The MRP Department has a problem.

Its computer “died” just as it spit out the following


information: Planned order release for item J27 = 640 units in week 2. The firm has been able
to reconstruct all the information they lost except the master schedule for end item 565. The
firm is fortunate because J27 is used only in 565s. Given the following product structure tree
and associated inventory status record information, determine what master schedule entry for
565 was exploded into the material requirements plan that killed the computer.