Professional Documents
Culture Documents
Amount Require for crane duty (rent of 01x day) of three lighting
pole modified and reinstalled at Lake View train information box,
dinosaur work completed on 20-06-2017. Work was carried out
against W/O no Mech-40 work supervised by Mr Arsalan Zahoor
(deputy manager tech)
(A.M Electrical)
.
Work Completion certificate
It is requested that Rs = 30,000 Amounting for Crane Work For
Shifting Of 05- Ride from Marjan Loan to Lake View Loan Work
has been completed. This Work has done against W/O no Tech-
74 worked supervised by (MANAGER TECH)
GM/Dircetor
It is Submitted that Digging work of entry gate and free fall ride.
Has been completed by the outsource vender. This Work has
done against W/O no Mech-104 worked supervised by
Mr.Arsalan Zahoor (MAINTENANCE MANAGER)
Maintenance Manager Head of Technical
DGM (MMM)
`
A.M (Electrical) Head of Technical
`
A.M (Electrical) Head of Technical
`
A.M (Electrical) Head of Technical
General Manager
General Manager
It is submitted that bumper car anchor bolt with hole work has
been completed. Therefore it is request that 100 % payment may
please be released accordingly. This Work has done against work
order no -111 worked supervised by Mr. Arsalan Zahoor
(Maintenance Manager)
Maintenance Manager Head of Technical
It is submitted that Daikool A.C Outer M.S Base frame with Black
paint has been completed.
Therefore it is request that remaining payment of amount
25,500=/may please be released accordingly. This Work has done
against work order No -112 worked supervised by . LT CDR (R)
Abid Raza (Head of Technical)
HVAC &Plumbing Lead Eng Head of Technical
It is submitted that leaf spring work carried out by outsource vendor on 02-
dinosaur ride of AAP. An amount of Rs 20,000 incurred on above job. Work
supervised work supervised by. LT (R) Arsalan Zahoor (Maintenance
Manager)
Maintenance Manager Head of Technical
It is submitted that Rs 15000 were taken as advance for padding and foaming
work of discovery ride from outsource vender .keeping in view the emergency
of said job ,the job was completed from as early as possible. Work
supervised by LT (R) Arsalan Zahoor (Maintenance Manager)
Maintenance Manager Head of Technical
It is submitte d that 02- Fiber mechanic was hired from outsource by basit for
20- days for converting 10 hearts in to fiber, further 02 more mechanic was
hired for 04 days for completing task prior eid operation .moreover, 02
painters was also hired for completing paint job of rides prior operations.
Breakdown is as under
6,000x 4 =24,000
Total 69,000:
Receiver name abdul basit CNIC #4220-170731223
for paint job total amount 31,500 receiver name
1- Muhammad Razzaq
2-Mukhtaj ullah
3- zafar Iqbal
4- muhammad irshad
For fiber shed work at bullet train 4,500 therefore, total cost
=69000+31,500+4500=10,500 additional cost was given from petty cash of
repair and maintenance,Work supervised by LT (R) Arsalan Zahoor
(Maintenance Manager)
It is submitted d that hors cart has been fabricated from outsource vender.
Total cost incurred on this project was Rs=1, 10,000 work has been
supervised by technical head Rs=10,000 has already been submitted to
vendor, however, Rs 10,000 are remaining, therefore, kindly approved
remaining payment
Head Of Technical General Manager (OPS)
AM Electrical
Maintenance Manager
A.M Electrical
Sr. Maintenance Manager
A.M Electrical
Sr. Maintenance Manager
It is submitted that bearings for chairlift has been purchased from M/S salman
Hamid Bearing Store with the price rate of Rs. 28,000/=. The bearing has been
fixed and now ride is operational. The payment was issue against Minute sheet with
the Name of Arsalan Zahoor Sr. Manager Maintenance. The bill and Vendor card is
attached.
It is submitted that crane work has been completed for repairing super space board,
moving of new genset, and frame fixing of food and fun court kiddy ride shade.
Therefore it is requested that kindly release Rs = 28,000 may please be release
accordingly on name Mr Syed Akber .this work has been completed and supervised
by LT (R) Arsalan Zahoor (Sr. Maintenance Manager)
Sr. Maintenance manager DGM OPS (AAP, SSK & AFC)
Work Completion certificate
A.M
Mechanical Sr. Maintenance Manager
A.M
Electrical Sr. Maintenance Manager
A.M
Electrical Sr. Maintenance Manager
Work Completion certificate
A.M
Electrical Sr. Maintenance Manager
Work Completion certificate
Lead
Plumbing Engineer Sr. Maintenance Manager
Work Completion certificate
A.M
Electrical Sr. Maintenance Manager
Work Completion certificate
Sr. Maintenance
Manager
Work Completion certificate
A.M
Electrical Sr. Maintenance Manager
It is submitted that complete work of cable termination of control panel of sync. System, incoming and
outgoing termination of Sync. Power System and master controller panel have been completed on date
15-09-2020
This work has done against work order # 05, sync. Control panel termination, cable re-rooting and
laying in trenches on proper root and incoming power cables of power complete termination
supervised by Mr.Zeeshan Ali (Power House In-charge) and Power House Team.
Incoming and Outgoing panel de-termination of old distribution panel and Gen-sets with new
outgoing power panel termination and distribution Supervised by Mr.Atif Hussain (A.M. Electrical)
and electrical team.
After completion of work check all Gen-sets backup power supply and K.E supply of all connected
facilities found Satisfactory.
________________________
Expense side
1. Staff payroll & benefits =4.5 M
2. Electricity =0.9 1.5M
3. Fuel & power charges =0.1M 0.1M
4. R&M. =1.0M 1.7M
5. Depreciation charges
Work Completion certificate
It is submitted that project of “laying of 12” PVC drain line in railway work with
labor & material” have been completed therefore that remaining amount of Rs
97,000 may please be released accordingly this worked satisfactorily under
supervision of Mr.Arsalan Zahoor (HOD Tech)and Mr.Abdul Asad (Lead
Plumbing Engineer).
Lead Plumbing Engineer Sr. Maintenance Manager
D.M
Electrical Sr. Maintenance Manager
It is submitted that the worked of 2- UPS 5KVA & 3KVA service has
been completed by Vendor (Dynamic Solution)
This Work has done against MR # 180509.
Supervised by Mr. Ahsan Ali Khan (AM Electronics)
A.M
Electronics Sr. Maintenance Manager
D.M Electrical
Head of Technical
D.M
Mechanical and Fabrication
Sr. Maintenance Manager
Head of Technical
D.M Electrical
Head of Technical
D.M
Mechanical Head of Technical
D.M
Mechanical Head of Technical
D.M
Mechanical Head of Technical
D.M
Mechanical Head of Technical
It is submitted that cable laying work of UAN Cable 900 Feet from
Joyco to PEC (Head Office) has been satisfactory completed
Therefore it is requested that remaining amount may please be
released accordingly.
This Work has been completed satisfactory and supervised by
Mr. Atif Hussain (DM Electrical)
D.M Electrical
Head of Technical
D.M Electrical
Head of Technical
D.M
Mechanical Head of Technical
D.M Electrical
Head of Technical
It is submitted that the worked of Two 6KVA -UPS service has been
completed by Vendor (Dynamic Solution)
This Work has done against MR # 40951.
Supervised by Mr. Ahsan Ali Khan (AM Electronics)
A.M
Electronics Head Of Technical
Head of Technical
Head of Technical
Work Completion certificate
It is submitted that worked of pixel installation have been
completed.
This Work has done against MR # 10989.
Therefore it is requested that amount may please be released
accordingly.
This work was completed satisfactorily under supervision of
Iftikhar Hussain (DM Mechanical)
Head of Technical