Professional Documents
Culture Documents
UNIT 7
AUDIT OF PROPERTY, PLANT AND EQUIPMENT
AND RELATED VALUATION ACCOUNTS
Estimated Time: 4.5 HOURS
Land P2,500,00
0
Land Improvements 560,000
Building 3,600,000
Machinery and 6,600,000
equipment
During 2016 the following data were available to you upon your analysis of
the accounts:
Required: Based on the above and the result of your audit, compute for the
following as of December 31, 2016:
1. Land
2. Land Improvements
3. Building
4. Machinery and Equipment
5. Total depreciable property, plant and equipment
site. The building has an estimated useful life of 20 years. Unaware of the
accounting procedures for government grants, the company did not reflect
the grant on its books.
Required:
1. Prepare the necessary adjusting journal entries as of December 31, 2016.
2. Determine the adjusted balances of the following as of December 31,
2016:
a. Land
b. Carrying value of building
c. Land and building
d. Organization cost, net (presented under Noncurrent Assets)
April 6 New parking spaces were completed for the new plant at a total
cost of P240,000.
Additional information:
The leasehold improvements were completed on December 31, 2012. The
related lease was to be terminated on December 31, 2018.
Additional information:
Virginia determined that the delivery equipment comprising the P3,000,000
beginning balance would have been depreciated at a total amount of
P400,000 for the year.
December 31 7,000,000
Angelo also has a P10 million 10%, 10-year note dated January 1, 2013 with
interest payable annually on December 31 and a P15 million, 12%, 5-year
note dated January 1, 2014 with interest payable annually.
1. Assuming that the building was completed on December 31, 2016, how
much is the cost of the building on December 31, 2016?
2. Assuming that the building was completed on June 30, 2016, how much is
the cost of the building?
3. Assuming that the building was completed on December 31, 2016 and the
specific construction loan was also used for general purposes, how much
is the cost of the building?
During 2013, several townhouses were constructed near the site to house the
employees. Total cost of the townhouses was P1,500,000. Estimated residual
value is P250,000.
During 2014, the first year of operations, only 5,000 tons of gold were
collected from the mine. In 2015, the employees were able to mine 1 million
tons of gold. Geologists discovered that the mine actually contained 3 million
tons more than the original estimation. Improvements of P275,000 were
made to the mine early in 2015 to facilitate the removal of the additional
gold. Furthermore, an additional townhouse was constructed at a cost of
P225,000 for the additional employees that would be hired to obtain the
additional gold. The new townhouse was not expected to have any residual
value.
In 2016, 2.5 million tons of gold were mined and costs of P1,100,000 were
incurred at the beginning of the year for improvements to the mine.