

In addition, finish F3 shall include filling air holes with mortar and treatment of
the entire surface with sack rubbed finish. It shall also include clean up of loose
and adhering debris. For a sack rubbed finish, the surface shall be prepared
within two days after of removal of the forms. The surface shall be wetted and
allowed to dry slightly before mortar is applied by sack rubbing. The mortar
used shall consist of one part cement to one and one half parts by volume of
fine (I.S. No. 16 mesh) sand. Only sufficient mixing water to give the mortar a
workable consistency shall be used. The mortar shall then be rubbed over the
surface with a fine burlap or linen cloth so as to fill all the surface voids. The
mortar in the voids shall be allowed to stiffen and solidify after which the whole
surface shall be wiped clean with clean burlap such that all air holes etc. are
filled and the entire surface presents a uniform appearance without air holes,
irregularities etc.

Class U1 Finish
This is the screeded finish used on surfaces over which other finishes such as
wearing coats etc. are to be placed. It is also the first step in the formation of
U2 and U3 finishes. The finishing operation consists of levelling and screeding
the concrete to produce an even and uniform surface so that the gradual
irregularities are not greater than 5 mm. Surplus concrete should be removed
immediately after consolidation by striking it off with a sawing motion of a
straight edge or template across a wooden or metal strip that has been set as
guide. Unless the drawings specify a horizontal surface or show the slope
required, the tops of narrow surfaces, such as stair treads, walls, curbs and
parapets shall be sloped approximately 10 mm per 300 mm width. Surfaces to
be covered with concrete topping, terrazzo, and similar surfaces shall be
smooth screeded and levelled to produce even surfaces, irregularities not
exceeding 5mm.

Class U2 Finish
This is a floated finish used on all outdoor unformed surfaces not prominently
exposed to view such as tops of piers etc. The floating may be done by hand or
power driven equipment. It should not however be started until some stiffening
has taken place in the surface concrete and the moisture film or 'shine' has
disappeared. The floating should work the concrete no more than is necessary
to produce a surface that is free from screed marks. All joints and edges should
be finished with edging tools. It shall include the repair of gradual irregularities
exceeding 5 mm. All abrupt irregularities shall also be repaired unless a
roughened texture is specified.

Class U3 Finish
This is a trovelled finish used on all surfaces exposed to view at close quarters
such as tops of parapets and kerbs etc. Steel trovelling should not be started
until after the moisture film and 'shine' have completely disappeared from the
floated surface and the concrete has hardened enough to prevent an excess of
fine material and water from being worked to the surface. Excessive trovelling,
especially if started too soon, tends to produce crazing and lack of durability.
Too long a delay will result in a surface too hard for proper finishing. Steel
trovelling should be performed with a firm pressure that will flatten and smooth
the sandy surface left by floating. Trovelling should produce a dense, uniform
surface free of blemishes, ripples and trovel marks. It shall include the repair of
all abrupt irregularities and the repair of gradual irregularities exceeding 5 mm.
It shall also include finishing the joints and the edges of concrete with edging
tools.

CLAUSE 1509 RE-USE OF FORMWORK


(Substitution)
This Clause shall read as under:

"After forms are stripped, all materials shall be examined for any damage and
damaged pieces, if any, shall be removed either as rejected or for rectification if

Signature of Bidder 93 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications
possible. The materials found fit to be reused shall be thoroughly cleaned. Holes
bored through sheathing for form ties shall be plugged by driving in common corks
or foamed plastics. Patching plaster may also be used to fill small holes. After
cleaning and before re-fixing, each formwork shall be got approved from the
Engineer.

Form work and staging shall be so used as to ensure quality of the exposed
surface. If in the opinion of the Engineer, any particular panel/member has
become unsatisfactory for use at any stage, the same will be rejected and
removed from site.”

Clause 1514 SPECIAL ARCHITECTURAL FINISHES


(Additional
Clause) Materials

Where special architectural finishes have been specified which require special
patterns, grooves, ridges, surface finishes etc., and which are to be obtained by
casting concrete against forms, need specially designed forms and special
finishing using suitable materials. These forms can be made from materials
specified in IRC-87, relevant IS codes with special workmanship/controls. Use
of any other material is to be permitted only after specific written approval from
the Engineer.

Design and Workmanship, Removal, Protection and Reuse


The design and workmanship of these formwork has to be got approved from
the Engineer. The method of removing formwork without damaging the 'form-
finished' surface, use of de-bonding agents, the protection and repair of forms
and forms-surfaces, and limit on re-use etc. are to be as per
specification/drawings in absence of which the proposed details are to be got
approved from the Engineer. All such methods will have to be suitably
improved based on the result of mock-up or field use. The final procedure and
details shall be improved till the specified/desired architectural finish is obtained.

Mock-up

After design and before incorporation in the main work, the effectiveness and
success in achieving the desired finish has to be demonstrated/confirmed by
casting the mock-up. The approved 'mock-up' surface shall be retained till the
end of the project and then the 'mock-up' should be dismantled/removed from
the work site and disposed off as directed by the Engineer.

Measurement and Payment


The measurement and payment for these items will be as specified in BOQ.

Clause1515 TOLERANCES
(Additional
Clause) All works shall be carried out true to the lines, levels and grades shown on the
drawings and within the tolerances specified below. The forms shall be so
designed and erected that the following tolerances are not exceeded unless more
stringent and specific specifications have been required by the design and specified
in the drawings/instructions. The contractor shall establish, erect and maintain in
an undisturbed condition until final completion and acceptance of the project,
control points and bench marks necessary and adequate to establish these
tolerances.

Element Limits
- For all elements, departure from established 10 mm
alignment

- Departure from established grades 10 mm

- Variation from plumb or specified batter in lines 10mm in 3 m. if exposed 20mm


and surfaces of piers, walls and abutments in 3 m. if backfilled

Signature of Bidder 94 AMC


Ahmedabad Municipal Corporation Section – V : Work Plan & Technical Specifications

- Variation from level or indicated grade in slabs, 10mm in 3 m. if exposed


beams, horizontal and railing offsets 20mm in 3 m. if backfilled.

- Variation in cross sectional dimensions of -5mm, + 10mm


columns, piers, slabs, walls, beams and similar
parts

- Variation in slab thickness -5mm, + 10mm

- Footings:
Plan dimensions -15mm, + 30mm

Misplacement or eccentricity 2% of footing width in the


direction of displacement and
not exceeding 30mm.

Reduction in thickness 5% of specified thickness


unless specified to be more
stringent.

- Variations in size and locations of slab or wall 10mm


openings

- The Alignment Tolerances shall be as under:

Tolerance in direction where `d' is the


dimension of members

Member with a depth of upto200 mm ± d/40


More than 200 mm 5 mm

SECTION 1700 STRUCTURAL CONCRETE

CLAUSE 1704 PROPORTIONING OF CONCRETE


(Addition) Add the following at the end of this clause:

“In proportioning concrete, the quantity of both cement and aggregate shall be
determined by weight. Where the weight of cement is determined by accepting the
manufacturer’s weight per bag, a reasonable number of bags shall be weighed
separately to check the net weight. Where cement is weighed form bulk stock at
site and not by bag, it shall be weighed separately form the aggregates. Water
shall either be measured by volume in calibrated tanks or weighed. All measuring
equipment shall be maintained in a clean and serviceable condition. Their
accuracy shall be periodically checked.

It is most important to keep the specified water-cement ratio constant and at its
correct value. To this end, moisture content in both fine and coarse aggregates
shall be determined as frequently as possible; frequency for a given job being
determined by the Engineer according to the weather conditions. The amount of
mixing water shall then be adjusted to compensate for variations in the moisture
content. The determination of moisture content in the aggregates shall be done as
per IS: 2386 (Part III). Suitable adjustments shall also be made in the weight of
aggregates to allow for the variation in weight of aggregates due to variation in
their moisture content.”

Signature of Bidder 95 AMC

You might also like