Professional Documents
Culture Documents
Power System Study For Distributed Generation Interconnection To Distribution Network-A Malaysian Case Study
Power System Study For Distributed Generation Interconnection To Distribution Network-A Malaysian Case Study
Abstract—This paper describes the power system study Recently, a large number of studies have been carried out to
required by Malaysian Sustainable Energy Development study the impact of DG interconnection to distribution
Authority (SEDA) prior to the Distributed Generation (DG) network. Most of the studies are focusing on power quality
interconnection. A number of DG interconnection guideline and
document are described. A case study is used to demonstrate the
issues such as voltage rise, voltage regulation, and harmonic to
procedure of steady state analysis. Load flow analysis under name a few most important [4-6]. These studies however are
steady state conditions and short circuit analysis are discussed. academically oriented and are not following the standard
Lastly, the simulation results are presented. requirement for DG interconnection as practice by utility. This
paper provides an overview of the standard procedure to
Keywords—Distributed generation, load flow analysis, short perform power system study based on the technical guidebook
circuit analysis, power system study
for the connection of generation to distribution network [7].
I. INTRODUCTION This paper describes the requirement of power system study
The Malaysian government has launched various renewable in Malaysia for the application of DG interconnection and one
energy (RE) programs to encourage the utilization of green example of study is presented. Power flow, voltage magnitude,
and clean energy resources such as Suria 1000, Malaysian power losses and short circuit analysis are the most important
Building Integrated Photovoltaic (MBIPV) and Feed in Tariff in the study. This study is performed using commercial
(FiT). Currently, Malaysian power generation is relying available simulation software, PSS/ADEPT. This paper is
arranged in the following manner. Section II describes the
heavily on natural gas and coal which is known causing
power system study required. Section III presents the
environmental pollution. Since the FiT program launched in methodology of study, the required details of the distribution
December 2011, RE developers are actively taking networks and how to model the respective DG. The results of
opportunity in installing RE to enjoy the premium tariff the simulation study are presented in Section IV followed by
offered for every kilowatt hour energy generated from solar the conclusion in the final section.
photovoltaic (PV), small hydro, biomass and biogas. Up to
December 2013, approximately 130 MW of RE already II. POWER SYSTEM STUDY
commissioned and connected to Malaysian distribution
For the reference of planning, design and operation of DG,
network [1].
a guidebook entitles “Technical Guidebook for the Connection
of Generation to Distribution Network” [7] was published.
Both renewable and non-renewable as a DG provide
This guidebook describes the typical steps involved in
benefits to the utility grid. This includes deferring
connecting DG plant to the distribution network. Fig 1
transmission and distribution infrastructure development,
depicting the flow of basic procedure involved for the
providing voltage support, and peak shaving to name a few.
application to connect DG to distribution network. Recently,
However, the rising number of DG integration to the
SEDA published another guidebook on the grid connected PV
conventional distribution network has raised a lot of concern
generation system to LV and MV distribution network [8].
on the power quality, reliability and security. Some of the
technical concerns are on network voltage control, voltage
unbalance, flicker, power losses, harmonic and additional A. Power System Analysis Requirement
short circuit current in the distribution network with DG. For During the project design stage, DG developer is required
example DG will increase the fault current in the distribution to submit the detailed information of the DG plant for power
network [2-3]. system study (PSS). PSS is carried out to identify the need for
additional equipment and facilities such as interfacing
978-1-4799-7297-5/14/$31.00
Authorized ©2014
licensed use limited to: UNIVERSITY 377 on September 27,2021 at 12:57:21 UTC from IEEE Xplore. Restrictions apply.
IEEENASIONAL. Downloaded
TENAGA
2014 IEEE International Conference Power & Energy (PECON)
transformer for interconnection and to estimate the costs. In 1. Three phase fault to ground on the generator
addition, PSS is necessary to assess the potential impact of the transformer.
respective DG on the panning and operation of the distribution 2. Three phase fault for 500ms at the main intake
system. Network capability to accommodate the proposed DG transformer secondary side followed by loss of the DG
and the connection configuration will be determined during feeder.
this stage. 3. Three phase fault for 500ms on a bus in the feeder
followed by loss of section supply large load.
The impact varies depending on the capacity of the
generator, type of generator, location and point of connection TABLE 1. Objective of network assessment
of the DG to the distribution network. The study is important Assessment Objective
to identify all technical requirements prior to the
interconnection. Table 1 shows the assessment and objective Network voltage To make sure the voltage does not
of each study which includes network analysis on voltage profile violate the statutory limit and to
profile, system adequacy, system losses and short circuit identify suitable voltage and power
studies. factor control.
System adequacy To identified any branch overload
for upgrading or reinforcement.
System losses To determine system performance
and cost estimation.
Short circuit To make sure short circuit level is
below 90% of the equipment short
circuit rating.
III. METHODOLOGY
PSS/ADEPT was used in modeling and simulation with
different scenarios. For the case study a typical distribution
network in the middle region of peninsular Malaysia is used.
378 on September 27,2021 at 12:57:21 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: UNIVERSITY TENAGA NASIONAL. Downloaded
2014 IEEE International Conference Power & Energy (PECON)
379 on September 27,2021 at 12:57:21 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: UNIVERSITY TENAGA NASIONAL. Downloaded
2014 IEEE International Conference Power & Energy (PECON)
Fig 3. PMU_1 load profile during peak and trough load period.
380 on September 27,2021 at 12:57:21 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: UNIVERSITY TENAGA NASIONAL. Downloaded
2014 IEEE International Conference Power & Energy (PECON)
to accommodate the proposed DG as the fault current is well [6] Jianhui Wong, Yun Seng Lim, Taylor Phil, and Morris Stella, "Optimal
utilisation of small-scale embedded generators in developing country - A
below the allowable limit for the bus section in OPEN or case study in Malaysia," Renewable Energy 36, pp. 2562-2572, 2011
CLOSED position. [7] Tenaga Nasional Berhad, 2005. Technical Guidebook for the
Connection of Generation to Distribution Network. Tenaga Nasional
TABLE 3. Busbar fault level when bus section is in CLOSE position. Berhad.
Bus Bus 3 phase fault current (kA) [8] Tenaga Nasional Berhad, "TNB Technical Guidebook on Grid-
Voltage Without DG With DG interconnection of Photovoltaic Power Generation System to LV and
MV Networks," 2013.
PMU 1 132 kV 0.823 1.15 [9] Wanik, M. Z., Erlish, I., Mohamed, A., & Salam, A. A. (2010).
Influence of Distributed Generations and Renewable Energy Resources
Power Plant on Power System Transient Stability. Power and Energy
PMU 1 L 11 kV 7.315 11.343 (PeCon 2010) (pp. 402-425). Kuala Lumpur: IEEE.
PMU 1 L 11 kV 6 8.683
PMU 1 R 11 kV 6 8.675
V. CONCLUSION
This paper has described the power system study required
before the DG interconnection with existing distribution
network is done. For the DG more than 180 kW and less than
5 MW, power system analysis which include power flow and
short circuit analysis is necessary. The power flow analysis
investigate the capability of existing network to accommodate
distributed generation without causing reverse power flow,
voltage limit violation and losses higher than without DG.
Whilst short circuit analysis is needed to make sure the fault
current is within 90% of the circuit breaker rating. This is to
protect the primary equipment and avoid the damage of circuit
breaker during the fault event. For the case study presented,
the interconnection will be rejected as the interconnection will
result in reverse power flow and losses higher than without
DG.
REFERENCES
[1] SEDA Malaysia. (2014). Sustainable Energy Development Authority of
Malaysia. Retrieved 03 12, 2014, from http://seda.gov.my/
[2] Abdel-Galil, D. T., Ahmed E.B. Abu-Elanien, E., El-Saadany, D. E.,
Girgis, D. A., Yasser A.-R. I. Mohamed, E., Salama, D. M., et al.
(2007). PROTECTION COORDINATION PLANNING WITH
DISTRIBUTED GENERATION. Natural Resources Canada.
[3] Doyle, M. (2002). Reviewing the impacts of distributed generation on
distribution system protection. Power Engineering Society Summer
Meeting (pp. 103-105). Chicago, IL, USA: IEEE.
[4] Asnawi Mohd. Bursah and Vigna Kumaran R., “The impact of grid
connected photovoltaic generation system to voltage rise in low voltage
network,” in Recent Advances in Energy, Enviroment and Economic
Development, Paris, 2012, pp. 44-49.
[5] Kein Huat Chua et al., “Mitigation of Voltage Unbalance in Low
Voltage Distribution Network with High Level of Photovoltaic System,”
Energy Procedia, vol. 12, pp. 495-501, 2011
381 on September 27,2021 at 12:57:21 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: UNIVERSITY TENAGA NASIONAL. Downloaded