Professional Documents
Culture Documents
net/publication/340679775
CITATIONS READS
0 238
1 author:
Richard Radevsky
Charles Taylor Adjusting
10 PUBLICATIONS 12 CITATIONS
SEE PROFILE
All content following this page was uploaded by Richard Radevsky on 16 April 2020.
Project teams naturally tend to focus their efforts mostly on project progress and solving complex
engineering issues. They may not have sufficient construction insurance expertise to anticipate
coverage problems that can be raised in the regular meetings with their brokers. It is not always easy
for the project team to identify where coverage needs clarifying or where there are gaps. They may
also not realise the consequences of failing to comply with policy conditions or that they can ask for
them to be modified if they are unsuitable. Spotting coverage gaps needs an understanding of how
the policy works, what the underwriter will have considered at the underwriting stage and an up to
date technical knowledge of how a project is running.
The case histories below, from risk engineering surveys of real projects, demonstrate the type of issues
that can arise mid-way through a project.
Clarifying coverage:
• Sections of a recently constructed motorway were brought into use, before handover. Were
these covered under the construction policy, or any other policy, whilst other sections were
still under construction?
• Major new equipment items (gas turbines) installed as part of a power project had been
brought into use but not yet received a signed provisional acceptance certificate. Was there
construction policy coverage or any other coverage?
• For a project with multiple buildings and a phased handover, the handed over/operational
areas relied on the operation of equipment located within areas still under construction.
Where were the boundaries between handed over work (insured under an operational
policy) and work still under construction (insured under a construction policy)?
2
• For a project with a phased handover, works were added as a result of variation orders.
Which of two polices applied?
o Either the operational policy (which contained the facility to cover some works)
o or the construction policy (which could, within limits, cover some variations)
• A construction project required some specialist items (for example a tunnel boring machine
and a firefighting barge) Was there any cover for the special items being used during a
project or supplied as part of the project?
• An insurance slip included some apparently inaccurate information (for example statements
about provision of unusual fire protection measures which were not appropriate and had
not been installed). What was the consequence in terms of coverage?
• The contractor for a waterside construction project decided to manoeuvre and lift large
project elements by vessels, barges and a floating crane. Did the construction policy cover
these operations?
• Major project components were stored at a yard outside the project’s boundary. How could
the project be sure the components fell within policy coverage?
• An onshore process plant was being built with construction cover with some automatic
cover for variations to the works. Would the policy extend to cover an offshore pipeline that
was added after construction had commenced?
• After a project had started, asbestos removal works, which were not anticipated at
underwriting stage, had to be undertaken. Could it be assumed that the project policy would
cover these or was additional specialist coverage needed?
If questions like those shown above are not raised, problems may go unnoticed and solutions will not
be found. Difficult situations may then have to be faced after a claim. Far better to tackle these matters
before claims arise, so everyone knows where they stand. Coverage can be extended if necessary,
with additional premium paid. Or a project team can see clearly that they have unprotected risks and
can take appropriate steps to manage them. If coverage issues can be clarified, gaps in coverage
eliminated and future claims problems reduced, then the quality of the insurance which the client
receives will be much enhanced.
Major construction projects are complicated endeavours that take years to complete. It is unrealistic
to believe that insurance coverage arranged before the start will not require some fine tuning during
a project’s life. Risk engineering surveys provide useful opportunities for technical reviews of coverage
to take place, supplementing the routine reviews that brokers undertake. If coverage issues are raised,
it is for the project team, the broker and underwriter, rather than the risk engineer, to arrive at
solutions. Raising such issues does not formally fall within the risk engineer’s brief, but he/she may
well be the person best placed to spot potential problems.