Classification of tenders
Open tender–Main tendering procedure employed by both the private sector and the
government. The client advertises the tender offers in the local newspaper along with
the key information of the proposed works and inviting interested contractors.
The tender notification includes an invitation by the employer for a suitable contract to
submit their bids or offers.
Selective tender—a short list of contractors is drawn up and they are invited to submit
tenders. The purpose of this tender is to improve the quality of bids received to ensure
that the contractors with necessary experience are given a chance to submit the
necessary bids for the specific reason of the employer.
Negotiation tender—Invitation is given to only one firm to render a service by quoting their
rates. If the quoted rates are high, it will be negotiated prior to the agreement of the
contract. Generally done in case if the owner has long term association with the
contractor and cannot consider any other bidder for the job.
Term tender—Normally used by projects that need maintenance. The contractor will be
asked to cover a range of different buildings in different locations. It is often limited to a
fixed time scale although the needs of the client may require this to be extended. This is
generally a standing offer to undertake a loosely defined extends of work usually within
a fixed amount of time.
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
Tendering Process :-
20. Detailed specifications or reference to standard specifications for each item of work
24. Time for completion and the progress to be made at intervals of time
Conditions regarding employment of technical personnel
27. Amount of Security deposit to be paid/ deducted from running bills of contractors
should be notified in the tender call notice
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
30. Penalty conditions for slow progress and delay in the completion of work
QUOTATION
For small jobs, the owner gives an offer to the contractor for
quoting rates for works and supplies required. No EMD is
required with a quotation.
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
CLERK OF WORKS
A clerk of works oversees the quality and safety of work on a construction site,
making sure that building plans and specifications are being followed correctly.
Duties include:
a) Performing regular inspections of the work on site and comparing completed
work with drawings and specifications
b) Measuring and sampling building materials to check their quality
c) Recording results
d) Identifying defects and suggesting ways to correct them
e) Liaising with other construction staff, such as contractors, engineers and
surveyors
f) Monitoring and reporting progress to construction managers, architects and
clients
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
In general, the coverage of construction all risk insurance plans are offered in the following
two sectors:
SECURITY DEPOSIT
a) Security deposit is the amount the contractor has to deposit with the
owner after his tender is accepted.
d) The contractor has to fulfill all the terms and conditions laid down in the
contract and maintain quality and speed satisfactorily. If he fails to do so, a
part or whole of the SD is forfeited.
SECURITY DEPOSIT
RETENTION MONEY
DIFFERENCE BETWEEN
EARNEST MONEY DEPOSIT, SECURITY DEPOSIT & RETENTION MONEY
For example, if you have to install a lift in your building, you will invite tenders.
In order to ensure that only the genuine companies offer to install the lift, you
prescribe an EMD of a particular amount. If the company you select for
installation of your lift suddenly backs out, in the absence of an EMD you could
suffer a loss of time and resources. EMD ensures that the company installs the
lift as it won't like to lose its EMD. After the lift is installed, you would like to
verify the company's claim that it has properly installed a good lift in your
building by using the lift actually for, say, six months. So you retain a part of
your payment which you could forfeit in case the lift turns out to be defective
during the first six months. Generally the retention money is withheld during
the period of warranty.
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
LIQUIDATED DAMAGES
b) This does not relieve the contractor from his obligations and liabilities
under the contract.
MOBILIZATION FUND
Firm period is the duration of time over which the firm price
is valid.
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
CONTRACT DOCUMENTS
1. Title page – name of work, name of owner, name of contractor, contract agreement no.,
contents, etc.
3. Tender notice – brief description of work, estimated cost of work, date and time of
receiving tender, amount of EMD and security deposit, time of completion, etc.
4. Tender form – the bill of quantities, contractor’s rate, total cost of work, time of
completion, amount of security deposit, etc.
7. Specifications –
a) General Specifications which specify the class and type of work, quality of materials, etc.
b) Detailed specifications – detailed description of each item of work including material and
method to be used along with the quality of workmanship required.
8. Conditions of contract
a) Rates of each item of work inclusive of materials, labour, transport, plant/equipment and
arrangements required for completion of work.
b) Amount and form of earnest money and security deposit
c) Mode of payment to contractor including running payment, final payment and refund of
security money, etc.
d) Time of completion of work
e) Extension of time for completion of work
f) Engagement of sub contractor and other agencies at contractor’s cost and risk
g) Penalty for poor quality and unsatisfactory work progress
h) Termination of contract
i) Arbitration for settlement of disputes
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
9. Special conditions – depending upon the nature of work taxes and royalties
included in the rates, labour camp, labour amenities, compensation to labour in case
of accidents, etc.
Pre-qualifications of Contractors
a) Work Experience
b) Financial solvency
c) Annual Turnover
d) Quality of work executed
e) Organizational structure
f) Equipments/ machinery available
g) Manpower available
h) General Reputation
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
Classification of Contracts
1. Lump-sum contract
2. Cost plus fixed percentage contract
3. Cost plus fixed fee contract
4. Target contract
5. Percentage rate contract (B1 system)
6. Item rate contract (B2 system)
7. Labour contract
8. Joint venture contract
9. Turn-key contract
10.Lump-sum contract for bungalows etc
11.BOT system
RIZVI COLLEGE OF ARCHITECTURE
4TH YR. B.ARCH | SEM - VII
PROFESSIONAL PRACTICE - 1
1. Lump-sum contract
c) Smaller the completion time more is the profit and hence the
contractors hurry to complete the work and the quality of
workmanship is not maintained.
4. Target contract
a) The contractor is paid a fixed fee on a prime cost basis for the
work performed under the contract and in addition he receives
a percentage on the savings effected against either a prior
agreed estimated total cost or a target value arrived without
changing the specification.
7. Labour contract
9.Turn-key contract
Termination of a contract
takes pace when the parties to the contract are released from their contractual
obligations.
By breach of contract.
By agreement
By performance of the party’s contractual obligations (i.e. after the completion of the
obligations as stated in the contract)
By inability to perform
By fraud