Professional Documents
Culture Documents
DOI 10.1007/s40098-017-0230-1
TECHNICAL NOTE
123
Indian Geotech J
123
Indian Geotech J
800 200.58 (FRL) 0 3 levels (3, 7 and 11 m from 7 14.2 from FRL
FRL)
600 4 m below FRL 4 2 levels (7 and 11 m from 6 14.2 from FRL
(196.58) FRL)
lateral wall movements than similar excavations made in present study aims to discuss a case study on deep exca-
homogeneous soil profiles. vation supported by diaphragm wall.
The application of a generalized effective stress soil
model, for predicting the performance of 22 m deep
excavations in the M1 pit near the Lehrter Bahnhof in Site Descriptions
central Berlin is described [4]. The behaviour of a 16-18 m
deep excavation for a metro station using cut-and-cover The site for the case study considered in the research work
technique in soft clay in the Shanghai metropolitan area is is located along Noida (India). The plot area of the pro-
studied [5] and concluded that the magnitudes of wall posed building is approximately 24,000 m2. The project
deflections, ground settlements and settlements of the includes the construction of Block 1 (G ? 13 floors) with
adjacent buildings and utilities were relatively small and three basements, Block 2 (G ? 13 floors) with three
less than the specified protection levels due to quick basements and Substation. Block 1 and 2 consists com-
excavation and rapid cast of rigid concrete floor slabs right bined basement of 3 levels. The three basement floors will
after the completion of excavation. be used as car parking and remaining all floors are to be
Though several researchers are working on various used as office space. The site investigation comprised of a
aspects of support system for deep excavation as men- series of 23 nos. deep borings in and around the footprint of
tioned in references [6–13], the reported work of case study the proposed building which extends to a depth of 30 m.
on support system for deep excavation is limited. Hence The site plan, along with boreholes and building location,
123
Indian Geotech J
diaphragm walls, and nearby existing structures of the stratigraphy at the site may be divided into three general-
present case study is shown in Fig. 1. Ground water ized strata as given in Table 1.
table was found to be around 6 m below the natural ground
level. The site is almost plain in topography with surface
elevation of 200.58 m. Detail study is made on all the 23 Support System for Deep Excavation
borelog data sheets and their respective laboratory test
results to prepare the generalised soil profile. During the excavation for the basement construction, the
Earlier the site was being used for agricultural purposes. diaphragm wall has been proposed to be supported by soil
The deposits at the site are alluvial in nature. The variation anchors (installed at two or three levels depending on the
of SPT N with depth for typical boreholes is shown in design requirement) as shown in Fig. 3. Initially the anal-
Fig. 2 and it reveals that SPT N values increases with ysis has been carried out by considering 600 mm thick
increase in depth irrespective of the type of soil. The diaphragm wall, two level of anchors and depth of
Table 3 Design soil parameters
Layers (m) Soil description Unit weight of soil Observed SPT ‘N’ value Young’s modulus Poissons ratio, l Friction angle, /
(kN/m3) (kN/m2) (degrees)
Top Bottom
Fig. 4 Schematic
representation of soil anchors
with failure plane
123
Indian Geotech J
embedment as 5 m below the excavation level and found wall based on the comparison between predicted and
that system is not safe. Then different options were anal- measured wall displacements during construction.
ysed by changing the thickness of diaphragm wall, number,
level and spacing of anchors, depth of embedment etc. and Analysis of Diaphragm Wall
finally adopted the safe and economical solution. The
details of diaphragm wall considered for execution are The analysis of diaphragm wall is divided into two phases.
summarised in Table 2. Embedment depth mentioned in The analysis of diaphragm wall supported by soil anchors
Table 2 is the depth of D-wall inserted into the ground in till the final excavation level is said to be Phase 1. Analysis
addition to the excavation depth. Though diaphragm wall of diaphragm wall by considering all the floor slabs in
of thickness 800 mm and 600 mm are adopted in the site, position is termed as Phase 2. Analysis of Phase 1 and 2
the design and performance of 800 mm thick diaphragm were carried out using PLAXIS 2D and STAAD Pro
wall is described in this paper. The main purpose of this software respectively. However, the diaphragm wall is
paper has been to assess the performance of the diaphragm designed as a flexural member for the worst case forces
2 2 2
4 4 4
6 6 6
Depth (m)
8 8 8
10 10 10
12 12 12
14 14 14
16 16 16
18 18 18
20 20 20
22 22 22
Towards Excavation Towards Excavation
123
Indian Geotech J
obtained from both the analysis. Brief description of basement area for lowering the ground water table to 1 m
analysis carried out using these two phases are described in below the bottom of excavation. Therefore no water pres-
Sects. 3.1.1 and 3.1.2. sure is considered for diaphragm wall analysis in this
phase. The excavation was carried out using three levels of
Phase 1: Analysis Using PLAXIS 2D soil anchor system for supporting 800 mm thick diaphragm
wall during the basement construction.
The soil parameters considered for PLAXIS analysis in Soil anchors are designed as pre-stressed anchors and
Phase 1 is shown in Table 3. the design is in accordance to BS 8081:1989 [16], IS:
A surcharge load of 20 kPa [14] is considered in addi- 10270 [17] and IS: 14268 [18] and The anchors are
tion to the earth pressure acting on the diaphragm wall. The designed for a design life of 2 years since the soil anchors
excavation has to be carried out in dry condition for the are designed to support the diaphragm wall till the final
construction activity and hence deep well dewatering sys- excavation level. Type C anchorage is adopted in the
tem [15] is proposed on both outside and inside the design. All the anchors shall be water tight and no leakage
123
Indian Geotech J
shall be allowed into the diaphragm wall. For the 800 mm Phase 2: Analysis Using STAAD Pro
thick diaphragm wall three levels of anchors are proposed
(viz. 3, 7 and 11 m from the NGL) at a horizontal spacing In Phase 2 analysis, the loads include self-weights and the
of 1.66 m c/c. Detailed design of soil anchors, determina- other downward load calculated based on the tributary area
tion of anchor lengths with failure wedge were carried out of the basement slabs depending upon the support system
for the present study. Refer Fig. 4 for the schematic rep- at the corresponding levels. At-rest earth pressure condition
resentation of soil anchors with failure plane. is considered behind the diaphragm wall along with the
Phase 1 analysis is carried out using PLAXIS 2D soft- surcharge of 20 kPa. The design water table level is con-
ware as a plane strain problem. In this analysis, the dia- sidered at ground level on soil side in this analysis.
phragm wall is modelled as plate element, soil anchors are In Phase 2 analysis, the diaphragm wall is modelled as a
modelled as node-to-node anchors and geo-grid elements 2D beam element of unit meter width on the out of plane
for free length and fixed length portion respectively. The direction. The soil resistance in the embedded portion of
soil behavior is modelled using Mohr–Coulomb model. the wall is modelled in the form of lateral springs up to the
The maximum total displacement of 50 mm occurs near embedment depth and with vertical spring support at the
the top of diaphragm wall and below the area of surcharge end. The earth pressure from the soil side is applied as
application. Stage wise analysis results of PLAXIS 2D horizontal loading with corresponding load intensity,
such as horizontal deflection, bending moment and shear including the lateral thrust due to vehicular loading and
force is shown in Fig. 5. As the excavation proceeded to ground water pressure. The diaphragm wall acts as a
lower levels, the diaphragm walls began to develop deep retaining wall and is restrained by basement slabs and
seated movements towards the excavation side. The values hence the diaphragm wall is not free to tilt. Therefore earth
of bending moment and shear force are reduced at the pressure at rest condition is considered in the design.
location of soil anchors. However maximum bending STAAD model for 800 mm thick diaphragm is shown in
moment and shear force occurs at the final excavation Fig. 6. Detailed load calculations, earth pressure calcula-
stage. tion for at rest condition and dynamic increment,
-1
-3 Basement slab
at -4.5m
-5
-7
Basement slab Diaphragm Wall
-9
at -9.0m
Depth (m)
-11
-13
Raft slab at
-15 -12.7m
-17
Fig. 7 Maximum and minimum bending moments and shear force for 800 mm thick diaphragm wall
123
Indian Geotech J
4
2nd level support
6
Depth below ground level (m)
12
Excavation level
14
16 E-79
Towards Excavation
N-52
18
N-21
20
Analysis Result
22
123
Indian Geotech J
and bending moment were considered irrespective of pos- responses are checked by field monitoring during the works
itive or negative sign. and contingency measures are implemented as and when
necessary. The deflections of the 800 mm thick diaphragm
walls were monitored using three inclinometers. Cross hole
Instrumentation sonic logging test is carried out to check the homogeneity
and integrity of concrete and Koden test is carried out to
As the deep excavation is made very close to buildings and accurately measure and record the shape of a drilled hole of
services, which require safeguarding against damage it was greater depth.
decided to adopt observational method where predicted
Fig. 9 CSL test graph for diaphragm wall panel number W-05 between tubes 1-2
123
Indian Geotech J
Inclinometer cage. The detailed test graphs received for diaphragm wall
panel number W-05 between tubes 1-2 is presented in
Digital inclinometer with portable and traversing probe Fig. 9.
system is used in the present study for monitoring lateral The following points can be concluded from cross hole
deformation. The predicted behavior of 800 mm thick sonic logging tests conducted on the diaphragm wall panel
diaphragm wall is compared with actual measured behavior no. W-05 based on data, diaphragm wall location and site
using three inclinometers. Figure 8 shows the comparison conditions at the time of testing.
plot between the predicted and actual horizontal displace-
• Diaphragm wall number W-05 shows minor defect for
ment profiles for 800 mm thick diaphragm walls after final
tube corridors 2-3 and 3-5.
level of excavation has reached. By the end of excavation
• The minor defect also seems likely to be reflection from
works for inclinometer E-79, the maximum deflection was
anchors as the locations match with the anchor
about 7 mm. Displacements observed in inclinometer N-52
locations.
was more, with a maximum of about 15 mm. Maximum
horizontal displacement in the other inclinometer N-21 was
still of greater magnitude (27 mm). Koden Test
The curves presented indicate that the numerical
behavior of the wall has a trend similar to that of the actual The Drilling Monitor system has been developed in com-
behavior measured using inclinometers. However, the pliance with the user’s needs arisen from the recent con-
actual realized movements are consequently below the struction environment to accurately measure and record the
predicted values this may be because of various reasons shape of a drilled hole of greater depth. It can be easily
like non homogeneity of soil, assumed design surcharge positioned and set up for measurement to provide quick
was not actually experienced in the site by the walls and so and accurate recordings of excavations. This monitoring is
on. done for every bite of all panels.
With the help of Koden ultrasonic echometer, both the
Cross Hole Sonic Logging Test three dimensional orientations and the actual dimensions of
a panel can be continuously checked. A typical log of panel
The field test of Cross-hole Sonic Logging (CSL) is number N-61 for the present case study is presented in
conducted in accordance with ASTM D6760-08 [19]. For Fig. 10 The vertical line ‘0’ bordered by two strips (X–X0 ),
conducting the sonic logging test five steel tubes of represents the vertical descent path of the probe. The trench
50 mm internal diameter were installed throughout the wall profile is shown by the inner borders of the dark strips.
length of the shaft by tying them to the reinforcement It is inferred that the vertical deviation of diaphragm wall
123
Indian Geotech J
panel number N-61 is 90 mm which is within the permis- geotechnical services team of L&T (B&F) for the help rendered in
sible limit 1 in 80 m. performing the analysis and for their great suggestions which sub-
stantially improved the presentation of this paper.
Conclusion References
This study focuses on the study of deep basement using 1. Clough G, Tsui Y (1974) Performance of tied-back walls in clay.
diaphragm wall. The 800 mm thick diaphragm wall was J Geotech Eng Div 10(12):1259–1273
monitored during the works using three digital inclinome- 2. Goh A (1990) Assessment of basal stability for braced excavation
system using finite element method. Comput Geotech
ters. The results from the observations have been used to 10(4):325–338
analyse the diaphragm wall response to various construc- 3. Gandhi SR, Suresh PK, Raju VS (1998) Lateral load tests on
tion and excavation activities. Observations from the large diameter bored pile and analysis. Indian Geotech Conf
monitoring results and the deduced diaphragm wall 1:373–377
4. Seo M, Olson SM, Yang KS, Kim M (2010) Sequential analysis
responses can be summarised as follows. of ground movements at three deep excavation sites with mixed
ground profiles. J Geotech Geoenviron Eng 136(5):656–668
1. Inclinometer measurements within the diaphragm 5. Nikolinakou MA, Whittle AJ, Savidis S, Schran U (2011) Pre-
walls indicated deep-seated inward horizontal move- diction and interpretation of the performance of a deep excava-
ments due to stress relief during excavation. tion in Berlin sand. J Geotech Geoenviron Eng
2. The predicted behaviour of the diaphragm wall has a 137(11):1047–1061
6. Tan Y, Wei B (2012) Observed behaviors of a long and deep
trend similar to that of the actual behaviour. Overall, excavation constructed by cut-and-cover technique in Shanghai
the predicted displacement trend of diaphragm wall is soft clay. J Geotech Geoenviron Eng 138(1):69–88
similar to the measured lateral deflection of the wall. 7. Konstantakos DC (2008) Online database of deep excavation
3. Inclinometer data indicated that the maximum mea- performance and prediction. In: 6th international conference on
case histories in geotechnical engineering, Arlington, pp 1–12
sured horizontal wall displacements varied from 17.5 8. Fekado T (2010) Analysis and parametric study of deep exca-
to 67.5% of the numerical results. vation supported by diaphragm walls. M.S. Thesis in Geotechnics
4. Cross-hole sonic logging test shows that there is no submitted to Addis Ababa University, Addis Ababa
major defect in the homogeneity and integrity of 9. Leung EHY, Ng CWW (2007) Wall and ground movements
associated with deep excavations supported by cast in situ wall in
concrete. mixed ground conditions. J Geotech Geoenviron Eng
5. Koden tests were carried out and found that the 133(2):129–143
verticality of the drilled hole is within allowable limit. 10. Ou C, Hsieh P, Lin Y (2011) Performance of excavations with
6. The tie-backed retaining wall system proved a suc- cross walls. J Geotech Geoenviron Eng 137(1):94–104
11. Konstantakos DC, Regalado AJWC, Scharner B (2004) Control
cessful method of constructing deep excavations, with of ground movements for a multi-level-anchored diaphragm wall
the major advantage of having no temporary struts during excavation. In: 5th international conference on case his-
obstructing the work site, thus allowing restriction-free tories in geotechnical engineering, New York, pp 1–7
basement construction from raft level. 12. Sen KK, Alostaz Y, Pellegrino G, Hagh A (2004) Support of deep
excavation in soft clay: a case history study. In: 5th international
Extensive monitoring carried out during the construction conference on case histories in geotechnical engineering, New
has given valuable insight into the performance of the York, pp 1–8
13. Wang JH, Xu ZH, Wang WD (2010) Wall and ground move-
diaphragm walls and the behaviour of the soil strata. ments due to deep excavations in Shanghai soft soils. J Geotech
However the final product was an effective design solution Eng ASCE 136(7):985–994
which took advantage of both analysis and project specific 14. Puller M (2003) Deep excavations a practical manual, 2nd edn.,
opportunities along with good workmanship, proper London, Thomas Telford
15. Control of groundwater for temporary works, CIRIA Report 113
installation of the support system and limited construction 16. BS 8081 (1989) British standard code of practice for ground
induced movements. Thus, this paper provides useful anchorages
guidance to practising engineers on the design of deep 17. IS 10270 (1982) Guidelines for design and construction of pre-
basements using diaphragm walls. stressed rock anchors
18. IS 14268 (1995) Uncoated stress relieved low relaxation seven-
ply strand for prestressed concrete-specification
Acknowledgements Authors are thankful to all the staff of Larsen 19. ASTM D6760-08 Standard test method for integrity testing of
and Toubro, Construction for granting the permission to use the concrete deep foundations by ultrasonic crosshole testing
experimental data to reach the conclusions. Special thanks to
123