Professional Documents
Culture Documents
ANS:
ANS:
Service rate = 3 minutes/call or 10 calls/30 minutes/CSR
Utilization(U)= Demand Rate/ [(Service Rate) (Number of Servers)]
0.80 = DR/ [(10 calls/30minutes/CSR) (3 CSRs)
Therefore, DR = (0.80) (30)
= 24 calls/30 minutes.
ANS:
Work in process = 6 (customers in check-out line)
Work in process (WIP) = Throughput * Flow Time
=R*T
6=R*3
Therefore,
R = 2 customers per minute or 120 customers per hour.
4.) A small assembly line for the assembly of power steering pumps
needs to be balanced. The precedence diagram is shown below. The
demand is forecasted to be 1600 units. The company operates for 8
hours every day and 5 days in a week.
How would the line be balanced using:
(a) Longest (largest) processing time first rule (you have done it in the
class session)?
(b) If you follow shortest (smallest) processing time rule, what will be the
assembly line balancing solution?
(c) Which solution you assess better, (a) or (b)?
ANS:
A) Assembly line balancing
Total time = 0.5 + 0.7 + 0.1 + 0.2 + 0.4 + 0.4 + 0.8 + 0.6 + 0.5 = 4.2 mins
Cycle time = (5 * 8 * 60)/1600 = 1.5 mins
Minimum number of workstations = Total Time/Cycle Time
= 4.2/1.5
= 2.8, approximately 3
Minimum number of workstations required are 3.
Workstation Tasks Total time Idle time
1 B, A, C, D 1.5 0
2 E, G 1.2 0.3
3 H, F, I 1.5 0
TOTAL 4.2 0.3
B) Total time = 0.5 + 0.7 + 0.1 + 0.2 + 0.4 + 0.4 + 0.8 + 0.6 + 0.5
= 4.2 mins
Cycle time = (5 * 8 * 60)/1600 = 1.5 mins
Minimum number of workstations = total time / cycle time
= 4.2/1.5
= 2.8, approximately 3
Minimum number of workstations required are 3.
ANS:
A)
Assembly time = 480 minutes per shift
Forecasted output rate = 60 units per shift
Cycle time = 480/60
= 8 minutes
Minimum no. of workstation = Sum of task times/ Cycle time
= 32/8
= 4
Assembly line
Workstation Tasks Total time Idle time
1 2 4 3 8 0
2 1 6 7 1
3 5 6 2
4 7 3 5
5 8 8 0
Total 32 8
6.)
7. A computer-system installation project consists of eight activities. The
immediate predecessors and activity times in weeks are shown below
A(6) C(2)
E(6)
F(3)
D(3)
H(3)
B(3)
G(9)
B (1) D(3)
A(3)
G(7) I(8)
C(2) E(5)
F(3) H(5)