Residence Residence Building (EPS) 1-Click enterprise tab in the menu bar and select the enterprise project structure. Building (EPS) 2- click add on the command bar to add new EPS. Building (EPS) 3- use the arrow tabs to optimize the new EPS in the hierarchy. Building (EPS) 4- add nodes and completely EPS. Organizational break down structure (OBS)
OBS element are assigned as responsible
manager for work within an EPS elements, project, Work break down structure. Genral Manager (Eng/Atef)
Manager for Saudi Arabia Projects
Manager for Egypt projects (Eng/Ahmed) (Eng/Mohamed)
Manager of Industerial Manager of Residential Manager of Industeria Manager of Residential
Manager of Alex Manager of Jeddah Area Al-Khobar Area Riyadh Area Cairo Area Area (Eng/Waleed) Sharm El-Sheikh Area (Eng/mahmoud) (Eng/yasser) (Eng/Hassan) (Eng/Moustafa) (Eng/Adel)
Manager of Project Manager of Project Manager of Project
Riyadh Residence Riyadh Residence Riyadh Residence (Eng/Islam) (Eng/Hany) (Eng/Islam Building (OBS) 1-Click enterprise tab in the menu bar and select the OBS. Building (OBS) 2- click add on the command bar to add new OBS, and use arrows to optimize the new OBS in the hierarchy. Building (OBS) 3- click the enterprise tab in the menu bar and select the enterprise project structure and select the responsible manger for EPS. calendars. Calendar is used for scheduling activities, and activity type determines whether the activity uses the calendar of the assigned resource or activity calendar. Types of calendars. 1- Global: contains calendars that can be used by all projects, available for all resources and activities.
2- Project: contains separate pool of calendars for each
project in the EPS, available for current project only.
3- Resource: contains separate calendar for each
resource. Creating Calendar. 1-Click enterprise tab in the menu bar and select Calendars. Creating Calendar. 2-Cick add to add new calendar in global window, and select calendar to copy from then rename it. Creating Calendar. 3-Cick Modify button then work week button, and nonwork button to adjust working days. Creating Calendar. 4-Select project window, then click add, then select the calendar of project and rename it with the project name.