Professional Documents
Culture Documents
Water by Design is a program of the South East Queensland Healthy Waterways Partnership
Construction and Establishment
Guidelines: Swales, Bioretention
Systems and Wetlands
Version 1.1, April 2010
Water by Design
Construction and Establishment Guidelines: Swales,is aBioretention
program of theSystems
South Eastand
Queensland
WetlandsHealthy Waterways Partnership 1
© South East Queensland Healthy Waterways Partnership 2009
This work may be reproduced in whole or part for study or training purposes subject to inclusion
of an acknowledgment of the source and no commercial usage or sale. Reproduction for the
purposes other than those named above requires the permission of the South East Queensland
Healthy Waterways Partnership office. Requests and enquires concerning reproduction rights
should be forwarded to info@waterbydesign.com.au
ISBN 978-0-9806278-0-0
This report should be cited as: Water by Design, 2010, Construction and Establishment
Guidelines: Swales, Bioretention Systems and Wetlands, South East Queensland Healthy
Waterways Partnership, Brisbane.
Disclaimer
The material contained in this publication is produced for general information only. It is not
intended as professional advice on specific applications. It is the responsibility of the user to
determine the suitability and appropriateness of the material contained in this publication to
specific applications. No person should act or fail to act on the basis of any material contained in
this publication without first obtaining specific independent professional advice. The South East
Queensland Healthy Waterways Partnership (SEQHWP) expressly disclaim all and any liability to
any person in respect of anything done by any such person in reliance, whether in whole or in part,
on this publication. The information contained in this publication does not necessarily represent
the views of the funding partners.
Acknowledgements
The Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
were developed by the Water by Design program of the South East Queensland Healthy
Waterways Partnership, with financial assistance from the State of Queensland acting through
the Department of Environment and Resource Management.
Authoring Team: The guidelines were authored by Shaun Leinster (DesignFlow) and Robin Allison
(DesignFlow) with significant input provided by Damian McCann (Australian Wetlands).
A number of government and industry stakeholders provided valuable input to the development
of the guidelines. The principal review of the guidelines was undertaken by Geoff Hunter
(J Wyndam Prince) with reviews also by (in alphabetical order) Jeff Byrne (Gary Dean
Constructions), Peter Curley (Environmental Protection Agency), Alan Hoban (Water by Design
program, SEQHWP), Greg Jenkyns (Shadforths Civil Contractors), Leon Rowlands (Sunshine
Coast Regional Council), Nick Sommes (Ecodynamics), Steve Tracey (Sunshine Coast Regional
Council) and landscape assessment staff at Sunshine Coast Regional Council. Scott Paten
(Brisbane City Council) and Grant Witherridge (Catchments and Creeks) also provided input
to the guidelines.
The photos contained in these guidelines are credited to (as indicated by the number in the
bottom right hand corner of each photo):
1. Shaun Leinster (DesignFlow, EDAW Ecological Engineering)
Sections of these guidelines are drawn from the Water Sensitive Urban Design Technical Design
Sign-off Forms
Each section of this document contains sample sign-off forms. A set of
editable sign-off forms is available from www.waterbydesign.com.au
1 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3 BIORETENTION SYSTEMS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
3.1 Bioretention Systems. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
3.2 Roles and Responsibilities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
3.3 Timing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.4 Civil considerations and specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
3.4.1 Ordering materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
3.4.2 Tolerances. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
3.4.3 Hydraulic structures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .56
Standard Drawings
Available 2009
Asset Management Resources
including Guidelines
Available 2010
2 Swales Vegetated swales are small vegetated depressions in the landscape used to
convey stormwater in lieu of, or in conjunction with, underground pipe drainage
systems. Swales convey stormwater flows along gentle slopes, disconnect
impervious areas from downstream waterways and remove coarse and medium
sediments. They are commonly combined with bioretention systems or trenches
to increase the removal of pollutants.
3 Bioretention Bioretention systems are vegetated soil profiles of sandy loam, sand and gravel
systems layers that capture stormwater on the surface. They treat stormwater as it
percolates through the soil layers. Pollutants are removed by filtration and by the
biological uptake of nutrients.
4 Constructed Constructed wetlands are shallow, vegetated water bodies that remove pollutants
wetlands from stormwater by enhanced sedimentation, fine filtration and biological uptake.
SUB-SECTION DESCRIPTION
Swales, bioretention systems and Describes the function of swales, bioretention systems and constructed wetlands
constructed wetlands within the concept of WSUD.
Roles and responsibilities Describes the roles of stakeholders in the construction, establishment and
certification of vegetated stormwater management systems.
Timing Summarises the issues that influence the timing of construction and
establishment of swales, bioretention systems and constructed wetlands.
Civil works considerations and Outlines issues that must be considered when preparing and completing
specifications landscape works and planting. This section can be referred to for specifications
from landscape drawings rather than generating a specification document.
Landscape considerations and Outlines issues that must be considered when preparing and completing
specifications landscape works and planting. This section can be referred to for specifications
from landscape drawings rather than generating a specification document.
Managing sediment during the building Describes problems associated with sediment during the building phase and how
phase these problems can influence construction and establishment of vegetated
systems.
Staged construction and establishment Summarises the need for staged construction and establishment of vegetated
methods stormwater management.
Stage 1 — Civil works construction Provides a step-by-step construction sequence with detailed descriptions and
photos. This section can be laminated and used as an on-site reference during
construction.
Stage 2 — Building phase protection Provides a step-by-step sequence for protecting systems during the building
phase. A number of options are given for bioretention systems. This section can be
laminated and used as an on-site reference during construction.
Stage 3 — Landscape establishment Provides a step-by-step sequence for establishing landscapes with detailed
descriptions and photos. This section can be laminated and used as an on-site
reference during construction.
Potential failure and rectification Outlines system failures as a result of poor construction and establishment.
Actions to rectify system failures are described.
Regulation and compliance Provides guidance on how local authorities can reference and mandate these
guidelines and details potential compliance processes.
Civil and landscape contractual issues Briefly outlines how best practice construction and establishment requirements
can be written into civil and landscape contracts.
Sign-Off Forms (addendums) Provides Sign-Off Forms to guide construction, establishment, certification and
compliance. The sign-off forms can be used within contracts, to guide day-to-day
construction and establishment, and to inform certification and compliance.
• highlight the issues and risks associated with • Rainfall: When civil works begin, stormwater can
construction and establishment damage the swale through scour or by depositing
sediment. This can result in poor drainage and can
• talk through a preferred approach for construction
reduce the function of the swale. Construction should
and establishment
take place during dry periods or diversion systems
• explain the as-constructed survey or drawings and should be put in place to isolate the swale site.
inspection and sign-off requirements.
Swale designer Design and Swale designers supervise construction and certify the functional elements
construction of the swale after it is constructed.
troubleshooting
Landscape Design and Landscape architects design landscape plans with the swale designer and
architect landscape specify plants in collaboration with an ecologist.
Site Supervise Site superintendents are responsible for all site works to deliver the
superintendent construction construction plans. They coordinate the construction and certification
processes and issue the final overall certification.
Civil contractor Civil works and Civil contractors are responsible for all civil components of the system
installation including bulk earthworks, placement of soil and overflow infrastructure.
They are also required to ensure the swales are protected from sediment
until the landscape contractors start work.
Landscape Landscape Landscape contractors install the landscape elements such as rocks, mulch
contractor installation and and vegetation. They can also be involved in edge details and erosion
establishment protection work, particularly in areas of high amenity.
Council compliance Compliance Compliance officers ensure the swale is built and established according
officer inspections to approved civil and landscape plans for the local council.
SWALES
Overflow pit and Standard pit and grate sizes are readily available. 2–3 days
grate
Non-standard pit and grates need to be custom-made 5+ days
either on-site or off-site.
SWALES
Surface levels Ensuring the surface of a swale meets the design level ± 25 mm Dumpy level or laser
and grades is critical. If the swale is located adjacent for construction
to a road, then the relative levels to kerbs must be
Survey for
achieved.
as-constructed.
2.5.4 Mulching
Mulching retains moisture around plants and provides
organic matter to assist with establishing plants.
Mulching must occur before planting.
2.5.5.3 ESTABLISHING • propagation is occurring with more than 2–3 stems and
Given the critical importance of successfully through seeding
establishing plant cover in a swale as quickly as possible,
a pro-active and adaptive approach should be taken, • no weeds.
responding to any issues relating to the health of the
plants. Responses can include watering or fertilising to
deal with plant stress, weed presence or weather
patterns. Spreading seed can improve the seed bank and
increase plant cover in bare areas.
• placing protective measures around, and along, swales. • Building phase — When the subdivision construction
works are complete or near complete and
Section 2-102.6 describes challenges associated with development plans are sealed, the building phase
the different phases of development sites. Section 2.7 of houses or buildings can start. This phase is
describes staged construction and establishment methods. effectively ‘uncontrolled’ due to the number of
building contractors and sub-contractors. Therefore,
2.6.1 Development phases the building phase represents the greatest risk to
In the context of a large development site, delivering the successful establishment of swales (Figure 2 6).
swales and establishing vegetation can be challenging. Controlling access onto swales for traffic or deliveries
The challenges are best described against each phase in is the main challenge.
the development of a greenfield or infill development
(see Figure 2 5):
Common issues to manage are parking for building Alternatively, the final vegetation can be planted
contractors, the location and bunding for deliveries such immediately after the civil works; however, this option
as soil, sediment from allotments and building traffic. risks damage
Description Construct the civil infrastructure associated with the Construct the civil infrastructure associated
swale including shaping topsoil. Isolate access to the with the swale including shaping of the
swale with appropriate fencing. Protect the swale topsoil. Protect the swale from erosion as
from erosion as soon as civil construction is complete soon as the civil construction is complete.
with turf or sterile grasses. Isolate access to the swale with appropriate
fencing and coordinate with the landscape
When 80–90% of the building in the catchment is
contractor to vegetate with final planting.
complete, remove any sediment build-up from the
swale and replace the temporary grasses with the final
vegetation.
Order of Follow the steps in Section 2.8 Follow the steps in Section 2.8
construction
Provides some sediment control during the Simple and early handover of asset.
building phase.
Vegetation established after completion of building The swale surface may require reworking.
phase.
Preferred
construction and
establishment
method
Streetscape
Parkland in high
profile location
Parkland in low
profile location
2.7.1 Option 1: Surface protection with - Cover the surface of the swale with temporary
temporary vegetation vegetation such as turf or hydroseed. This
vegetation will protect the integrity of the swale’s
To minimise the risk of damage and the cost of any
surface and provide for some sedimentation of
re-establishment, the functional elements of a swale can
flows over the swale.
be undertaken and temporary protective measures
installed to prevent damage to the surface and • Stage 3 Landscape Establishment: When the building
vegetation. This involves: phase is 80–90% complete, replace the temporary
vegetation with final plantings. Local erosion or
• Stage 1 Civil Works: Undertake civil construction
sediment build-up may mean that the swale’s surface
including shaping of the swale surface.
will need to be reshaped.
• Stage 2 Building Phase Protection:
As illustrated in Figure 2 -7, this approach means the
- Install sediment fences around the perimeter of the swale will be in the Building Phase Protection mode for
swale to prevent access to the surface and to up to 24 months, followed by a 12-month period of
prevent sediment from being carried into the landscape establishment.
system by overland flow.
STEP 1: Pre-start meeting A pre-start meeting with the swale designer, civil engineer, landscape architect, site
superintendent, civil contractor, landscape contractor and, where required, the
Council compliance officer to:
- talk through a preferred construction and establishment approach for this site
STEP 2: Preparation Preparation for construction should occur before starting on site. Preparation
includes organising the correct equipment to achieve tolerances, sourcing materials
and assessing the risk of rainfall during construction
(refer Section 2.4).
STEP 3: Install overflow pit and outlet pipe Install the overflow pit and ensure the crest of the pit is at the design level.
The crest of the pit can then be used as a datum from which other levels within the
Construct outflow headwalls and install sections of the stormwater outlet pipe. If
the outlet pipe is below the receiving environment levels, consult the superintendent
and designers to resolve a change in the design.
27
28
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 4: Bulking out Undertake bulk earthworks. Swales will have at least 150 mm of topsoil applied after
earthworks (refer Section 2.5.1) and a further 100 mm set down from adjacent roads.
Design levels for the top of the bund are INCLUSIVE of this layer of topsoil and 100
mm of set down. Bulk earthworks should leave the top of the swale 250 mm below
the final surface level depending on topsoil requirements (Section 2.5.1).
STEP 5: Trimming and profiling Undertake detailed excavation, trimming and profiling of bunds, batters, sides and
base of swale, ensuring swale is free-draining and is free of debris. Ensure an
appropriate set down from the flush kerb so that the final topsoil is 100 mm below
the kerb’s edge.
If check dams are included in the design they should be installed at this step.
STEP 6: As-constructed survey Undertake an as-constructed survey of the swale at this stage, including:
- the overflow pit crest level, invert level and under-drainage connections invert and
diameter
Use the base of swale to illustrate that the level allows for topsoil and 100 mm set
down.
STEP 7: HOLD POINT Inspection and sign-off Following collection of the as-constructed survey, the site superintendent and swale
(Form A) designer will inspect the swale with the contractor, review the as-constructed survey
STEP 8: Install topsoil Ensure the topsoil meets the AS 4419 — Soils for landscaping and garden use. Refer
Section 2.5.1.
STEP 9: As-constructed survey Undertake an as-constructed survey of the swale surface at four spots on the
surface for every 50 m of swale.
STEP 10: HOLD POINT Inspection and sign-off Following collection of the as-constructed survey, the site superintendent and swale
(Form B) designer will inspect the swale with the contractor, review the as-constructed survey
and take photos. If the construction meets the tolerances outlined in Section 2.4.2
and conforms with the design, Sign-Off Form B will be completed and signed and the
as-constructed survey and photos attached.
If landscape works are to commence immediately, without the need for building phase protection, skip
directly to Step 14.
2.8.2.1 OPTION 1
Table 2.6: Building phase protection step-by-step sequence — Option 1 Surface protection with temporary vegetation
STEP 11: Install sediment fences Immediately after installation of the topsoil, install sediment fences around
the swale to prevent sediment entering from the batters and to keep
construction vehicles off the swale.
STEP 12: Install temporary erosion works Install any temporary vegetation being used to protect the swale during the
building phase. Install turf perpendicular to the flow path. Hydroseed
STEP 13: HOLD POINT Inspection and sign-off (Form C) If the building phase protection has been installed, Sign-Off Form C will be
PRACTICAL COMPLETION completed, signed and photos attached.
2.8.2.2 OPTION 2
Table 2.7: Building phase protection step-by-step sequence — Option 2 Surface protection with permanent vegetation
STEP 11: Install sediment fences Immediately after installation of the topsoil, install sediment fences around
the swale to prevent sediment entering from the batters and to keep
construction vehicles off the swale.
SSTEP 12: Install temporary erosion works Install design vegetation according to Stage 3, Steps 14 to 25.
STEP 13: HOLD POINT Inspection and sign-off (Form C) When the building phase protection is installed, Sign-Off Form C will be
PRACTICAL COMPLETION completed, signed and photos attached.
STEP 14: Pre-start and plant set-out meeting Before starting landscape preparation, hold a pre-start and plant set-out meeting
with the swale designers, site superintendent and landscape contractors. The
meeting should confirm design and planting requirements and set out the planting
to ensure the correct plants are installed in the correct locations.
STEP 15: Preparation Prepare for the landscape up to six months before starting, including ordering and
inspecting plants at the nursery, ordering and receiving organic mulch and matting
and organising a source of irrigation water (refer Section 2.5).
STEP 16: Removal of building phase protection Remove the building phase protective measures and any accumulated sediment. If
the final landscape is to be turf and the turf protection is in good health, very little
STEP 17: Re-establish swale profile Once the protective layers are removed, re-profile the surface of the soil to the
design requirements using a spreader bar. Fill in any over-excavated zones.
CONSTRUCT ION STEP ACTIV IT Y PHOTOS (swales)
STEP 18: Mulching Mulching should occur in accordance with the guidance provided in Section 2.5.4.
Create holes through the mulch for planting. Ensure the holes have 50 mm
separation from stem of the plant to the mulch.
STEP 19: Soil preparation Dig planting holes by hand and, where necessary, place the prescribed amount of
slow-release native fertiliser in the hole. Place pre-soaked wetting agents in the
hole if necessary.
STEP 20: Planting Plants should be supplied in accordance with requirements listed in Sections 2.5.2
and 2.5.3.
Plant the tubestock ensuring the root ball is covered with soil and stems are above
the soil surface. Clear away any mulch from the stem to 50 mm.
STEP 21: Inspection and sign-off (Form D) After installing the mulch and plants, the site superintendent and swale designer will
PRACTICAL COMPLETION inspect the swale with the contractor and Sign-Off Form D is completed, signed and
photos attached.
If there is no rain, each plant should receive 2.5–5.0 litres per week during
establishment in the first six weeks (40 mm per week).
STEP 23: Weeding Inspect swale plants fortnightly during establishment, removing weeds by hand.
STEP 24: On-going inspection and final landscape Monitor the establishment of plants until they are robust and self-sustaining.
establishment
An established swale is measured by:
STEP 25: Inspection and sign-off (Form E) After plants in the swale are established (typically 12 months, less for turf), the site
superintendent and swale designer will inspect the swale and complete
Sign-Off Form E with attached photos.
2.9 Potential failure and rectification
Constructing and establishing any civil or landscape
asset requires refinement and repair of defects to
ensure compliance with the design. Table 2.9 outlines
potential construction and establishment failures or
defects that can occur and suggests actions to rectify
the problems. The table focuses on construction and
establishment defects and on functional failures that
can occur after construction. Consult the swale designer
or an external expert to confirm rectification actions if
the following failures occur.
Table 2.9: Potential failure scenarios for swales and rectification actions
Damage to invert Vehicle traffic is the most common cause, creating Re-establish perimeter protection fence.
of the swale from preferential flow paths and facilitating erosion.
Re-grade swale batters and invert replacing
traffic
topsoil where required.
Scour of swale High velocities within swales, particularly at Stabilise upslope extent of erosion.
invert stormwater outfalls.
Backfill, stabilise and re-vegetate scour.
Accumulation of Building in the catchment or adjacent to the swale. Remove sediment and re-vegetate. Reinstate
sediment protective fences and investigate and
resolve source of sediment.
Scour of swale Lateral concentrated surface flows entering the swale Redirect lateral flows to small, rock-lined
batters from catchments adjacent to the swale. channels that flow down batters to the swale
invert. Rectify and plant out scoured zones.
Failure of plants Topsoil does not meet specifications. Review Sign-Off Form B to confirm the soil meets the
specifications outlined in Section 2.5.
Inappropriate watering during If the plants are alive, irrigate according to the
establishment of plants. recommendations in Section 2.5.
Lack of mulch or fertiliser during If the plants are alive, apply a small quantity of liquid
establishment of plants. fertiliser and mulch. If plants have died, mix compost or
organics into the top 50–100 mm of the soil, mulch and
replant.
Poor plant cover of less than five plants Review species selection in consultation with the swale
per m2. designer and select an alternative species better suited to
the site and replant.
Excessive weed cover. Remove weeds manually to protect native plants. Avoid
weed seed set by pro-actively maintaining and reducing
weed infiltration from the edges of the swale.
Civil certification Site (civil) superintendent Swale designer’s certification of functional elements
Landscape Site (landscape) superintendent Swale designer’s or ecologist’s certification of plant species
certification
As-constructed drawings showing final species and plant
numbers
2.11 Compliance
Compliance of swale construction and establishment
is a major challenge for local authorities.
System location:
Developer
Site superintendent
(landscape)
Bioretention designer
Civil engineer
Landscape architect
Civil contractor
Landscape contractor
NAME OF
SIGN-OFF FORM DATE COMPLETED SIGNATORY & ROLE SIGNATURE
(E . G . SUPERINTENDENT)
Pre-Start Meeting
Form C — Protective
Measures
Form D — Landscape
Installation
Form E — Landscape
Establishment
Location
Date
Developer
Site
superintendent(landscape)
Swale designer
Civil engineer
Landscape architect
Civil contractor
Landscape contractor
Other
Other
Other
Purpose: To ensure earthworks bulking out, trimming and profiling together with the key levels of functional (hydraulic)
structures are in accordance with design drawings and specifications. The earthworks and structures dictate the movement of
stormwater through the swale and are a critical element in its function.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent AND swale designer inspection and sign-off before proceeding.
Date: Date:
Purpose: To ensure finished levels of swale surface and batters are correct and meet the design.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent AND swale designer inspection and sign-off before proceeding.
Date: Date:
HOLD POINT: Superintendent AND swale designer inspection and sign-off before proceeding.
Date: Date:
Purpose: To ensure the correct plants are supplied, installed and established.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent AND swale designer inspection and sign-off before proceeding.
Date: Date:
Purpose: To ensure the correct plants are supplied, installed and established.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
PLANT ESTABLISHMENT
3. At least 5 plants/m2
(preferably 6–10 plants/m2).
5. Propagation is occurring
(more than 2–3 stems, seeding).
6. No weeds.
Date: Date:
Vegetation
Bioretention systems can be installed at various scales, • using coarse gravel (10–20 mm) mixed with a source of
for example, as planter boxes, in streetscapes carbon (straw and hardwood chips) in the base of the
integrated with traffic calming measures, in suburban saturated zone to support the removal of nitrogen
parks, and in regional retarding basins.
• ensuring the base of the system is flat.
Figure 3.2: Typical cross-section through a bioretention system with a saturated zone
Vegetation
Bund/Embankment
Overflow grate
Table 3.1: Roles and responsibilities for bioretention system construction and establishment
Bioretention Design and The bioretention designer designs the bioretention system. They should support
designer construction the superintendent by supervising construction works and providing certification
troubleshooting of the functional elements of the constructed system. This certification forms the
basis of the superintendent’s overall certification.
Landscape Design and The landscape architect develops landscape plans in association with the
architect landscape bioretention designer, providing plant specifications in collaboration with an
troubleshooting ecologist.
Civil engineer Design of civil The civil engineer designs the civil works related to the bioretention system such
components as edge details, overflow pits, pipe work and structural elements.
Site Supervision of The site superintendent is responsible for all site works associated with delivering
superintendent construction the construction plans. The site superintendent coordinates the construction and
certification processes and issues the overall final certification of the
bioretention systems.
Civil contractor Civil works and The civil contractor is responsible for all civil components of the system — bulk
installation earthworks, placement of overflow infrastructure, under-drainage and placement
of filter media. In some situations, the civil contractor may leave the installation
of bioretention filter media to the landscape contractor. The civil contractor is
also required to ensure the bioretention systems are protected from sediment
until the landscape contractors start work.
Supplier of Supply of The supplier of the bioretention media is responsible for testing, supplying and
bioretention bioretention certifying the bioretention media for each layer of the system. The supplier will
media media co-ordinate with the civil or landscape contractor and site superintendent to
ensure appropriate media is delivered and installed.
Landscape Landscape The landscape contractor installs mulch, plants vegetation and may undertake
contractor installation and some edge details and inlet erosion protection work in areas of high amenity. In
establishment some cases the landscape contractor may also install the bioretention media and
protective measures.
Local government Compliance The compliance officer represents the interests of the local authority to ensure
compliance officer inspections the system is built and established according to approved civil works and
landscape plans.
Overflow pit and Standard pit and grate sizes are readily available. 2–3 days
grate
Non-standard pit and grates must be custom-made either 5+ days
on-site or off-site. Custom grates are made off- site.
Liner Filter cloth in most cases with pegs or pins to secure. 1–2 days
Under-drains Slotted rigid pipes (i.e. PVC) or ag-pipe and end caps for 2 days
clean out (refer to Section 3.4.5 for details).
Drainage layer 2–4 mm clean or washed aggregate (refer to Section 3.5.3 2–5 days to confirm correct material
for details). with superintendent and engineers.
2 days to supply.
Transition layer Coarse sand (refer to Section 3.5.2 for details) Plan for selection and supply of this
material at least 10 days* before
construction:
- 2 days to supply.
Filter media Bioretention filter media material (refer to Section 3.5.1 for Plan for selection and supply of this
details). material at least 10 days* before
construction:
- 2 days to supply.
Filter cloth liner, Filter cloth liner, topsoil and turf to protect the surface of 2 days
topsoil and turf the bioretention system during building phase and to
protect batters until landscape works are complete.
* If coarse sand or filter media does not comply with the specifications,
alternative materials will need to be sourced, which will delay the supply
of material by more than 10 days.
- weirs.
Under-drains To freely drain the base of bioretention systems, the under- + 25 mm Dumpy level or
drains must be sloped towards the outlet pit at a grade of laser
0.5% in most cases. Installation of the under-drains should
meet the recommended tolerance to ensure this grade is
achieved.
Drainage and The depth of the drainage layer should ensure at least 50 + 25 mm Dumpy level
transition layers mm of aggregate cover over the under-drainage. The depth or laser
of the transition layer should ensure that 100 mm of coarse
sand covers the aggregate.
Surface level The surface of the bioretention filter media must be free + 25 mm Dumpy level or
(filter media from localised depressions to ensure even distribution of laser for
+ 40 mm for
surface) stormwater flows across the surface and to prevent construction
systems greater
localised ponding. Compaction should be light and even
than 300 m2 Survey for as-
across the surface.
provided the constructed*
Achieving a flat surface on large bioretention systems can ‘average’ extended
be challenging so a separate tolerance is provided. detention depth is
within 25 mm of the
design requirement
Embankments and Embankments or bunds around bioretention systems hold - 25 mm Survey for as-
bunds stormwater within the extended detention during rainfall. If constructed*
+50 mm
required, they force runoff from larger rainfall into the
hydraulic structures. Therefore, the crest level on the It is preferable for
embankments or bunds is important. the bund to be
higher than lower.
Under-drains
+/- 25mm by dumpy
level or laser
Outlet overflow The outlet overflow pit collects flows above the Overflow pit requirements:
pit filtration rate of the filter media up to the ‘design’ - concrete construction
event, typically a minor storm. The outlet overflow
- letter box or dome grate (not flush grate)
pit transfers flows to an outlet pipe that is
- crest level typically 100–300 mm above the
connected to the receiving systems.
surface of the filter media and 300 mm+ below
the high flow bypass weir level or surcharge point
- under-drainage pipes must be sealed into the
overflow pit.
Outlet pipes Outlet pipes transfer flows from the overflow pit to If the outlet pipe contains water or is
the receiving systems and are sized to convey the ‘backwatered’ during construction, consult with
amount of water from the design event. Outlet the bioretention system designers.
pipes must be free draining and include a seepage
Rock protection may be required at the outfall of
collar.
the pipe. Seepage collars around pipes required.
High-flow weir Where required, the high-flow weir conveys water High-flow weirs need to operate under high-flow
from ‘above design’ events, which in some instances conditions requiring:
can be major storms. - a mass concrete weir crest, typically 500 mm
deep with reinforcing
- grouted rock protection on both sides of the
crest to at least the base of the batters
- concrete and rock protection extending up the
batters and into bunds or batters at the ends of
the weir to avoid scouring.
Drainage layer 2–4 mm clean or washed aggregate (refer to 2–5 days to confirm correct material with
Section 3.5.3 for details). superintendent and engineers.
2 days to supply.
Transition layer Coarse sand (refer to Section 3.5.2 for details) Plan for selection and supply of this material at
least 10 days* before construction:
When installing under-drainage, there are a number • The maximum length of 100 mm slotted PVC is 25 m
of specifications to consider: before the flow conveyance of the pipe is reached.
For longer lengths the pipe size must be increased
• Typically, 100 mm-slotted PVC is the preferred type or duplicated to increase conveyance.
of rigid pipe.
• For effective drainage, perforated pipes should
• The slots in the pipes should not allow the drainage grade at a minimum of 0.5% towards the overflow
layer aggregate to freely enter the pipes. For example, pit. This is best achieved by grading the base of the
if a 2–4 mm aggregate is used for the drainage layer, bioretention system towards the pit, placing the
Rigidity The grade of rigid pipes is not affected by local Flexible ag-pipe tends to follow the final profile
depressions in the base of the bioretention system. of the bioretention base, which includes local
This makes it easy to achieve a 0.5% grade towards depressions, making it difficult to create a
the overflow pit. constant grade to the overflow pit. There is also
a risk of local ponding within the ag-pipe.
Ease of connection Standard plumbing for rigid pipes makes it easy to Connecting ag-pipe can be difficult and may
and sealing create connections and sealing for the under- require a substantial amount of sealant.-
drainage. under-drainage pipes must be sealed into the
overflow pit.
Smooth profile The smooth profile (internal surface) of rigid pipes The ribbed profile of ag-pipe is more likely to
is free draining and does not hold water for a retain beads of moisture inside the pipe,
significant period after rain. This minimises the increasing the potential for tree roots to enter
potential for tree roots to enter the pipes in search the pipes in search of water.
of water.
Conveyance The smooth profile of the rigid pipe is less The ribbed profile of ag-pipe creates quite a high
resistant to flow. At a 0.5% grade, a slotted rigid resistance to flow. At a 0.5% grade, an ag-pipe
pipe can convey up to 3L/s, approximately double can convey up to 1.5L/s.
the capacity of ag-pipe.
4. The relevant sections of the Bioretention Media • a planting density of 6–10 plants/m2
Sign-Off Form should be completed and signed. • a minimum of three species per bioretention system.
This Sign-Off Form is provided as part of the
If the design does not allow for these specifications,
construction certification by the site superintendent
consult the designers.
or bioretention designer.
3.6.1 Planting • checking the roots of plants for fresh white roots
Work is ongoing to determine species that are most • ensuring that plants have a ‘hardening off’ phase
suited to stormwater management contexts. Species before delivery and that they are not taken directly
need to be reliable through both wet and dry periods, from a shade house to the construction site.
while also providing good root structure and landscape
3.6.2.1 TIMING
amenity. These characteristics should be considered as
Plant availability varies considerably in different regions
part of the design. These guidelines do not specifically
and at different times of year. Sufficient time must be
detail species selection. The WSUD Technical Design
allowed to order plants. Up to six months lead time may
Guidelines for SEQ (SEQHWP, 2006) and the local
be required to ensure appropriate species are available.
authority should be consulted for more detail.
If provenance plant stock is required, up to 18 months
may be required to collect seeds and propagate plants.
• viro tubes: 50x90mm with a minimum plant height • Inorganic mulch that does not float, such as gravel
of 300 mm or stone, can also be used. Care must be taken with
inorganic mulch to ensure that it does not inhabit plant
• 50 mm tubes: 50 x 75–90 mm with a minimum plant
growth. For example during summer, gravel and stones
height of 300 mm
can heat up to the point where they kill tubestock.
1 This can be measured by marker stakes in the bioretention basin at a rate of one stake for every 500m2of bioretention basin.
- construction traffic and other works damaging the Table 3.6 summarises the issues and considerations
bioretention systems associated with each of the methods to allow local
authorities, developers, designers and contractors
- all works undertaken during the subdivision
to select the method most suited to their site.
construction are ‘controlled’ through the principal
The following sections discuss each method in
contractor and site manager, meaning that risks can
more detail.
be managed through guidance and supervision.
• Building phase — When the subdivision construction
works are complete and development plans are sealed,
the building phase can commence (i.e. construction of
houses or buildings). This phase is effectively
‘uncontrolled’ due to the number of building
contractors and sub-contractors. Therefore, the
building phase represents the greatest risk to the
successful establishment of bioretention systems.
Figure 3.8: Typical phases in the creation of a development site (amended from Leinster, 2006)
OPTI ON 1 : SU RFACE P ROTECTI ON OPTION 2: BYPASS AND EARLY OPTION 3: SEDIMENT BASIN AND O P TIO N 4 : LE AVE AS SE DIM E N T
ESTABLISHMENT BIORETENTION FUNCTION B ASIN
Description Construct the civil infrastructure, Construct the civil infrastructure for The approach combines Option 1 Install the hydraulic structures and
including under-drainage and media, the bioretention system. Bypass (surface protection) with a sediment bulk out the system. Allow it to
for the bioretention system. Install stormwater around the bioretention basin upstream of the bioretention operate as a sediment basin (Type C,
protective layers on the surface of system or isolate it from system. Outflow from the sediment D or F) during the building phase.
the filter media, allowing it to stormwater using a temporary bund. basin is discharged to the Refer to a suitable erosion and
operate as a shallow sediment basin This allows the surface of the bioretention system for further sediment control guide, for example
during the building phase. Surface bioretention system to be planted treatment before discharging to the theBest Practice Erosion and
protection options are: out and established immediately. receiving environment. Sediment Control (IECA, 2008) for
Vegetation is fully established by design requirements of sediment
- filter cloth, topsoil and turf The sediment basin should be
the end of the building phase. basin.
designed to capture either coarse
- coarse sand, topsoil and turf
When 80–90% of building in the sediment only (125um) or as a Type C, When building in the catchment is
When 80–90% of building in the
catchment is complete, the bypass D or F sediment basin. Refer to a 80–90% complete, the bioretention
catchment is complete, remove the
systems can be removed and the suitable erosion and sediment system can be cleaned and profiled,
protective layers and establish
bioretention system allowed to control guide, for example the Best the under-drainage and bioretention
vegetation in the bioretention
function. Practice Erosion and Sediment media installed, and the vegetation
system.
Control (IECA, 2008) for design planted and established.
requirements of sediment basin.
Order of construction PFollow the procedures in Section Follow the procedures in Section 3.9 Follow the procedures in Section 3.9 Follow the procedures in Section
3.9 from Step 1 to Step 40. from Step 1 to Step 40. from Step 1 to Step 40. 3.10.
Advantages Protects filter media. Protects filter media. Protects filter media. Bioretention system not
constructed until after building,
Very little maintenance during Early establishment of vegetation. High level of protection to receiving
therefore no sediment issues.
building phase. environment.
High amenity.
High level of protection to receiving
Moderate amenity. Amenity should be moderate to high,
Simple and early handover of asset. environment.
provided construction and
establishment is successful.
Disadvantages Moderate protection to receiving Low protection to the receiving Additional space is required for the Poor landscape amenity.
environment (only manages coarse environment during the building sediment basin.
Delay of construction results in a
sediment down to 125um). phase. If Option 2 is adopted, it
A high level of management of long period before asset handover.
should be combined with strict
Vegetation established after sediment basin required, particularly
erosion and sediment control on the A high level of management of
completion of building phase. if it is a Type F sediment basin.
building sites or sediment basins at sediment basin required, particularly
Delayed handover of asset. the discharge point of the drainage if it is a Type F sediment basin.
system (i.e. downstream of the
bioretention systems).
* Timing dictated by the Building Phase period. (this timing assumes 18-24 moth Building Phase)
69
3.8.1 Option 1: Surface protection • Stage 3 Landscape Establishment — When the
To minimise the risk of damage and the cost of any building phase is 80–90% complete, the temporary
re-establishment, the civil works for bioretention measures protecting the bioretention systems and the
systems can be undertaken and temporary protective accumulated sediment can be removed. The
measures installed to prevent clogging of the filter bioretention system can be planted and established
media during the building phase (see Figure 3.9). according to Section 3.9.3.
Option 1 involves:
As illustrated in Figure 3.10, for Option 1, the system
• Stage 1 Civil Works — Civil construction and
will be in the Building Phase Protection mode for up to
installation of the functional elements of the
24 months, followed by a 12-month period of landscape
bioretention system should be undertaken in
establishment.Advantages of Option 1 are:
accordance with Section 3.9.1.
• the bioretention system is comprehensively protected
• Stage 2 Building Phase Protection
during the building phase
- Sediment fences should be installed around the
• very little maintenance or irrigation is required during
perimeter of the filter media and the top of the
building phase.
batter to prevent sediment from being carried into
the system by overland flow. The fences clearly show Disadvantages of Option 1 include:
that construction traffic should not enter the • the landscape is not established until after the
system. building is complete and plants will not be fully
- Covering the surface of the filtration media with a established until 6–12 months after the building phase
temporary filter cloth or coarse sand (25 mm) and • the filter cloth used to protect the surface of the filter
laying 25 mm of topsoil and turf over it will protect media has blocked in some situations, therefore, the
the bioretention system during the construction and use of coarse sand is also supported.
building phases.
- During the building phase, the extended detention
acts as a shallow sediment basin.
Figure 3.9: Illustration of Option 1: Protect the bioretention system during the building phase
Figure 3.11: Illustration of Option 2: Protection of the bioretention system during the building phase
Figure 3.12: Stages of construction associated with Option 2: Protect and establish
vegetation during building phase (amended from Leinster, 2006)
STEP 1: Pre-start meeting Hold a pre-start meeting with the bioretention designer, civil
engineer, landscape architect, site superintendent, civil
contractor, landscape contractor and, where required, the Council
compliance officer to:
STEP 2: Preparation Prepare for construction at least 10 days before starting on site.
Preparation includes organising the correct equipment to achieve
required tolerances (Section 3.4.2), sourcing the bioretention
media, ensuring the supplier of the filter media is completing the
correct testing (Section 3.5), ordering materials and identifying
construction timing and rain contingency plans (Section 3.3).
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 3: Install overflow pit and Install the overflow pit and ensure the crest of the pit is at design
outlet pipe level. The crest of the pit can be used as a datum from which other
levels within the system are measured. The pit requires holes for
under-drainage pipe connections. These holes should be drilled at
this stage or plastic stubs should be installed at the time of
casting the pit.
STEP 5: Trimming and profiling Undertake detailed excavation, trimming and profiling of bunds,
embankments, batters, sides and base of system, ensuring the
base has a minimum 0.5% grade towards pit, unless the design
specifies a flat base and design levels achieve (+ 50 mm).
If the design has a flat base and does not contain the 0.5% grade,
confirm with the designer and refer to these guidelines or the
WSUD Technical Design Guidelines for SEQ (SEQHWP, 2006).
STEP 6: Construct overflow weir Where an overflow weir is part of the system design, it should be
if required constructed at this stage and appropriately ‘keyed’ into the bunds
to avoid potential scour at the edges of the weir. Design levels and
tolerances must be achieved (+25 mm).
STEP 7: As-constructed survey Undertake an as-constructed survey of the system at this stage
to confirm design and tolerances (Section 3.4.2) are achieved,
including:
STEP 8: HOLD POINT Following collection of the as-constructed survey, the site
Inspection and sign-off (Form A) superintendent and bioretention designer will inspect the system
with the contractor, review the as-constructed survey and take
photos. If the construction meets the tolerances outlined Section
3.4.2 and conforms with the design, complete Sign-Off Form A
attaching the as-constructed survey and photos.
STEP 9: Filter cloth Lining Line system with filter cloth, ensuring the filter cloth extends a
minimum of 500 mm beyond the top of the bioretention system
side walls.
STEP 10: Install under-drainage Install slotted rigid under-drainage pipes and ag-pipes and rigid
collector pipes in the specified layout outlined in Section 3.3.6.
Ensure all pipes are laid at a minimum 0.5% slope with no localised
depressions verified using levels or string lines. Ensure levels are
achieved (+25 mm). Seal junctions and connections using sufficient
sealant to prevent sand, gravel or soil passing into drainage
network.
STEP 11: Install cleanouts Connect clean-out points ensuring top of clean-out points will
ultimately sit at least 50 mm (preferably 150 mm) above the
bioretention surface. The caps on the clean-out points should be
screwed in place to secure against vandalism.
STEP 12: HOLD POINT Following installation of the liner and under-drainage, either the
Inspection and sign-off (Form B) site superintendent or bioretention designer will inspect the
system with the contractor and take photos. If the lining and
under-drainage meets the design and construction requirements,
they will complete Sign-Off Form B and attach photos.
STEP 13: Source drainage layer, Testing and sourcing the drainage, transition and filter media
transition layer and filter media layers should have commenced as part of Step 2. By Step13, the
material material can be delivered and stockpiled on site ready for
installation.
STEP 14: Install drainage layer Install 200–250 mm deep gravel drainage layer to cover the
slotted under-drainage pipe network. The preferred approach is
to use an excavator (long-arm if required) or conveyor belt (see
Section 3.4.7) positioned on the edge of the system to place
gravel into the system. Contractors can then spread and flatten
the gravel to the specified depth using spreader bars. The exact
procedure for constructing the drainage layer is determined
through consultation with the contractor. It may differ from the
procedure described in Section 3.4.7.
STEP 15: HOLD POINT The site superintendent or bioretention designer should inspect
Inspection of drainage layer the drainage layer to ensure the correct depths (200–250 mm)
and grades (typically 0.5%) have been achieved and the surface is
flat. The relevant sections of Sign-Off Form C must be completed
and photos taken. There is no need to stop construction for this
inspection unless specifically required. The site superintendent or
designer should undertake the inspection as construction occurs.
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 16: Install transition layer Install a 100 mm deep coarse sand transition layer on top of the
gravel drainage layer using the same approach outlined in Step 14
to achieve the correct tolerances (+25 mm) and to ensure the
surface is flat.
STEP 17: Inspection of The site superintendent or bioretention designer should inspect
transition layer the transition layer to ensure the correct depths (100 mm) and
grade (typically 0.5%) have been achieved and that the surface is
flat. The relevant sections of Sign-Off Form C should be
completed and photos taken. The site superintendent or designer
can undertake the inspection as construction occurs.
STEP 18: Install filter media Place the bioretention filter media to the designed the surface
level of the bioretention system in two separate lifts, where
required, with each lift lightly compacted as outlined in Section
3.4.6. At the completion of the section lift and compaction, use a
spreader bar to flatten the surface of the filter media. Ultimately,
the surface of the filter media must be at the design level (+25
mm) and free from local depressions.
STEP 19: Install sediment fences Immediately after installing the filter media, install sediment
fences around the filter media and at the top of the batter to
prevent sediment from entering the batters and to keep
construction vehicles off the system.
STEP 20: Lay protective filter If there is a delay between Step 18 and Steps 25 and 29, the
79
80
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 21: As constructed survey Undertake an as-constructed survey of the system surface and
surrounding bunds, picking at least four spots on the surface of
the small bioretention systems (<100 m²), one spot level per 100
m² on the surface of large bioretention systems and at least one
spot level every 10 m along the top of the bunds as well as any
low points.
STEP 22: HOLD POINT Following collection of the as-constructed survey, the site
Inspection and sign-off superintendent and bioretention designer will inspect the system,
(Forms C and D) review the as-constructed survey and take photos. If the
construction meets the tolerances outlined in Section 3.4.2 and
conforms to the design, Sign-Off Forms C and D will be completed
and signed and the as-constructed survey and photos attached.
STEP 23: Install coarse sediment Construct the coarse sediment forebay in accordance with the
forebay design and advice provided in Section 3.4.9. Concrete is preferred
with surface treatment as directed by the design.
STEP 24: Inspection and sign-off The site superintendent or bioretention designer should inspect
(Form E) the coarse sediment forebay to ensure consistency with design.
PRACTICAL COMPLETION The relevant sections of Sign-Off Form E should be completed
and photos are taken before either Building Phase Protection
CONTINUE TO STEP 25 (Building Phase Protection) if there is building or works in the catchment
that will cause damage to the bioretention system or the accumulation of sediment in the system.
Table 3.8: Building phase protection (Stage 2) step-by-step sequence — Options 1 and 3
STEP 25: Install sediment fences If not installed as part of Step 19, sediment fences should be
installed around the filter media and at the top of the batter to
prevent sediment entering from the batters and to keep
construction vehicles off the system.
STEP 26: Install protective layers Cover the surface of filter media with filter cloth or 25–50 mm of
on surface of filter media (filter coarse sand and place 25 mm topsoil and turf over the filter cloth
cloth and turf) or coarse sand.
STEP 27: HOLD POINT Inspection Following installation of protective layers, the site
and sign-off (Form F) superintendent and bioretention designer will inspect the system
with the contractor. If approved, Sign-Off Form F can be
completed and signed and photos attached.
STEP 28: Building phase During the building phase, which may be as long as 2–4 years, the
operation bioretention system will operate as a shallow sediment basin, and
protect the filter media from sediment and clogging.
81
82
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 25: Install sediment fences If not already installed as part of STEP 19, sediment fences should
be installed around the filter media and at the top of the batter to
prevent sediment entering from the batters and to keep
construction vehicles off the system.
STEP 26A: Install bypass system The majority of the bioretention system should be isolated from
(temporary protective bunds) sediment-laden inflows. This can be achieved by:
- the crest of the bund should be higher than both the overflow
pit and the surrounding embankments to ensure no sediment-
laden flow enters the bioretention system and the bund should
be keyed into the batters to avoid scouring around the edges
causing water to enter the system.
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 26B: Install protective Install temporary protective covering over the bioretention
layers on surface of filter media surface located within bunded area adjacent to the coarse
(filter cloth and turf) sediment forebay. Cover the surface of filtration media with filter
cloth (or coarse sand) and place 25 mm topsoil and turf over the
filter cloth.
STEP 27: HOLD POINT Inspection Following collection of the as-constructed survey, the site
and sign-off (Form F) superintendent and bioretention designer will inspect the system,
review the as-constructed survey and take photos. If the
construction meets the tolerances outlined in Section 3.4.2 and
conforms to the design, Sign-Off Forms C and D will be completed
and signed and the as-constructed survey and photos attached.
STEP 28: Building phase During the building phase, which may be up to 2–4 years,
operation landscape can be established on the majority of the bioretention
system surfaces in accordance with Stage 3: Landscape Works
(Step 29 onwards).
STEP 29: Pre-start and plant set- Before starting landscape preparation, hold a pre-start and plant
out meeting set-out meeting with the bioretention designers, including an
ecologist, site superintendent and landscape contractors. The
meeting should confirm design and planting establishment and
set out the planting to ensure the correct plants are installed in
the correct locations.
STEP 30: Preparation Prepare for the landscape establishment up to six months before
starting, including ordering and inspecting plants at the nursery,
ordering and receiving organic mulch and matting and organising a
source of irrigation water.
STEP 31: Remove building phase Remove the building phase protective measures such as bunds,
protection and flushing of under- filter cloth, coarse sand, turf and accumulated sediment. Care
STEP 32: Flatten surface After the protective layers are removed, flatten the surface of the
filter media using a spreader bar. Additional filter media may be
required to fill in any over-excavated zones. Care should be taken
to not over-compact the filter media (refer Sections 3.4.6 and
3.4.7).
STEP 33: Mulching Mulch the filter media surface in accordance with Section 3.6.4.
Create holes in the mulch for planting. Ensure the holes have 50
mm separation from stem of the plant to the mulch.
STEP 34: Soil preparation Dig planting holes by hand and apply the prescribed amount of
slow-release native fertiliser detailed in Section 3.6.3. Pre-soaked
wetting agents are recommended in this step.
STEP 35: Planting Plant tubestock ensuring the root ball is covered with filter media
and the stem is sitting above the filter media. Clear away any
mulch from the step to 50 mm (refer Section 3.6.5).
STEP 36: Inspection and sign-off After installing the mulch and plants, the site superintendent and
(Form G) bioretention designer will inspect the system and Sign-Off Form
PRACTICAL COMPLETION G is completed and photos attached.
STEP 39: On-going inspections Monitor the establishment of plants until they are robust and
and final landscape self-sustaining.
establishment
An established bioretention is measured by (Section 3.6.7):
7. no weeds.
STEP 40: Inspection and sign-off After plants are established, the site superintendent and
(Form H) bioretention designer will inspect the system and complete
Sign-Off Form H with attached photos.
STEP 1: Pre-start meeting Hold a pre-start meeting with the bioretention designer, civil
engineer, landscape architect, site superintendent, civil
contractor, landscape contractor and, where required, the Council
compliance officer to:
STEP 2: Preparation Prepare for construction at least 10 days before starting on site.
Preparation includes organising the correct equipment to achieve
required tolerances (Section 3.4.2), ordering materials and
identifying construction timing and rain contingency plans
(Section 3.3).
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 3: Install overflow pit and Install overflow pit and ensure the crest of the pit is at design
outlet pipe level. The crest of the pit can be used as a datum from which other
levels within the system are be measured. The pit requires holes
for under-drainage pipe connections. These holes should be
drilled at this stage or plastic stubs should be installed at the time
of casting the pit.
89
90
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 5: Install sediment basin The various flow controls for the sediment basin should be
flow controls installed in accordance with the sediment basin design, for
example the Best Practice Erosion and Sediment Control
(IECA, 2008).
STEP 6: Stabilise base of The base of the sediment basin should be stabilised to avoid
sediment basin scour and re-suspension of sediment. This may involve installation
of turf or filter cloth in the base of the system.
PRACTICAL COMPLETION OF STAGE 1 CIVIL WORKS: The ‘bulked out’ bioretention system operates as
a sedimentation basin during building phase of development. At the end of the building phase (80–90%
completion of building) the bioretention system (sediment basin) is cleaned out and civil works
completed and landscape established.
Table 3.11: Civil construction and landscape establishment step-by-step sequence — Option 3
STEP 7: Pre-start meeting Hold a pre-start meeting with the bioretention designer, civil
engineer, landscape architect, site superintendent, civil
contractor, landscape contractor and, where required, the Council
compliance officer to:
STEP 8: Preparation Prepare for construction at least 10 days before starting on site.
Preparation includes organising the correct equipment to achieve
required tolerances (Section 3.4.2), sourcing the bioretention
media ensuring the supplier of the filter media is completing the
STEP 9: Clean out the Drain the bioretention system and remove accumulated sediment,
bioretention system gross litter and any lining installed for sediment basin operation.
91
92
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 10: Check the hydraulic The hydraulic structures should be inspected for damage or
structures movement.
STEP 11: Trimming and profiling Undertake detailed excavation, trimming and profiling of bunds,
embankments, batters, sides and base of system, ensuring base
has minimum 0.5% grade towards pit, unless the design specifies
a flat base and design levels achieve (+ 50 mm).
If the design has a flat base, confirm with the designer and refer
to these guidelines or the WSUD Technical Guidelines for South
East Queensland (SEQHWP, 2006)if the designer does not
understand the purposes of the 0.5% grade.
STEP 12: Construct overflow weir Where an overflow weir is part of the system design, it should be
if required constructed at this stage and appropriately ‘keyed’ into the bunds
to avoid potential scour at the edges of the weir. Design levels and
tolerances must be achieved (+25 mm).
STEP 13: As-constructed survey An as-constructed survey of the system is required at this stage
to confirm design and tolerances (Section 3.4.2) are achieved,
- overflow weir
STEP 14: HOLD POINT Following collection of the as-constructed survey, the site
Inspection and sign-off (Form A) superintendent and bioretention designer will inspect the system
with the contractor, review the as-constructed survey and take
photos. If the construction meets the tolerances outlined Section
3.4.2 and conforms with the design, complete Sign-Off Form A
attaching the as-constructed survey and photos.
STEP 15: Filter cloth lining Line system with filter cloth, ensuring filter cloth extends
a minimum of 500 mm beyond the top of the bioretention
system’s side walls.
STEP 16: Install under-drainage Install slotted rigid under-drainage pipes or ag-pipe and rigid
collector pipes in the specified layout outlined in Section 3.4.5.
Ensure all pipes are laid at a minimum 0.5% slope with no
localised depressions verified using levels or string lines. Ensure
levels are achieved (+25 mm). Seal junctions and connections
using sufficient sealant to prevent sand, gravel or soil passing into
drainage network.
STEP 17: Install cleanouts Connect clean out points ensuring the top of clean out points will
ultimately sit at least 50 mm (preferably 150 mm) above the
bioretention surface. Clean out caps should be screwed in place to
93
94
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 18: HOLD POINT Following collection of the as-constructed survey, the site
Inspection and sign-off (Form B) superintendent and bioretention designer will inspect the system
with the contractor, review the as-constructed survey and take
photos. If the construction meets the tolerances outlined Section
3.4.2 and conforms with the design, complete Sign-Off Form A
attaching the as-constructed survey and photos.
STEP 19: Source drainage layer, Testing and sourcing of the drainage, transition and filter media
transition layer and filter media layers should have commenced as part of Step 2. By Step 19, the
material material can be delivered and stockpiled on site ready for
installation.
STEP 20: Install drainage layer Install 200–250 mm deep gravel drainage layer to cover the
slotted under-drainage pipe network. The preferred approach is
to use an excavator (long-arm if required) or conveyor belt (see
Section 3.4.7) positioned on the edge of the system to place
gravel into the system. Contractors can then spread and flatten
the gravel to the specified depth using spreader bars. The exact
procedure for constructing the drainage layer is determined
through consultation with the contractor. It may differ from the
procedure described in Section 3.4.7.
STEP 21: HOLD POINT The site superintendent or bioretention designer should inspect
Inspection of drainage layer the drainage layer to ensure the correct depths (200–250 mm)
and grade (typically 0.5%) have been achieved and the surface is
flat. The relevant sections of Sign-Off Form C must completed
and photos taken. There is no need to stop construction for this
inspection unless specifically required. The site superintendent or
designer should undertake the inspection as construction occurs.
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 22: Install transition layer Install a 100 mm deep coarse sand transition layer on top of the
gravel drainage layer using the same approach outlined in Step 14
to achieve the correct tolerances (+25 mm) and to ensure the
surface is flat.
STEP 23: Inspection The site superintendent or bioretention designer should inspect
of transition layer the transition layer to ensure the correct depths (100 mm) and
grade (typically 0.5%) have been achieved and that the surface is
flat. The relevant sections of Sign-Off Form C should be
completed and photos taken. There is no need to stop
construction for this inspection, unless specifically required.
The site superintendent or designer should undertake the
inspection as construction occurs.
STEP 24: Install filter media Place the bioretention filter media to the designed the surface
level of the bioretention system, in two separate lifts where
required, with each lift lightly compacted as outlined in Section
3.4.6. At the completion of the section lift and compaction, use a
spreader bar to flatten the surface of the filter media. Ultimately,
the surface of the filter media must be level at the design level
(+25 mm) and free from local depressions.
STEP 25: Install sediment fences Immediately after installing the filter media, install sediment
fences around filter media and at the top of the batter to prevent
sediment from entering the batters and to keep construction
vehicles off the system.
STEP 26: Lay protective filter If there will be delay between Step 34 and Step 35 (handover from
cloth, where required civil contractor to landscape contractor), the surface and batters
of the bioretention system should be covered with a temporary
layer of filter cloth to protect against sediment-laden runoff. The
filter cloth will be removed prior to installation and establishment
of the landscape.
STEP 27: As constructed survey Undertake an as-constructed survey of the system surface and
surrounding bunds, choosing at least four spots on the surface
of the small bioretention systems (<100 m²), one spot level per
100 m² on the surface of large bioretention systems and at least
one spot level every 10 m along the top of the bunds as well as any
low points.
STEP 28: HOLD POINT Following collection of the as-constructed survey, the site
Inspection and sign-off superintendent and bioretention designer will inspect the system,
(Forms C and D) review the as-constructed survey and take photos. If the
construction meets the tolerances outlined Section 3.4.2 and
conforms with the design, Sign-Off Forms C and D will be
completed and signed and the as-constructed survey and
photos attached.
STEP 29: Install coarse sediment Construct coarse sediment forebay in accordance with the design
STEP 30: Inspection and sign-off The site superintendent or bioretention designer should inspect
(Form E) the coarse sediment forebay to ensure consistency with design.
PRACTICAL COMPLETION The relevant sections of Sign-Off Form E should be completed
and photos taken before either Building Phase Protection works
or Landscape Works start.
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
CONTINUE TO STEP 31 (Landscape Works) immediately. This will involve a rapid handover from the
civil contractor to the landscape contractor.
Landscape works Before starting landscape preparation, hold a pre-start and plant
STEP 31: Pre-start and plant set-out meeting with the bioretention designers, including an
set-out meeting ecologist, site superintendent and landscape contractors. The
meeting should confirm design and planting establishment and
set out the planting to ensure the correct plants are installed in
the correct locations.
STEP 32: Preparation Prepare for the landscape establishment up to six months before
starting, including ordering and inspecting plants at the nursery,
ordering and receiving organic mulch and matting and organising a
source of irrigation water. For bioretention systems, recycled
water for irrigation is generally not recommended.
STEP 33: Remove temporary If temporary protective filter cloth was installed at STEP 26, this
protection should be removed at this stage. Care should be taken to avoid
damaging the clean-out points for the under-drainage.
STEP 34: Flatten surface After the protective layers are removed, flatten the surface
of the filter media using a spreader bar. Additional filter media
may be required to fill in any over-excavated zones. Care should
be taken to not over-compact the filter media (refer Sections
3.4.6 and 3.4.7).
STEP 35: Mulching Mulch the filter media surface in accordance with Section 3.6.4.
Create holes in the mulch for planting. Ensure the holes have 50
mm separation from stem of the plant to the mulch.
STEP 36: Soil preparation Dig planting holes by hand and apply the prescribed amount of
slow-release native fertiliser detailed in Section 3.6.3. Pre-soaked
wetting agents are recommended in this step.
STEP 37: Planting Plant tubestock ensuring the root ball is covered with filter media
and the stem is sitting above the filter media. Clear away any
mulch from the step to 50 mm (refer Section 3.6.5).
STEP 41: On-going inspections Monitor the establishment of plants until they are robust and
and final landscape self-sustaining.An established bioretention is measured by
establishment (Section 3.6.7):
7. no weeds.
99
100
CONSTRUCT ION STEP ACTIV IT Y PHOTOS P HOTO S
(SMALL BIORETENTION SYSTEM) ( LAR GE B IO R E TE N TIO N SYSTE M )
STEP 42: Inspection and sign-off After plants are established, the site superintendent and
(Form H) bioretention designer will inspect the system and complete
Sign-Off Form H with photos attached.
Table 3.12: Potential failure scenarios for bioretention systems and rectification actions
Ponding water on surface or Blinding or blockage of filter media surface Confirm surface blinding or blockage by scraping back the surface sediment to reach the bioretention
reduce filtration rate with sediment. filter media filling the void with water to see if the water drains. In-situ hydraulic conductivity testing
should be undertaken at the surface, middle and bottom of the filter media profile in accordance with
Practice Note 1: In-Situ Measurement of Hydraulic Conductivity (Hatt and Le Coustumer, 2008).
- collecting samples at the surface and at depth at a number of locations in the system
- testing samples for particle size distribution and saturated hydraulic conductivity in accordance
with the Guideline Specifications for Soil Media in Bioretention Systems (FAWB, 2008).
- the in-situ hydraulic conductivity testing confirms low conductivity at the surface and high
conductivity at depth
- the particle distribution size analysis finds finer material at the surface.
DEFECT OR FAI LU RE CAUS ES RECTIFICATION
- removing the surface layer of sediment and re-installing the filter media to achieve the design
surface level, then mulching and replanting
- planting with rushes, grasses and trees to increase plant and root density to break up the surface.
The bioretention system must drain according to design requirements within 12 months. If it does not
drain, remove the surface sediment and re-mulch and replant the system.
If the testing finds the filter media has structurally collapsed, rectification is required.
- removing the filter media and installing new media that meets the specifications, mulch and replant
(preferred)
- planting with rushes, grasses and trees to break-up the surface (alternative).
The bioretention system must drain according to the design requirements within 12 months. If it does
not drain, remove the surface sediment and re-mulch and replant the system.
Ponding water on surface or Blockage of transition or drainage layer with To confirm if the transition layer or drainage layer is blocked with sediment, a geotech specialist can
reduce filtration rate (cont). sediment. create boreholes at a number of locations in the bioretention system to allow the collection of samples
for particle size distribution analysis. Permeability testing should also be undertaken at the transition
layer and drainage layer to confirm hydraulic conductivity.
If the transition layer or drainage layer is blocked with sediment (i.e. contains significant fine soils),
remove the bioretention media and refill the system with filter media and plant out in accordance with
these guidelines.
Filter cloth around under-drainage or Filter cloth should not be installed around the under-drain or between any of the bioretention media
between the filter media and transition layer/ layers. The Sign-Off Forms and photos will confirm that filter cloth has not be used.
drainage layer is clogged with fine sediment.
If filter cloth has been used and is clogged with fine sediment, remove the filter cloth and the
bioretention media. Refill the bioretention system with filter media and plant out in accordance with
these guidelines.
Blockage of under-drains. Clean out under-drains with standard plumbing equipment. The bioretention system should drain after
cleaning. If system does not drain, then investigate blockage of the transition or drainage layers,
blinding of filter media, or structural collapse of the filter media.
Scour and short-circuiting of Under-drains that are not sealed into outlet To rectify (Figure 3.16):
flows at outlet pit pit can result in flow short-circuiting down
- seal the under-drainage pipes into the pit
the side of pit and scouring the filter media,
the transition layer and the drainage layer. - dig out the eroded sections of the bioretention profile including the filter media, transition layer and
drainage layer well beyond the bounds of the scour
- install a layer of filter cloth to the pit and extend it down the side of the pit into the filter media to a
depth of300 mm, extending the filter cloth horizontally out into the filter media by 300–500 mm as
shown in the sketch to minimises the risk of scour down the side of the pit.
DEFECT OR FAI LU RE CAUS ES RECTIFICATION
- install a layer of filter cloth to the pit and extend it down the side of the pit into the filter media to a
depth of 300 mm, extending the filter cloth horizontally out into the filter media by 300–500 mm as
shown in the sketch to minimises the risk of scour down the side of the pit
- replace the drainage layer, transition layer and filter media and compact the layers.
- replace the drainage layer, transition layer and filter media and compact the layers
103
104
DEFECT OR FAI LU RE CAUS ES RECTIFICATION
- install clay within the 0.5 m space, from the edge of the filter media to the wall
- compact the clay to ensure there is no potential flow connection from the wall to the drainage layers
of the bioretention system
- install filter fabric up the vertical edge of clay and across flat surface
- install the drainage layer, transition layer and filter media and compact the layers
Scour around the high-flow weir If the weir crest and grouted rock protection Extend the concrete weir crest and grouted rock batters up the batters to at least 500 mm above the
is not extended up the batters of the weir invert.
bioretention system, scour may occur around
the edge of the weir as flows will skirt the
weir.
Scour of bioretention batters Lateral surface flows enter the bioretention Direct the lateral flows to small rock-lined channels that feed down the batters to the bioretention
system from a small catchment directly system. Plant out scoured zones. Where required, organic mesh or netting may be required to avoid
adjacent to the bioretention. erosion of the batters.
Failure of the bioretention bunds Failure of bioretention bunds can occur Rectify scour and ensure geotech certification of the bund for stability and capacity. If necessary, raise
through scours and overflows. The bunds can the bund well above the top of the potential flood levels in the bioretention system and provide rock
Damaged to clean-out or missing The systems may be vandalised, for example, Replace inspection caps and ensure they are secured with screws to reduce the risk of vandalism.
inspection caps inspection caps may be removed.
DEFECT OR FAI LU RE CAUS ES RECTIFICATION
Failure of plants Plants may fail to thrive if the filter media Review Bioretention Construction and Establishment Sign-Off Form C to confirm the media meets the
does not meet specifications, particularly for specifications outlined in Section 3.5.
water-hold capacity and organic content.
Collect samples within the bioretention system at the surface, middle and base of the filter media
approximately every 250 m2. Complete the FAWB tests on the samples in accordance with Section 3.5
and compare the results with the specification.
If the installed media does not meet the specifications, seek advice from laboratory on how to ensure
the specifications are met. In-situ amelioration may be possible; however, if not the filter media will
need to be removed and replaced.
Inappropriate watering during establishment If plants are alive, irrigate according to the recommendations in Section 3.6.6 or install a riser at the
of plants. outlet pit to raise water levels in the bioretention system to just below the root of the plants.
If the plants have died, mulch, replant and irrigate according to Section 3.6.6 or install a riser to raise
water levels in the bioretention system.
Lack of mulch or fertiliser during If plants are alive, apply small quantity of liquid fertiliser and apply much. If plants have died, mix
establishment of plants. compost or organics into the top 50–100 mm of the filter media, mulch and replant.
Poor plant cover of less than five to six plants Review species selection in consultation with the bioretention designer and select an alternative
per m2. species that is better suited to the subject site.
Excessive weed cover. Remove weeds manually to protect native plants. Avoid weed seed set by pro-actively maintaining and
reducing weeds from the edge of the bioretention system.
106 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
3.13 Compliance The tender and contract documents can refer to the
Compliance of bioretention systems are a major relevant sections of this guideline. If requirements for
challenge for local authorities. the Sign-Off Forms are not achieved, then the contract is
not fulfilled and payment should be withheld.
The Bioretention Construction and Establishment
Sign-Off Forms and the certification requirements 3.14.2 Ownership and handover
outlined in Section 3.12 provide the basis for compliance. A common problem with the construction and
To support the final compliance inspection for practical establishment of WSUD systems is ownership and
completion the required documentation includes: maintenance during both the handover of the asset
• completed Construction and Establishment from the civil contractor to civil contractor and the
Sign-Off Forms building phase. These issues must be considered when
establishing the contracts:
• as-constructed survey and photos
• Handover from civil contractor to landscape
(as per Sign-Off Form requirements)
contractor — This handover process can take months
• site superintendent certification to occur due to a number of reasons, for example,
• bioretention designer certification. separate operational works approval processes for
landscape design. The bioretention system may
Additionally, it is recommended compliance inspections remain un-vegetated and unmanaged during this
are undertaken at the following hold points: period. Sediment accumulation and damage will during
• pre-start meeting rainfall events and maintenance or rectification will be
• inspection of the bioretention with under-drainage required.
installed prior to installation of media (Step 12)
If there will be a delay between the civil works and
• practical completion or on-maintenance of civil works landscape works, then it is recommended a maintenance
(at Step 22 and, where applicable, Step 28 and when contract is established (or maintenance allowance
Sign-Off Forms A, B, C, D, E and F are complete) is made in the civil contract) for inspection, cleanout
• practical completion or on-maintenance of landscape and rectification of the civil works during this period.
works (STEP 36 and Sign-Off Form G) This could be costed as a monthly allowance or on a
• final inspection or off- maintenance following per inspection or a per maintenance event basis. It is
landscape establishment (STEP 40 and Sign-Off recommended the civil contractor is responsible for
Form H). this work and the contract reflects the inspection or
maintenance requirements.
3.14 Civil and landscape contracts • Building phase maintenance — During the building
phase, sediment accumulation and damage will occur.
3.14.1 Contracts It is important that regular inspections occur after
rainfall events and that appropriate cleanout and
To ensure all parties are aware of the certification rectification is undertaken. It is recommended a
requirements, the Tender and Civil and Landscape maintenance contract is established for this purpose.
Contracts must include: The maintenance contract could be costed as a
• construction and establishment specifications monthly allowance or on a per inspection or per
(provided in Sections 3.4, 3.5 and 3.6 of these maintenance event basis and the work can be
guidelines) undertaken by the civil or landscape contractor or a
• preferred construction and establishment method maintenance contractor. Once 80–90% of the building
(see Section 3.8) is complete, the maintenance contract would cease
and landscape works would commence.
• Sign-Off Forms with the as-constructed survey and
drawing requirements
• certification requirements listed in Table 3.14.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 107
3.15 Sign-Off Forms
The Bioretention Construction and Establishment
Sign-Off Forms provided outline the key items to be
reviewed when delivering and inspecting bioretention
systems. The Sign-Off Forms follow the construction
methods provided in Sections 3.9 and 3.10. The
forms are to be used by contractors, construction
site superintendents, designers and local authority
compliance inspectors to ensure all the elements of
the bioretention system have been constructed in
accordance with the design. If an item receives an ‘N’ in
the ‘Satisfactory Criteria’, indicating that an element is
‘not satisfactory’, appropriate actions must be specified
to rectify the construction issue before final inspection
sign-off is given.
108 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
BIORETENTION SYSTEM CONSTRUCTION & ESTABLISHMENT SIGN-OFF FORMS
System location:
Developer
Site superintendent
(landscape)
Bioretention designer
Civil engineer
Landscape architect
Civil contractor
Landscape contractor
NAME OF
SIGN-OFF FORM DATE COMPLETED SIGNATORY & ROLE SIGNATURE
(E . G . SUPERINTENDENT)
Pre-Start Meeting
Form B — Under-Drainage
Form F — Protective
Measures
Form G — Landscape
Installation
Form H — Landscape
Establishment
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 109
PRE-START MEETING
List pre-start meeting attendees who are to sign indicating they have attended the meeting and understand the design intent,
construction and establishment process.
Location
Date
Developer
Site
superintendent(landscape)
Bioretention designer
Civil engineer
Landscape architect
Civil contractor
Landscape contractor
Other
Other
Other
110 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM A — EARTHWORKS AND FUNCTIONAL (HYDRAULIC) STRUCTURES
Purpose: To ensure earthworks bulking out, trimming and profiling and the key levels of functional (hydraulic) structures are in
accordance with design drawings and specifications. The earthworks and structures dictate the movement of stormwater
through the bioretention system and are a critical element in the function of the system.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 111
FORM B — UNDER-DRAINAGE
Purpose: To ensure under-drainage is installed correctly before the bioretention media is installed.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.
Date: Date:
112 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM C — BIORETENTION MEDIA
Purpose: To ensure that the media placed in the system meets the required specifications and that there is a record of the
media being delivered to site.
To ensure media layers are installed correctly and meet the design and specification requirements.
ACTION (IF
DRAINAGE LAYER CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent or bioretention designer inspection and review of test results and certifications before proceeding.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 113
FORM C — BIORETENTION MEDIA (CONT .)
ACTION (IF
CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
INSPECTION: Superintendent and bioretention designer inspection and sign-off to occur while installation of media is
occurring. Photos must be taken by the superintendent, the bioretention designer or the contractor.
NB: Laboratory test results, certification, delivery dockets and photos attached.
Date: Date:
114 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM D — FINISHED LEVELS
Purpose: To ensure finished levels of system surface and bunds are correct and meet the design.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 115
FORM E — COARSE SEDIMENT FOREBAY
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent or bioretention designer inspection and sign-off before proceeding.
Date: Date:
116 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM F — PROTECTIVE MEASURES
Purpose: To ensure protective measures are correctly installed to protect the bioretention system while building is occurring in the catchment.
HOLD POINT: Superintendent and bioretention designer inspection and sign-off before proceeding.
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 117
FORM G — LANDSCAPE INSTALLATION
Purpose: To ensure the correct plants are supplied, installed and established.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent AND bioretention designer inspection and sign-off before proceeding.
Date: Date:
118 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM H — LANDSCAPE ESTABLISHMENT
Purpose: To ensure the correct plants are supplied, installed and established.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
PLANT ESTABLISHMENT
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 119
FOUR CONSTRUCTED WETLANDS
120 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
4.1 Constructed Wetlands
Natural wetlands are places in the landscape that are of pollutants, or actually become a source of pollutants
inundated with water for all, or at least part, of the year. itself. The essential elements for a constructed
The plants that grow in natural wetlands adapt so wetland are:
they can survive inundation or wet and dry cycles. • the correct mix of open water and planted zones
The capacity of wetlands to absorb pollutants has
led wetlands to be artificially constructed to improve • the correct installation of hydraulic structures
the quality of stormwater in urban environments.
• good quality growing soil and media for plants
Constructed wetlands are used as biological filters
that bring together a range of processes, both physical, • the right plants in the right locations
chemical and biological, to improve the quality
of stormwater. • effective establishment and pro-active maintenance
to ensure the wetland functions in the long term.
As complex and highly active biological systems,
wetlands use a variety of processes to intercept, Constructed wetlands consist of an inlet zone,
transform and remove pollutants from stormwater. a sediment basin to remove coarse sediments,
They are robust and dynamic systems able to cope a macrophyte zone1 and a high-flow bypass channel
with large variations in flow, climate and nutrients. to protect the macrophyte zone from scour and
However, constructed wetlands need to be built to vegetation damage. Figure 4.1 shows the key elements
support the best conditions for plant growth and of a constructed wetland system. Further description
the removal of pollutants. of the elements of constructed wetland systems is
provided in the WSUD Technical Guidelines for South
From the perspective of stormwater management, an
East Queensland.
effective constructed wetland enables the processes for
removing pollutants under varying hydraulic conditions.
If an element is not considered appropriately, the
wetland may fail to establish, offer limited treatment
1 A shallow, heavily vegetated area to remove fine particulates and to take up soluble pollutants.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 121
4.2 Roles and responsibilities A pre-start meeting with all the stakeholders identified
While constructed wetlands have been used for some in Table 4.1 must be held to:
time to remove stormwater pollutants, there are many • explain the function of the wetland
areas where better construction and establishment can
enhance pollutant removal, aesthetics and reduce the • highlight issues and risks associated with construction
need for reworking. and establishment
Knowing who is responsible for different elements of • talk through the preferred construction and
construction, and particularly establishment, is critical. establishment approach
Strong and ongoing communication between designers,
• explain the as-constructed survey or drawing,
superintendents and contractors is critical. Table 4.1
inspection and sign-off requirements.
summarises recommended roles and responsibilities for
constructing, establishing and certifying constructed
wetlands.
Table 4.1: Roles and responsibilities for wetland construction and establishment
Wetland designer Design and The wetland designer designs the wetland. They ultimately provide final
construction certification of the constructed system and help to solve construction issues.
troubleshooting
Landscape Design and The landscape architect develops landscape and planting plans in association
architect landscape with the wetland designer as well as other elements such as boardwalks,
viewing platforms and edge treatments.
Civil engineer Design civil The civil engineers design the civil works related to the wetland such as edge
components structures or overflow pits.
Site Supervise The site superintendent is responsible for all site works associated with
superintendent construction delivering the construction plans. The site superintendent coordinates the
(civil and construction and certification processes.
landscape)
Civil contractor Civil works and The civil contractor is responsible for all civil components of the system —
install bulk earthworks, construction of hydraulic structures and other structures
such as bridges and footpaths. They are also required to protect the system
from sediment until the landscape contractors plant vegetation.
Geotech specialist Design and The geotech specialist is responsible for the design and certification of liners
certification of lining and embankments.
and embankments
Landscape Landscape The landscape contractor plants the vegetation and may also be involved in
contractor installation and some edge details in areas of high amenity.
inspection
Local government Compliance The compliance officer represents the interests of the local authority to
compliance officer inspections ensure the system is built and established according to approved construction
plans and they certify the designs.
122 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
4.3 Timing should target a suitably dry period for construction or
The timing of civil and landscape works for constructed have a diversion system in place to isolate the site.
wetlands must be carefully planned to ensure the Approximate construction periods are:
construction and establishment process, and the
- small constructed wetlands of <100m2 : 7 days
downstream waterways, are not impacted by
stormwater and sediment. This requires consideration - large constructed wetlands of >100m2 : up to 2
of the following: months
• Construction phase erosion and sediment control: Civil works should progress quickly to stabilise and
Before the construction works begin, ensure the area protect the constructed wetland against storm events.
is stabilised and appropriate erosion and sediment This requires all materials to be ordered and delivered to
control is present in the catchment. Erosion and the site and protective measures installed (diversion
sediment control (ESC) measures must be in place in systems) before construction starts.
accordance with local government requirements and a • Landscape works: Landscape works for constructed
recognised guideline such as Best Practice Erosion wetlands should start as soon as possible after the
and Sediment Control (IECA, 2008) and upstream civil works are complete and the building protection
flows diverted away from the works area. The civil measure are installed. This limits the risk of erosion
works contractor and site superintendent should and sediment-laden runoff entering the system. Close
consider a number of things: coordination between the civil contractor and the
landscape contractor is required. The responsibility
- Whether the constructed wetland can form the
for the constructed wetland site during handover
sediment basin for the catchment during the
between the civil works and the landscape works must
construction phase.
be clear. Responsibility for any remedial works if the
- If the wetland is not used as the sediment basin for constructed wetland is damaged should be explicit.
the catchment during construction phase, then a Section 4.7 discusses further the protection of
construction phase sedimentation basin maintained constructed wetlands during the building phase.
upslope of the wetland may give additional
protection if effective erosion control is not
achieved on exposed soil surfaces. 4.4 Civil considerations
- The site must comply with erosion control standards and specifications
when construction phase sediment basins are It is critical that wetlands are delivered in accordance
decommissioned or transformed into constructed with the design. Changes made during construction and
wetlands or other stormwater management devices. establishment can result in a compromised wetland.
- ESC measures downslope of constructed wetlands Wetland vegetation is extremely sensitive to water
must be operational during construction of depths and any proposed modifications during
constructed wetlands. The ESC measures must construction must be approved by the designer.
remain in place until the constructed wetlands are A number of critical civil works issues that require
stabilised against soil erosion. particular attention are:
• Rainfall: When the civil works begin, stormwater
1. construction phase erosion and sediment control
inflows can cause irreparable damage to constructed
wetlands. If it rains when the macrophyte zone has 2. hydraulic structures — high-flow bypasses, transfer
been planted with tubestock and there is no diversion pits and outlet structures
structure installed then sediment laden runoff can
3. impervious liners
enter the system. If this occurs, the sediment may
smother the tubestock plants and change the depth 4. earthworks
profile of the wetland meaning the accumulated
sediment and plants may need to be removed. 5. tolerances
Therefore, the timing of civil works must be planned to
6. inlet pond and maintenance access.
protect the macrophyte zone from any stormwater
inflows during construction if the zone has been
planted.The civil contractor and site superintendent
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 123
4.4.1 Controlling erosion and sediment 4.4.2 Hydraulic structures
during the construction phase Correct hydraulic function is critical for constructed
During the construction phase of the development (see wetlands to operate successfully. Most wetland
Section 4.6), the bulked out constructed wetland will, in hydraulic structures are relatively simple; however, the
many cases, be used and maintained as sediment basin. fine tolerances required can be easily overlooked, having
The timing of decommissioning of the sediment basin a dramatic effect on wetland vegetation and function.
and transforming it into a wetland must be carefully All structures must be constructed in accordance with
considered. The site must comply with erosion and the design. Any potential changes to the design must
sediment control standards of the local authority before be confirmed in writing with the wetland designers
the sediment basin is decommissioned or its before construction starts. Once constructed, the
effectiveness is reduced. This requires the following hydraulic structures should be surveyed and reviewed
issues to be considered: by the designers before finer shaping of the earthworks
are undertaken.
• The catchment draining to the wetland and the area
adjacent must be protected by erosion and sediment Even for very large wetlands, very fine tolerances
control (ESC). Turfing and hydromulching footways and (<25 mm) are required for all the hydraulic structures
allotments are the most effective way to minimise soil (see Section 4.4.5 for tolerances). Table 4.2 summarises
erosion. the hydraulic structures, the preferred designs and
construction requirements. If the proposed design is
• ESC measures downslope of the proposed wetland missing any of the hydraulic structures, or varies from
must be in place and operational before, and during, the descriptions provided in the table, the designer
construction of the wetland. should be consulted in writing for guidance.
Further guidance on erosion and sediment control is
provided in:
124 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
Table 4.2: Constructed wetland hydraulic structures
Inlet zone This structure transfers flows from Overflow pit requirements:
connection to an inlet zone, or pond, to the
- concrete construction
the macrophyte macrophyte zone. It controls the
zone (overflow water levels in the inlet pond and the - letter box or dome grate (not flush grate)
pit and pipe) maximum flow rate that can reach - crest level typically 100–300 mm above the macrophyte zone
the macrophyte zone. water level and 300 mm+ below the high-flow bypass weir
level.
It consists of an overflow pit and
pipe sized to convey a 1-year ARI Pipe connection requirements include scour protection at the
stormwater event. outlet to the macrophyte zone (refer to design for details).
High-flow The weir is located in the inlet zone High-flow weirs need to operate under high-flow conditions
bypass weir (pond) and enables stormwater to requiring:
safely discharge from the inlet zone
- a mass concrete weir crest typically 500 mm deep with
around the macrophyte zone in
reinforcing
periods of high flows.
- grouted rock protection at least on the downstream face of
the crest to the toe of the batters
High-flow The channel protects the wetland The bypass channel typically consists of turf but can be formed
bypass channel from large, infrequent flows by a number of landscapes. Where turf is adopted, it should be
bypassing excess flows around the laid perpendicular to the flow direction and pinned in place.
wetland, reducing the risk of damage
from erosion, scour and re-
mobilisation of pollutants.
Macrophyte zone The riser outlet is designed to The riser outlet should be located in a pit on the embankment
outlet (riser outlet) provide a uniform detention time for or bund of the wetland. This allows access for inspection and
water passing through the maintenance. A submerged connection minimises the risk of
macrophyte zone of the wetland. litter accumulation. The riser can be formed through either an
upstand pipe with holes or a plate with holes. See Figure 4.2.
Macrophyte The maintenance drain allows the The maintenance drain consists of a pipe connected to the ‘low
zone outlet macrophyte zone to be drained and points’ or deep-water zones of the wetland. The pipe passes
(maintenance also enables adjustments in the through the macrophyte zone outlet pit. A valve is installed on
drain) water level while vegetation the pipe to allow the macrophyte zone to drain.
establishes.
Macrophyte zone These outlet pipes drain from the If the outlet pipe is drowned during construction, consult with
outlet pipes macrophyte zone outlet pit to the the wetland designers.
receiving environment.
The outlet pipe should incorporate a seepage collar.
It is important that wetlands are free
draining to the downstream
environment.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 125
Figure 4.2: Example of riser located in a pit Following installation of the liner, hydraulic structures
involving pipe connections are constructed, often
through the impervious liner. It is critical that the
liner is intact at these connection points and adequate
attention is paid to establishing a waterproof seal.
126 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
Table 4.3: Constructed wetland tolerances
• inlet pipes
• outlet riser
• bypass weir
Earthworks (base The bathymetry or final earthworks through all elements of ± 50 mm Survey*
of wetland) the constructed wetland is critical. The establishment of
wetland vegetation relies on correct water depths. The
tolerance provided relates to all earthworks through the
wetland and must be measured at the surface of the
topsoil.
Embankments or The embankment or bunds around the wetland act to hold ± 50 mm Survey*
bunds stormwater within the extended detention during rainfall
events and, where required, force larger rainfall events into
the hydraulic structures. Therefore, the crest level on the
embankments or bunds is important.
4.4.6 Maintenance access • For slopes less than 1 in 4, access should be reinforced
Access to the constructed wetland is important for concrete from the base of the inlet pond to 0.5 m
maintenance. In particular, the inlet zone (pond) requires above the standing water level. From 0.5 m above the
a track that is suitable for heavy machinery to remove water level, and upward, the access can be formed with
debris and for de-silting as well as an area for de- gravel or reinforced turf.
watering removed sediments. If sediment removal • Where maintenance access to the inlet pond cannot be
requires earthmoving equipment to enter the basin, then provided, suitable access and space should be allowed
a stable ramp suitable for heavy plant will be required for a sucker truck to remove sediment. This option is
into the base of the inlet zone. The width of the access subject to approval by the local authority.
into the inlet pond should be a minimum of 3 m with the It is recommended that the inlet zone is constructed
following preferred surface finishes: with a hard (i.e. concrete or rock) bottom to assist with
• For slopes greater than 1 in 4, access should be maintenance. This allows excavator operators to detect
reinforced concrete designed in accordance with local when they have reached the base of the inlet zone during
council requirements to support machinery. Surface desilting operations.
finishes can be applied for landscape purposes. Macrophyte zones require access for weeding and
replanting as well as regular inspections of the outlet
pit. Commonly, these access tracks can be incorporated
with walking paths around the wetland.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 127
4.5 Landscape considerations purchased from a soil supplier and must still comply
and specifications with the AS 4419.
There are a number of key issues to consider for the 4.5.1.2 AMENDMENT AND TREATMENTS
landscape works associated with constructed wetlands. Amending the topsoil to meet the specifications will be
guided by a laboratory and may involve adding fertiliser
4.5.1 Topsoil or organics to the soil.
The correct topsoil is crucial to successful macrophyte The topsoil covering the bed of the wetland should be
establishment and to the long-term functioning of the treated with gypsum or lime, which is standard on most
wetland. Wetland macrophytes prefer medium-textured construction sites. The gypsum or lime facilitates
silty- to sandy-loams that allow for easy rhizome and flocculation, reducing the turbidity of the water column.
root penetration. Although there are a few plants that With lower turbidity, higher levels of light are able to
can grow in in-situ heavy clays (e.g. phragmites), growth reach the plants, helping their growth and establishment.
is slow and the resulting wetland system will have a low The gypsum should be applied at a rate of 0.4 kg/m²,
species richness. preferably immediately prior to the initial inundation of
4.5.1.1 SPECIFICATION the wetland. Further application may be required at
Within the wetland macrophyte zone, topsoil should be intervals depending on the condition of the wetland and
placed to a depth of 300 mm. Design levels for wetlands the amount of exchangeable sodium.
are inclusive of topsoil, therefore, when earthworks are The application of lime may be required where the soil
occurring, allowance for 300 mm of topsoil is required. If testing identifies a potential soil pH problem (pH < 5) or
the wetland sits on in-situ clay, the base should be ripped where acid sulphate soils exist. The rate of application
before placing topsoil to avoid a distinct soil horizon. should be guided by soil test results, an Acid Sulphate
Topsoil must be tested by a NATA-accredited laboratory Management Plan and water quality (pH) monitoring of
in accordance with AS 4419—Soils for landscaping and the wetland and inflow.
garden use. If the proposed topsoil has high salt levels,
extremely low levels of carbon (<5%), or any other 4.5.2 Plant types and density
extreme that may retard plant growth, it should be The planting specification should be considered as part
rejected. The laboratory testing will identify any of the design and documented on the design drawings.
amelioration requirements. The results of the topsoil Planting design should be undertaken in collaboration
test must be given to the site superintendent and with a freshwater aquatic ecologist to consider:
wetland designer for review before the topsoil is
• water depth
installed.
• hydrology and hydrologic effectiveness
Topsoil for wetlands can be sourced from the in-situ
• potential drying periods
topsoil or from soil suppliers. During the wetland
construction process, topsoil will be stripped and • location within macrophyte zone.
stockpiled. Most terrestrial topsoils provide a good The WSUD Technical Guidelines for South East
substratum for wetlands, but laboratory soil testing in Queensland (SEQHWP, 2006) and the local authority
accordance with AS 4419 is necessary to ensure the should be consulted for more detail.
topsoil will support plant growth. If stockpiled topsoil is
It is important to use a relatively high density and
used, it must be approved by the laboratory and wetland
diversity of species. This ensures a higher likelihood of
designer and will need to be screened to remove any
successful establishment and quickly delivers a dense,
coarse organic matter.
mature planting, managing any potential weed issues.
Avoid excessively weed-ridden site soils, particularly Local authorities should be consulted for planting
soils containing aggressive pasture grasses tolerant of density requirements. The following is recommended
wetland conditions such as setaria and barnyard grass. as a minimum:
If these species are present, and no other sources of
• planting density of 6–10 plants/m2
topsoil exist, a minimum of 50 mm should be scraped
from the soil and discarded. • two species per macrophyte zone.
If the in-situ topsoil is not suitable and amending it If the design does not allow for these specifications,
not practical or cost effective, topsoil should be consult the designers.
128 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
4.5.3 Plant procurement Figure 4.3: Example of suitable mature tubestock
Vegetation used in constructed wetlands is typically
tubestock available from wholesale nurseries. Specialist
nurseries are familiar with supplying plants for WSUD
projects. Purchasing from specialist suppliers increases
the chances of obtaining the right plants in the correct
condition. Availability varies between nurseries and is
influenced by the time of year. Substituting species
when specified plants are unavailable can be
problematic. If a change in species is necessary,
confirm any changes with the designers and document
the change in the as-constructed drawings. Ideally,
plant availability should be discussed at the site
inception meeting.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 129
Seeding pots of 20 mm should be avoided for required. Planter holes should be twice the size of the
constructed wetlands. These seedlings are considered tubestock. Plants should be carefully removed from the
to be relatively immature and may result in high loss tube to ensure their stems do not break from the root
rates and patchy growth. ball. The top of the root ball should be slightly lower than
the surface level after topsoil has been firmly placed in
4.5.4 Timing of planting the planting hole and around the plant. Water crystals
Timing of planting is dependent on a suitable time of and fertiliser may also be used to assist with
year, irrigation requirements and the building phases of establishment; however, fertiliser should not be
the development. October and November are considered necessary in ameliorated soils.
ideal times to plant vegetation in constructed wetlands. 4.5.5.3 ESTABLISHING
Macrophytes are more tolerant of inundation in warmer Ideally, wetland plants, except true aquatic species,
waters and this timing allows for adequate should be established in a mudflat environment. Wetland
establishment and root growth before the heavy plants require 2.5–5.0 litres of water per plant per week.
summer rainfall period. Planting late in the year also Watering should be responsive to prevailing conditions
avoids the dry winter months, reducing maintenance to preserve the muddy substrate. A mudflat environment
costs associated with watering. Construction planning reduces the risk of plants drowning and makes the
and phasing should try to correspond with suitable freshly planted site less attractive for problem birds
planting months, wherever possible. However, as lead such as swamp hen and ibis (refer Section 4.4.9 for more
times from earthworks to planting can be long, detail).
temporary erosion controls should always be used
before planting. It is very important to ensure plants are established
correctly in the early stages of the wetland
Planting should be avoided during periods of extreme establishment because replanting and increasing plant
weather conditions such as very hot days or during frost cover in a wetland that has been flooded, and possibly
or heavy rainfall. with an established bird population, is very difficult,
time consuming and expensive.
4.5.5 Planting procedure
If plants must be established in a flooded wetland, water
4.5.5.1 PLANT SET-OUT
levels should be established at half the height of the
While many wetland plants may look the same, there can
wetland plants. It must not exceed two-thirds of the
be substantial differences in growing requirements,
height of the plants to avoid stress and drowning,
particularly water depth. Species planted too deep or in
particularly in winter. Planting in water will be 2–3 times
a location that is too dry will struggle to establish. This
slower than in dry conditions.
makes plant set-out important and must be a hold point
in the construction process. If the superintendent lacks Given the critical importance of successfully
specialist plant knowledge, an appropriately qualified establishing plant cover within the wetland as quickly as
ecologist or landscaper should be consulted to confirm possible, a pro-active and adaptive approach should be
that set-out and any proposed adjustments are taken, responding to any issues relating to the health of
appropriate. the plants. Responses can include adjusting water levels
(see Section 4.4.6), eliminating weeds, addressing issues
It is important to get an even cover of vegetation
with weather patterns or broadcasting seed to improve
perpendicular to the dominant flow path. Design plant
the wetland seed bank and increase plant cover in bare
densities must be checked to ensure there is no
areas.
excessive clumping of plants at the expense of other
areas that are bare. Uneven distribution of planting More than 90% of plants must survive with 80%
increases the establishment time, promotes short- coverage of the wetland, otherwise replanting should
circuiting and can compromise the wetland’s treatment occur.
performance.
4.5.6 Water level control
4.5.5.2 PLANTING
To maximise the chances of successful establishment of
Plants in constructed wetlands are usually planted as
vegetation, the water level of the wetland system should
tubestock using either hand tools or machinery. In very
be manipulated in the early stages of vegetation growth.
large wetland plantings, tractors are sometimes
When first planted, vegetation in the deep marsh and
130 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
pool zones may be too small for their prescribed water • Week 1–6 5 waterings per week
depths. Seedlings intended for inundated sections • Week 6–10 3 waterings per week
should ideally have half their stem height above water • Week 11–15 2 waterings per week.
level, and must not have any less than one-third of their
In the absence of rain, it is recommended that each plant
stem above the water level. This may not be possible if
receives 2.5–5.0 litres per week during the first six
planting stock is immature and initially planted at the
weeks to retain a muddy substrate (40 mm of watering
intended depth. If planted too deeply, young, submerged
per week during establishment).
plants will not be able to access sufficient light in the
open water zones. Without competition from submerged After this initial four-month period, watering may still be
plants, phytoplankton (algae) may start to proliferate. required within the ephemeral zones of the wetland,
particularly during the first winter or dry period.
The water depth must be controlled in the establishment
period for wetland plants. Closing off the connection Importantly, a suitable source and quantity of irrigation
between the inlet zone and the macrophyte zone and water must be identified before plants are delivered to
opening the maintenance valve in the riser outlet will site. Recycled water may be appropriate for use but
help to control the depth. The deep marsh zones should should be confirmed with the superintendent.
be approximately 150–200 mm for at least the first 6–8
weeks. This will ensure these areas are inundated to a 4.5.8 Weed control
shallow depth and that the shallow marsh zone remains Weed management in constructed wetlands is important
moist, providing suitable conditions for plant to ensure that weeds do not compete with the planted
establishment. Seedlings planted in the ephemeral species. Most weed seeds that enter a wetland will find
marsh and littoral zones of the wetland will require it difficult to establish due to the permanently wet
ongoing watering (see Section 4.4.7). When plants are nature of wetlands. However, it is important to manage
establishing well and growing actively, they should be of native aquatic species like typha or phragmites that
sufficient height to endure deeper water. The connection naturally can appear in constructed wetlands and
between the inlet pond and the macrophyte zone can be compete with more important planted species.
temporarily opened to allow the wetland to fill slowly. The most effective method of managing weeds during
The designed operating water level can be established establishment is by fortnightly inspection and removing
when it is clear the wetland plants have matured to the the weeds by hand. Regular inspections will minimise the
point where at least half of the stem is above the work and ensure the weeds are not able to establish in
operating water level. large populations and start to propagate.
Before planting macrophytes, the wetland can be fully High planting densities also help design vegetation
inundated for a period of 1–2 weeks. This allows establish rapidly and propagate quickly to the point
sufficient time for sedimentation, assisted by the added where weeds find it difficult to establish.
gypsum, if necessary, to ensure that the water is
relatively clear. It will also give time for nutrient cycling If a wetland becomes weed-infested, any herbicides
within the water body to reach an acceptable level of used must be are carefully selected to avoid potential
equilibrium. Vegetation planting must start immediately impact on downstream ecosystems. Herbicides should
after this inundation period because conditions will be be applied via painting onto the weeds rather than
favourable for algal growth, increasing the threat of an spraying. It should be done during autumn when the
algal bloom. weeds may be senescing. Weed spraying and any use of
chemicals should be undertaken by staff with relevant
training and certification such as a Chemcert certificate.
4.5.7 Watering
Regular watering during plant establishment is essential Mulching of the batter, embankments and littoral banks
to retain a muddy substrate in the shallow marsh and can occur, but must consider the risk that conventional
ephemeral sections of the wetland. The frequency of surface mulches such as tanbark will float. Adopting high
watering is dependent on rainfall, the maturity of plant planting density rates and, if necessary, applying a
stock and the water-holding capacity of the soil. A suitable biodegradable erosion control matting to the
watering program should be established to suit the site wetland batters will help to combat weed invasion. If
conditions. The following guidance provides a starting mulch is used on the littoral zones, it must be secured in
point for the irrigation program: place with appropriate organic mesh or netting (local
authority approval may be required to use netting).
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 131
4.5.9 Bird protection 4.6 Managing sediment during the
During the early stages of wetland establishment, water building phase
birds can be a major problem as they may pull out
recently plantings. Interlocking planting systems, where 4.6.1 Managing sediment
several plants are grown together in a single container The inflow of sediment-laden runoff to a macrophyte
such as ‘floral edges’, can be an effective solution. Water zone is a risk to the successful establishment and long-
birds find it difficult to lift the interlocking plants out of term function of constructed wetlands. Sediment can
the substrate unlike single plants grown in tubes. smother vegetation, change water depths in the
macrophyte zone and ‘muddy’ the water thus reducing
Another option is to install protective fencing such as
plant photosynthesis (i.e. drown plants). In some
para-webbing on the open water side of a planting to
constructed wetlands, the accumulation of sediment has
discourage the birds.
required a complete reconstruction of wetlands at
When establishing a new wetland, there is a small significant cost. Therefore, managing sediment during
window of opportunity before a water bird population the construction and establishment of wetlands is
establishes, making an efficient and successful plant- critical and involves:
out essential. Failure to take advantage of this window
• effective erosion and sediment control of civil
can make it difficult to vegetate.
construction and landscape establishment within the
catchment of the wetland in accordance with local
4.5.10 Measuring success government requirements and a recognised guideline,
The wetland planting is considered to be ‘established’ for example the Best Practice Erosion and Sediment
when the plants are robust and self-sustaining. Growth Control (IECA, 2008)
and maturity should be recorded through three-monthly
• effective erosion and sediment control during the
photo logs. Measurements of an established wetland
building phase in accordance with local government
are:
requirements
1. greater than 90% of plants surviving
• protecting the macrophyte zone from sediment-laden
2. 80% coverage of the macrophyte zone runoff while plants are establishing.
3. preferably more than one species per macrophyte Section 4.5.2 describes the challenges associated with
zone the different phases of development sites. Section 0
4. at least 5 plants/m2, but preferably 6–10 plants/m2 describes staged construction and establishment
methods available to manage these challenges.
5. an increase in plant height of at least 50% through the
establishment phase
4.6.2 Development phases
6. propagation is occurring with more than 2–3 stems and
In the context of a large development site, delivering
through seeding
wetlands and establishing vegetation can be challenging.
7. no weeds. The challenges are best described against each typical
phase in the development of a greenfield or infill
development (see Figure 4.4):
132 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
Importantly, all works undertaken during subdivision
construction are ‘controlled’ through a principal
contractor and site manager. This means the risks can be
managed through appropriate guidance and supervision
and the implementation of appropriate erosion and
sediment controls.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 133
4.7 Staged construction Table 4.4 summarises the issues and considerations
and establishment methods of each option. This will allow local authorities,
developers, designers and contractors to select
To overcome the challenges associated with delivering
the method most suited to their site.
constructed wetlands, one of two options for staged
construction and establishment is recommended:
Description Construct wetland and disconnect inlet pond from Install wetland hydraulic structures and
macrophyte zone during the building phase. This bulk out the system. Allow the system to
allows the macrophyte zone vegetation to operate as a sediment basin during building
establish during building. When building in the phase. When building in the catchment is
catchment is 80–90%, then the inlet pond is 80–90% complete, clean the inlet pond and
cleaned and disconnection removed. macrophyte zone, install the topsoil and
plant and establish vegetation.
Order of construction Following sequence outlined in Section 4.7. Following sequence outlined in Section 4.8.
Advantages Allows early establishment of vegetation early. Wetland is not constructed until after the
building phases, so there are no sediment
Protects vegetation.
issues.
High amenity.
There is a high level of protection to the
Allows early handover of asset to Council. receiving environment.
Disadvantages There is moderate protection to the receiving It offers poor landscape amenity.
environment (inlet zone removes coarse
Delay in construction results in a long
sediment, but only down to 125um).
period before asset handover.
Preferred construction
and establishment
method:
Streetscape X
134 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
4.7.1 Option 1: Bypass flows and early - The disconnection to remain in place to ensure the
establishment of vegetation majority of flows from the catchment continue to
bypass the macrophyte zone allowing wetland plants
To reduce the risk of damage and the cost of re-
to reach full maturity without the risk of being
establishment, the civil works associated with the
smothered. The macrophyte zone can be fully
wetlands can be undertaken and temporary protective
commissioned and be ready for operation when the
measures installed to prevent smothering the
building phase is complete.
macrophytes during the building phase (see Figure 4.6).
This involves: • Stage 3 Landscape Establishment (inlet pond) — When
80–90% of the building phase is complete, clean the
• Stage 1 Civil Works — Disconnect the inlet zone from
inlet zone of accumulated sediment, remove the
the macrophyte zone so stormwater is diverted to the
disconnection between the inlet zone and macrophyte
high-flow bypass protecting the macrophyte zone
zone, and allow the constructed wetland to operate in
from excessive sediment loads:
accordance with the design.
- complete bulk earthworks and install hydraulic
As illustrated in Figure 4.7, Option 1 means that very
structures
little landscape establishment is required once the
- create and stabilise the inlet zone and high-flow building phase is complete. The asset can be handed
bypass over in a mature state immediately.
- block the inlet zone connection and divert
stormwater to the high-flow bypass
- complete the civil works.
• Stage 2 Building Phase Protection and Stage 3
Landscape Establishment simultaneously:
- With the macrophyte zone isolated from stormwater
inflows, plant establishment can occur in
macrophyte zone.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 135
Figure 4.7: Stages of construction and establishment of a constructed wetland
(amended from Leinster, 2006)
136 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
4.8 Step-by-step sequence — Option 1
The following sections provide a step-by-step sequence for civil construction, building phase protection and
landscape establishment for the Staged Construction and Establishment Option 1. Detailed descriptions and, where
available, photos are provided for each step in tabular format. It is envisaged the tables will be laminated and used
as an on-site reference during construction and establishment.
STEP 1: Pre-start meeting Hold a pre-start meeting with the wetland designer, ecologist, civil engineer,
landscape architect, site supervisor, civil contractor, landscape contractor and,
where required, the Council compliance officer to:
STEP 2: Preparation Preparation for construction should occur at least 10–20 days before starting on
site. Preparation includes organising for the hydraulic structures to be fabricated or
supplied, organising the correct equipment to achieve required tolerances (Section
4.3.5), ensuring the topsoil is tested (Section 4.4.1) and identifying construction
137
138
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 3: Setting out Survey the wetland layout in accordance with the set-out plans.
STEP 4: Strip and stockpile topsoil Remove ground cover and strip topsoil. If the topsoil is to be used in the wetland,
on the bunds or the high-flow bypass, it must be tested (see Section 4.4.1) and
screened to remove coarse material and weed seeds.
STEP 5: Bulking out Undertake bulk earthworks including the macrophyte zone, inlet pond, high-flow
bypass and surrounds.
STEP 6: Trimming and profiling Trimming and profiling of earthworks levels must allow for 300 mm of topsoil to
form the final design levels within the wetland and on batters or bunds. The
design levels for the wetland are INCLUSIVE of topsoil, so an additional 300 mm
of excavation below the design levels is required during bulk earthworks (refer
Section 4.3.4).
If an impervious liner is specified in the design, the excavation must allow for this
as well (refer Section 4.3.3). For example, if a clay liner of 300 mm is specified, in
the design, excavation of an additional 300 mm (total of 600 mm when
considering topsoil) will need to occur within the wetland.
STEP 7: HOLD POINT Inspection and sign-off Following completion of the bulking, the site superintendent and wetland
(Form A) designer will inspect the wetland with the contractor and review the bulked-out
system. Where appropriate, the as-constructed survey can be reviewed as part
of the inspection. However, the as-constructed survey of the final topsoil levels
is the critical requirement. If the construction meets the design requirements,
Sign-Off Form A will be completed and signed with photos attached, together
with the as-constructed survey if it was collected.
STEP 8: Install impervious liner (where required) Install the impervious liner to design and supplier specifications. It is critical
that the liner is sealed and geotechnical certification of the liner is obtained
(refer Section 4.3.3).
STEP 9: Placement of key wetland bunds Construct the earth bunds between the inlet pond and macrophyte zone of the
wetland and between the wetland and the lake, including a clay core within the
bunds. Compact the bunds, including the top of the bund, to ensure it retains
water in the wetland. Geotechnical certification of the liner must be obtained
outlining that the bunds will hold water (refer Section 4.3.3).
STEP 10: HOLD POINT Inspection and sign-off After placement of the liner and the bunds, the site superintendent and wetland
(Form B) designer will inspect the wetland with the contractor and review the system.
Where required, the geotech specialist will also attend the inspection. As a
minimum, the geotechnical certification must be reviewed as part of the
inspection.
STEP 11: Install hydraulic and functional Construct all hydraulic, functional and structural elements of the wetland.
structures This includes, but is not limited to:
• outlet riser
• bypass weir
• rock protection
• maintenance access.
Construction of the hydraulic, functional and structural elements should meet the
tolerances outlined in Section 4.3.5. The as-constructed survey is required at this
stage for each of the elements.
STEP 12: HOLD POINT Inspection and sign-off Following collection of the as-constructed survey, the site superintendent and
(Form C) wetland designer will inspect the hydraulic and functional structures with the
contractor, review the as-constructed survey and take photos. If the construction
STEP 13: Topsoil placement and profiling to final A suitable source of topsoil will have been identified in Step 2 and tested in
levels accordance with Section 4.4.1. If necessary, add gypsum to the topsoil and install
topsoil to a minimum depth of 300 mm.
Profile the topsoil using a ‘pozitrack’ bobcat with a spreader bar to achieve the final
wetland design levels in accordance with the tolerances in Section 4.3.5. The design
levels through the macrophyte zone must be achieved to within 50 mm and will often
require a number of profiling steps to achieve the required levels.
The as-constructed survey of the final topsoil levels through the entire wetland, in
particular the macrophyte zone, will be required. Superimpose this survey on the
original design for the site superintendent and wetland designer.
STEP 14: HOLD POINT Inspection and sign-off Following collection of the as-constructed survey, the site superintendent and
(Form D) wetland designer will inspect the topsoil and final levels through the wetland with
the contractor, review the as-constructed survey and take photos. If the
construction meets the tolerances outlined Section 4.3.5, and conforms with the
design, Sign-Off Form D will be completed and signed with the as-constructed
survey and photos attached.
Table 4.6: Building phase protection (Stage 2) and landscape establishment (Stage 3a) step-by-step sequence — Option 1
STEP 15: Disconnect the inlet zone from the To allow vegetation to establish within the macrophyte zone, exclude sediment-
macrophyte zone laden runoff from the zone and manipulate the water level. This is only a temporary
measure achieved by blocking the connection between the inlet zone (pond) and the
macrophyte zone. However, include a mechanism to open this connection for short
periods to slowly fill or flush the wetland when required. Place moveable steel plates
on the overflow pit in the inlet zone pit.
During this establishment period, all flows from minor and major storms will be
directed over the inlet zone bypass weir and into the bypass channel. The inlet pond
forms a sediment basin and may require desilting several times before
establishment.
STEP 16: Stabilise the high-flow bypass (vegetate Stabilise the high-flow bypass channel if it will receive flows during most rainfall
with turf) events while vegetation is establishing in the macrophyte zone. The high-flow
STEP 17: Install sediment fences Install sediment fences around the perimeter of the wetland to prevent sediment
entering from the batters and to keep construction vehicles off the wetland.
STEP 18: HOLD POINT Following installation of the temporary disconnection, bypass and protective layers,
Inspection and sign-off (Form E) the site superintendent and wetland designer will inspect the wetland with the
contractor and Sign-Off Form E can be completed and signed with photos attached.
PRACTICAL COMPLETION OF CIVIL WORKS & COMMENCEMENT OF STAGE 3 LANDSCAPE WORKS (i.e. with the protective measures in place the macrophyte zone can be established)
STEP 19: Pre-start and plant set-out meeting Before landscape works and wetland planting start, hold a pre-start and plant
set-out meeting with the wetland designers, including an ecologist, the site
superintendent and the landscape contractors. Confirm design and planting
requirements and set out the planting to ensure the correct plants are installed in
the correct locations.
STEP 20: Installation of hardscapes Install pathways and boardwalks according to the design and certified by the
landscape architects and engineers.
STEP 21: Mulch batters Mulch the batters of the wetland that are above the top of extended detention and
place a sediment fence on the downslope side of the mulch for batters that are
steeper than 1 in 4. Mulch should be suitably secured with organic netting or other
measures to avoid it floating into the wetland.
STEP 22: Flooding of macrophyte zone Partially open the disconnection between the inlet zone and macrophyte zone to
allow the macrophyte zone to fill with stormwater. Fully inundate the wetland for a
period of, say, 1–2 weeks. This allows sufficient time for sedimentation, assisted by
the gypsum, to ensure that the water is relatively clear and that nutrient cycling
within the water body reaches an acceptable equilibrium. Commence vegetation
planting immediately after this inundation period.
STEP 23: Inspection of plant tubestock As part of Step 2, plants should have been procured. Instruct the landscape
contractor and wetland designer to inspect the tubestock before it is delivered to
ensure the requirements outlined in Section 4.4.3 are met.
STEP 24: Plant substitutions If any plants have been replaced with a species other than those specified on the
design, confirm with the wetland designers prior to ordering. Any changes to plant
species or numbers of plants must be recorded in the as-constructed landscape
plans.
STEP 25: Planting Plant the tubestock is planted in accordance with the design species, densities and
setout ensuring the root ball is covered with topsoil and the stem is sitting above the
topsoil.
STEP 26: Inspection and sign-off (Form F) After planting, the site superintendent and wetland designer will inspect the
PRACTICAL COMPLETION wetland with the contractor and Sign-Off Form F will be completed and signed with
photos attached.
STEP 27: Water level control Ideally, wetland plants should be established in a mudflat environment. Therefore,
manipulate the water level in the macrophyte zone in the early stages of vegetation
growth. The maximum water level should be half the height of the wetland plants and
it must not exceed two-thirds of the height of wetland plants to avoid stress and
drowning, particularly in winter. The deep marsh species will dictate the depth.
Therefore, lower the water level by at least 300 mm during establishment. Water the
dryer planting zones regularly to sustain a mudflat environment during
establishment.
If lowering of the macrophyte zone via a valve is not possible, pump out will be
required.
STEP 28: Watering Wetland plants should be established in a mudflat environment. Water the dryer
parts of the wetland (shallow marsh, ephemeral and littoral zones) while the water
level in the wetland is low. Water the plants according to in Section 4.4.7:
If there is no rain, each plant should receive 2.5–5 litres of water per week (40 mm
per week minimum during establishment).
STEP 29: Weeding Inspect wetland plants fortnightly, removing any weeds by hand.
STEP 30: Establish normal water level Fill the wetland to its normal operating water level when the plants are mature and
tall enough to endure deeper water. It typically takes 3–4 months, depending on the
season, for plants to reach this level of maturity.
Temporarily open the connection between the inlet pond and the macrophyte zone
to fill the wetland to normal operating water levels. Once filled, close off the
connection between the inlet pond and the macrophyte zone to allow for a further
period of plant establishment with limited water-level variation.
- no weeds.
Record growth and maturity through three-monthly photo logs every 500m2.
STEP 31: Inspection and sign-off (Form G) Following establishment of plants and normal water level in the macrophyte zone,
the site superintendent and wetland designer will inspect the basin and complete
PRACTICAL COMPLETION OF LANDSCAPE WORKS. The system continues to establish while most stormwater events during the building phase pass through the inlet zone and bypass the
wetland macrophyte zone. At the end of the building phase the macrophyte zone in the wetland will be fully established with mature vegetation and ready for operation. The only component
left to establish is the inlet zone. Inspect wetland plants fortnightly, removing any weeds by hand.
STEP 32: On-going inspection and final landscape Inspect wetland plants fortnightly during establishment, removing any
establishment weeds by hand. Monitor the establishment of plants until they are robust
and self-sustaining.
4.8.3 Stage 3 — Landscape establishment (inlet zone only)
At the end of the building phase, the macrophyte zone in the wetland will be fully established with mature vegetation
and be ready for operation. The only component left to establish is the inlet zone. When 80–90% of the building is
complete, the inlet zone is de-silted, the disconnection between the inlet zone and macrophyte zone is removed and
the constructed wetland is allowed to operate in accordance with the design.
The recommended landscape establishment sequence for the inlet pond is summarised in Table 4.7. The
establishment sequence should be read in combination with the Constructed Wetlands Construction and
Establishment Sign-Off Forms.
Table 4.7: Landscape establishment of inlet pond (Stage 3b) step-by-step sequence — Option 1
STEP 28: Pre-start and plant set-out meeting Before final establishment of the inlet zone, hold a pre-start meeting between the
wetland designers, including an ecologist, the site superintendent and landscape
contractors. The meeting will confirm cleanout and planting establishment
requirements.
STEP 29: Clean out the inlet zone or pond Remove accumulated sediment and gross litter from the inlet zone or pond down to
the concrete or rock base.
STEP 30: Soil preparation Place topsoil to a depth of 300 mm in the inlet zone from the batters to a depth of
500 mm below the water level for planting.
STEP 31: Remove disconnection between inlet Remove the disconnection between the inlet zone and macrophyte zone so the
zone and macrophyte zone wetland macrophyte zone will be fully engaged.
STEP 33: Inspection and sign-off (Form H) Following installation of the mulch and plants, the site superintendent and wetland
designer will inspect the inlet zone with the contractor and Sign-Off Form H will be
completed and signed with photos attached.
147
148
4.9 Step-by-step sequence — Option 2
The following sections provide a step-by-step sequence for civil construction, building phase protection and
landscape establishment for the Staged Construction and Establishment Option 2. Detailed descriptions and, where
available, photos are provided for each step in tabular format. It is envisaged the tables will be laminated and used
as an on-site reference during construction and establishment.
STEP 1: Pre-start meeting Hold a pre-start meeting with the wetland designer, ecologist, civil engineer,
landscape architect, site supervisor, civil contractor, landscape contractor, and
where, required the Council compliance officer to:
STEP 2: Preparation Preparation for construction should occur at least 10–20 days before starting on
site. Preparation includes organising for the hydraulic structures to be fabricated or
supplied, organising the correct equipment to achieve required tolerances (Section
STEP 3: Setting out Survey the wetland layout in accordance with the set-out plans.
STEP 4: Strip and stockpile topsoil Remove ground cover and strip topsoil. If the topsoil is to be used in the wetland, on
the bunds or high-flow bypass, it must be tested (see Section 4.4.1) and screened to
remove coarse material and weed seeds.
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 5: Bulking out Undertake bulk earthworks including the macrophyte zone, inlet pond, high-flow
bypass and surrounds.
STEP 6: Trimming and profiling Trimming and profiling of earthworks levels need to allow for of 300 mm of topsoil
to form the final design levels within the wetland and on batters or bunds. The
design levels for the wetland are INCLUSIVE of topsoil, so an additional 300 mm of
excavation below the design levels is required during bulk earthworks (refer Section
4.4.1).
If an impervious liner is specified in the design, the excavation must allow for this as
well (refer Section 4.3.3). For example, if a clay liner of 300 mm is specified in the
design, excavation of an additional 300 mm (total of 600 mm when considering
topsoil) will need to occur within the wetland.
STEP 7: HOLD POINT Inspection and sign-off Following completion of the bulking, the site superintendent and wetland designer
(Form A) will inspect the wetland with the contractor and review the bulked-out system.
Where appropriate, the as-constructed survey can be reviewed as part of the
inspection. However, the as-constructed survey of the final topsoil levels is the
critical requirement. If the construction meets the design requirements, Sign-Off
Form A will be completed and signed with photos attached, together with the
as-constructed survey if it was collected.
STEP 8: Install impervious liner (where required) Install the impervious liner to design and supplier specifications. It is critical that
the liner is sealed and geotechnical certification of the liner is obtained (refer
149
150
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 9: Placement of key wetland bunds Construct the earth bunds between the inlet pond and macrophyte zone of the
wetland and between the wetland and the lake, including a clay core within the
bunds. Compact the bunds, including the top of the bund, to ensure it retains water
in the wetland. Geotechnical certification of the liner must be obtained outlining
that the bunds will hold water (refer Section 4.3.3).
STEP 10: HOLD POINT Inspection and sign-off After placement of the liner and the bunds, the site superintendent and wetland
(Form B) designer will inspect the wetland with the contractor and review the system. Where
required, the geotech specialist will also attend the inspection.
As a minimum, the geotechnical certification must be reviewed as part
of the inspection.
STEP 11: Install hydraulic and functional Construct all hydraulic, functional and structural elements of the wetland.
structures This includes, but is not limited to:
- outlet riser
- bypass weir
- maintenance access.
Construction of the hydraulic, functional and structural elements should meet the
tolerances outlined in Section 4.3.5. The as-constructed survey is required at this
stage for each of the elements.
CONSTRUCT ION STEP ACTIV IT Y PHOTOS
STEP 12: HOLD POINT Inspection and sign-off Following collection of the as-constructed survey, the site superintendent and
(Form C) wetland designer will inspect the hydraulic and functional structures with the
contractor, review the as-constructed survey and take photos. If the construction
meets the tolerances outlined in Section 4.3.5 and conforms with the design,
Sign-Off Form C will be completed and signed with the as-constructed survey and
photos attached.
PRACTICAL COMPLETION OF STAGE 1 CIVIL WORKS: The ‘bulked out’ constructed wetland operates as a sedimentation basin during the building phase of development. At the end of the
building phase (80–90% completion of the building) the wetland is cleaned out and civil works completed and landscape established.
Table 4.9: Civil construction and landscape establishment step-by-step sequence — Option 2
STEP 13: Clean out the macrophyte zone and inlet Remove accumulated sediment and gross litter from the inlet zone or pond and the
zone or pond macrophyte zone.
STEP 14: Check liner and hydraulic structures The impervious liner should be reassessed at this stage (or installation delayed to
this step) to ensure it conforms with the requirements of Section 4.3.3. Additionally,
the hydraulic structures should be inspected for damage or movement.
STEP 15: Topsoil placement and profiling to final A suitable source of topsoil will have been identified in Step 2 and tested in
levels accordance with Section 4.4.1. If necessary, add gypsum to the topsoil and install
topsoil to a minimum depth of 300 mm.
Profile the topsoil using a ‘pozitrack’ bobcat with a spreader bar to achieve the final
wetland design levels in accordance with the tolerances in Section 4.3.5. The design
The as-constructed survey of the final topsoil levels through the entire wetland, in
particular the macrophyte zone, will be required. Superimpose this survey on the
original design for the site superintendent and wetland designer.
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 16: HOLD POINT Inspection and sign-off Following collection of the as-constructed survey, the site superintendent and
(Form D) wetland designer will inspect the topsoil and final levels through the wetland with
the contractor, review the as-constructed survey and take photos. If the
construction meets the tolerances outlined Section 4.3.5 and conforms with the
design, Sign-Off Form D will be completed and signed with the as-constructed
survey and photos attached.
STEP 17: Disconnect the inlet zone from the To allow vegetation to establish within the macrophyte zone, exclude sediment-
macrophyte zone laden runoff from the zone and manipulate the water level. This is only a temporary
measure achieved by blocking the connection between the inlet zone (pond) and the
macrophyte zone. However, include a mechanism to open this connection for short
periods to slowly fill or flush the wetland when required. Place moveable steel plates
on the overflow pit in the inlet zone pit.
During this establishment period, all flows from minor and major storms will be
directed over the inlet zone bypass weir and into the bypass channel. The inlet pond
forms a sediment basin and may require desilting several times before
establishment.
STEP 18: Stabilise the high-flow bypass Stabilise the high-flow bypass channel if it will receive flows during most rainfall
(vegetate with turf) events while vegetation is establishing in the macrophyte zone. The high-flow
bypass channel can be stabilised with turf, or reinforced turf, placed perpendicular
to the flow and pinned down.
STEP 19: Install sediment fences Install sediment fences around the perimeter of the wetland to prevent sediment
entering from the batters and to keep construction vehicles off the wetland.
STEP 20: HOLD POINT Inspection and sign-off Following installation of the temporary disconnection, bypass and protective layers,
(Form E) the site superintendent and wetland designer will inspect the wetland with the
contractor and Sign-Off Form E can be completed and signed with photos attached.
STEP 21: Pre-start and plant set-out meeting Before landscape works and wetland planting start, hold a pre-start and plant
(landscape establishment) set-out meeting with the wetlands designers including an ecologist, the site
superintendent and the landscape contractors. Confirm design and planting
requirements and set out the planting to ensure the correct plants are installed in
the correct locations.
STEP 22: Installation of hardscapes Install pathways and boardwalks according to the design and certified by the
landscape architects and engineers.
STEP 23: Mulch batters Mulch the batters of the wetland that are above the top of the extended detention
and place a sediment fence on the downslope side of the mulch for batters that are
STEP 24: Flooding of macrophyte zone Partially open the disconnection between the inlet zone and macrophyte zone to
allow the macrophyte zone to fill with stormwater. Fully inundate the wetland for a
period of say 1–2 weeks. This allows sufficient time for sedimentation, assisted by
the gypsum, to ensure that the water is relatively clear and that nutrient cycling
within the water body reaches an acceptable equilibrium. Commence vegetation
planting immediately after this inundation period.
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 25: Inspection of plant tubestock As part of Step 2, plants should have been procured. Instruct the landscape
contractor and wetland designer to inspect the tubestock before it is delivered to
ensure the requirements outlined in Section 4.4.3 are met.
STEP 26: Plant substitutions If any plants have been replaced with a species other than those specified on the
design, confirm with the wetland designers prior to ordering. Any changes to plant
species or numbers of plants must be recorded on the as-constructed landscape
plans.
STEP 27: Planting Plant the tubestock in accordance with the design specifications, densities and
setout ensuring the root ball is covered with topsoil and the stem is sitting above the
topsoil.
STEP 28: Inspection and sign-off (Form F) After planting, the site superintendent and wetland designer will inspect the wetland
PRACTICAL COMPLETION with the contractor and Sign-Off Form F will be completed and signed with photos
attached.
STEP 29: Water level control Ideally, wetland plants should be established in a mudflat environment. Therefore,
manipulate the water level in the macrophyte zone in the early stages of vegetation
growth. The maximum water level should be half the height of the wetland plants and
it must not exceed two-thirds of the height of wetland plants, to avoid stress and
drowning, particularly in winter. The deep marsh species will dictate the depth.
Therefore, lower the water level by at least 300 mm during establishment. Water the
If lowering of the macrophyte zone via a valve is not possible, pump out
will be required.
155
156
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 30: Watering Wetland plants should be established in a mudflat environment. Water the dryer
parts of the wetland (shallow marsh, ephemeral and littoral zones) while the water
level in the wetland is low. Water the plants according to in Section 4.4.7:
If there is no rain, each plant should receive 2.5–5 litres of water per week.
STEP 31: Weeding Inspect wetland plants fortnightly, removing any weeds by hand.
STEP 32: Remove disconnection between inlet Remove the disconnection between the inlet zone and macrophyte zone so the
zone and macrophyte zone wetland macrophyte zone will be fully engaged.
STEP 32: Establish normal water level Fill the wetland to its normal operating water level when the plants are mature and
tall enough to endure deeper water. It typically takes 3–4 months, depending on
season, for plants to reach this level of maturity.
Temporarily open the connection between the inlet pond and the macrophyte zone
to fill the wetland to normal operating water levels. Once filled, close off the
connection between the inlet pond and the macrophyte zone to allow for a further
period of plant establishment with limited water-level variation.
- no weeds.
Record growth and maturity through three-monthly photo logs every 500 m2.
CONSTRUCT ION STEP ACTI VI TY PHOTOS
STEP 33: Inspection and sign-off (Form G) Following establishment of plants and normal water level in the macrophyte zone,
the site superintendent and wetland designer will inspect the basin and complete
Sign-Off Form G with attached photos.
STEP 34: On-going inspection and final landscape Inspect wetland plants fortnightly during establishment, removing any weeds by
establishment hand. Monitor the establishment of plants until they are robust and self-sustaining.
Table 4.10: Potential failure scenarios for constructed wetlands and rectification actions
Failure of wetland plants if open water The depths through the macrophyte zone are too deep causing Lower the normal water level in the wetland by changing the riser
covers more than 30% of the macrophyte ‘drowning’ of wetland plants. Wetland plants will not survive long outlet levels.
zone area term in depths of greater then 0.5 m and will generally begin to die
If it is not possible to lower the water levels in the wetland due to
out after about two years.
level constraints at the outfall, then drain the wetland and add
topsoil to reduce depths. The final wetland depths should be
between 0.5 m below the normal level to 0.2 m above the normal
water level.
The water level in the macrophyte zone is above the normal water Change the outlet riser to reduce notional detention time in the
level for long periods thus drowning the plants because: wetland. In South East Queensland, the preferred notional detention
time is 48 hours.
- the notional detention time in the wetland is too long
- the wetland is small in relation to the catchment with low Lower the wetland water level below the normal level to allow the
plants to re-establish.
hydrologic effectiveness.
Blocked riser outlet. Clean the outlet riser and inspect regularly.
DEFECT OR FAILURE CAU SES RECTIFICATION
Poor topsoil. The quality of topsoil used in the wetland should have been
confirmed through the construction and establishment process and
Sign-Off Form D. If topsoil is considered to be the cause of plant
loss, then soil one sample per 250–500 m2 should be collected and
tested in accordance with AS4419. If the testing finds the presence
of poor topsoil, then the soils should be ameliorated to support plant
growth or replaced.
Ponding of water in isolated pools that may Poor topsoil trimming or footmarks. Fill isolated pools with topsoil and plant out.
support mosquitoes Ensure the finished surface is level.
Scour of wetland vegetation Where the flows entering the macrophyte zone from the inlet pond Retrofit an energy dissipation system at the outlet of the connection
are large, local velocities maybe be high resulting in scour of the pipe to the macrophyte zone. Seek advice from a stormwater
vegetation if appropriate energy dissipation is not provided in the engineer.
design.
Scour of inlet pond Where flow exits the pipe system to the inlet pond, there is a risk of Rectify scour, provide rock protection to outlet and, where
scour where rock protection is not provided. appropriate, plant out.
Scour around high-flow bypass weir If the weir crest and grouted rock protection is not extended up the Extend the concrete weir crest and grouted rock batters up the
batters of the wetland and the high-flow bypass channel, scour can batters to at least 0.5 m above the weir invert.
occur around the edge of the weir and flows will skirt the weir.
Scour within high-flow bypass channel Where this is constructed with a moderate grade along the high-flow Rectify scour, provide rock protection to outlet and, where
bypass, scour can occur as a result of high velocity. appropriate, plant out.
Scour of wetland batters Lateral surface flows entering the wetland from the small catchment Direct lateral flows to small, rock-lined channels that feed down the
directly adjacent to wetland. batters to the wetland. Rectify and plant out scoured zones.
Failure of the wetland bunds Failure of the bunds can occur through a number of scour and Rectify scour and ensure geotech certification of the bund for
overflow mechanisms or due to the bunds being constructed too low stability and water-hold capacity. Where required, raise the bund
or scour along outlet pipes. well above the top of the potential flood levels in the wetland and
provide rock protection in high velocity locations.
Leaking wetland The wetland liner was constructed incorrectly or has been damaged Drain the wetland, inspect for evidence of damage in open water
resulting in either water losses or groundwater infiltration. zones, and seek advice from a geotechnical consultant. Application
of bentonite clay may assist in blocking a leak.
Failure of the seepage collars around the wetland pipe outlets. Drain the wetland and expose the outlet pipe and seepage collar.
Repair or install seepage collars as directed by the wetland designer
(typically 500 m around pipe).
Civil certification Site (civil) Constructed wetland designer’s certification of functional elements
superintendent
Civil engineer’s certification of structural elements
Landscape Site (landscape) Constructed wetland designer’s or ecologist’s certification of plant species
certification superintendent
As-constructed drawings showing final species and plant numbers
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 161
4.12 Compliance The tender and contract documents can simply refer to
Compliance of constructed wetlands represents a major the relevant sections of these guidelines. If the Sign-Off
challenge for local authorities. Given that the systems form requirements are not achieved, then the contract is
are essentially civil infrastructure with a landscape not fulfilled and payment is withheld.
overlay, the responsibility for compliance and asset
handover has not been well defined. Most local 4.13.2 Ownership and handover
authorities have different approaches for dealing with A common problem with the construction and
these issues, which has resulted in confusion within the establishment of WSUD systems is ownership and
industry. maintenance during both the handover of the asset from
the civil contractor to the landscape contractor and the
The Construction and Establishment Sign-Off Forms
building phase maintenance. These issues must be
attached to this guideline and the certification
considered when establishing the contracts:
requirements outlined in Section 4.10 provide the basis
for compliance. To support the final compliance • Handover from the civil contractor to the landscape
inspection and practical completion, the following contractor — This handover process can take months
documentation is required: to occur for a number of reasons, such as separate
operational works approval processes for landscape
• completed Construction and Establishment Sign-Off
design. The wetland may remain un-vegetated and
Forms
unmanaged during this period. Sediment accumulation
• as-constructed survey and photos (as per Sign-Off and damage will occur during rainfall events and
Form requirements) maintenance or rectification will be required.
• site superintendent certification If there will be a delay between the civil works and
• wetland designer certification. landscape works, then it is recommended a
maintenance contract is established (or maintenance
It is also recommended that compliance inspection is
allowance is made in the civil contract) for inspection,
undertaken at the following hold points:
cleanout and rectification of the civil works during this
• pre-start meeting period. This could be costed as a monthly allowance or
• practical completion (on-maintenance) of civil works on a per inspection or per maintenance event basis. It
(Sign-Off Forms A, B, C, D and E are complete) is recommended the civil contractor is responsible for
this work and the contract reflects the inspection and
• practical completion (on-maintenance) of landscape
maintenance requirements.
works (Sign-Off Form F)
• Building phase maintenance — During the building
• final inspection following landscape establishment
phase sediment accumulation and damage will occur.
(Sign-Off Form G).
It is important that regular inspections are made
after rainfall events and that appropriate cleanout
4.13 Civil and landscape contracts
or rectification is undertaken. It is recommended a
4.13.1 Contracts maintenance contract is established for this purpose.
To ensure all parties involved in the construction and The maintenance contract could be costed as a
establishment of the constructed wetland are aware of monthly allowance or on a per inspection or per
the certification requirements and the associated maintenance event basis and the work can be
Construction and Establishment Sign-Off Forms, the undertaken by the civil or landscape contractor or a
Tender and Civil and Landscape Contracts must include maintenance contractor. Once 80–90% of the building
the following: is complete, the maintenance contract would cease
and landscape works would commence.
• the construction and establishment specifications
provided in Sections 4.4 and 4.5 of these guidelines
• the preferred construction and establishment method
(see Section 4.7)
• Sign-Off Forms with the as-constructed survey and
drawing requirements
• the certification requirements listed in Table 4.11.
162 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
4.14 Sign-Off Forms
The Construction and Establishment Sign-Off Forms
outline the key items to be reviewed when delivering and
inspecting constructed wetlands. The Sign-Off Forms
follow the construction method described in Sections
4.7 to 4.8. The forms are to be used by contractors,
construction site supervisors, designers and local
authority compliance officers to ensure all the elements
of the constructed wetland have been constructed in
accordance with the design. If an item receives an ‘N’ in
the ‘Satisfactory’ criteria, indicating that elements are
not satisfactory, actions must be specified and delivered
to rectify the construction issue before final inspection
sign-off is given.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 163
CONSTRUCTED WETLAND CONSTRUCTION & ESTABLISHMENT SIGN-OFF FORMS
Wetland location:
Developer
Site superintendent
(landscape)
Wetland designer
Civil engineer
Landscape architect
Civil contractor
Landscape contractor
Pre-Start Meeting
164 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
PRE-START MEETING
Pre-starting attendees to be listed and sign that that have attended and understand the design intent, construction and
establishment process.
Location
Date
Developer
Site
superintendent(landscape)
Wetland designer
Civil engineer
Landscape architect
Civil contractor
Landscape contractor
Other
Other
Other
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 165
FORM A — EARTHWORKS BULKING OUT AND PROFILING
Purpose: To ensure earthworks bulking out, trimming and profiling is in accordance with design drawings and specifications
(allowance for 300 mm topsoil and, where required, minimum 300 mm of impervious liner).
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent and wetland designer inspection and sign-off before proceeding.
Date: Date:
166 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM B — BUNDS AND IMPERVIOUS LINER
Purpose: To ensure the bunds are installed and sealed and the impervious liner is constructed as per the specifications and the
test results verify this.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent or wetland designer inspection and sign-off before proceeding.
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 167
FORM C — HYDRAULIC AND FUNCTIONAL STRUCTURES
Purpose: To ensure that the hydraulic structures associated with the wetland are constructed in accordance with design and
specifications.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent AND Wetland Designer inspection and review of test results and certifications before proceeding.
Date: Date:
168 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM D — TOPSOIL AND FINISHED LEVELS
Purpose: To ensure the topsoil is installed to the correct depth and finished levels of wetland are correct and meet the design.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent and wetland designer inspection and sign-off before proceeding.
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 169
FORM E — BUILDING PHASE (MACROPHYTE) PROTECTION
Purpose: To ensure protective measures are correctly installed to protect the macrophyte zone during establishment while
building is occurring in the catchment.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent or wetland designer inspection and sign-off before proceeding.
Date: Date:
170 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM F — MACROPHYTE ZONE LANDSCAPE INSTALLATION
Purpose: To ensure the correct plants are supplied, installed and established.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 171
FORM G — MACROPHYTE ZONE LANDSCAPE ESTABLISHMENT
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
6. No weeds.
HOLD POINT: Superintendent and wetland designer inspection and sign-off before proceeding.
Date: Date:
172 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands
FORM H — INLET ZONE LANDSCAPE INSTALLATION AND ESTABLISHMENT
Purpose: To ensure the correct plants are supplied, installed and established.
ACTION (IF
ITEMS CHECKED SATISFACTORY INITIAL
UNSATISFACTORY)
HOLD POINT: Superintendent AND Wetland Designer inspection and sign-off before proceeding.
PLANT ESTABLISHMENT
Date: Date:
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 173
FIVE REFERENCES
Chapter 2 References
Australian Standards (2003), AS 4419-2003—Soils for Maroochy Shire Council (2007), Manual for Erosion and Sediment
landscaping and garden use. Control (Version 1.1). http://www.maroochy.qld.gov.au/
environment/sitePage.cfm?code=manual_sediment_erosion.
International Erosion Control Association (IECA) (2008)
Accessed 19 February 2009.
Best Practice Erosion and Sediment Control, International
Erosion Control association (Australasia), Picton NSW. South East Queensland Healthy Waterways Partnership
(SEQHWP) (2006), Water Sensitive Urban Design Technical
Leinster, S. (2006) ‘Delivering the Final Product — Establishing
Design Guidelines for South East Queensland. South East
Water Sensitive Urban Design Systems’, in A. Deletic and T.
Queensland Healthy Waterways Partnership, Brisbane.
Fletcher (eds), 7th International Conference on Urban Drainage
Modelling and 4th International Conference on Water Sensitive VicRoads (2004) Drainage of Subsurface Water from Roads
Urban Design Book of Proceedings, Volume 2, Melbourne. — Technical Bulletin No 32. http://webapps.vicroads.vic.gov.au/
VRNE/vrbscat.nsf/CatalogByCategory/886A25970B50E572CA2
Maroochy Shire Council (2007), Manual for Erosion and
56BF3000604DB?OpenDocument. Accessed 27 February 2009.
Sediment Control (Version 1.1). http://www.maroochy.qld.gov.
au/environment/sitePage.cfm?code=manual_sediment_
erosion. Accessed 19 February 2009. Chapter 4 References
Australian Standards (2003), AS 4419–Soils for landscaping
South East Queensland Healthy Waterways Partnership
and garden use.
(SEQHWP) (2006), Water Sensitive Urban Design Technical
Design Guidelines for South East Queensland, South East International Erosion Control Association (IECA, 2008),
Queensland Healthy Waterways Partnership, Brisbane. Best Practice Erosion and Sediment Control, International
Erosion Control association (Australasia), Picton NSW.
Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands 175
176 Construction and Establishment Guidelines: Swales, Bioretention Systems and Wetlands