11. Connect and clamp the harnesses ( x3, x1).
Bypass Covers
1. Set the left cover [A]. Make sure that the claws are set correctly in their holes.
SM 3-127 D074/D075/M044
Multi Bypass Tray (D517)
3. Re-attach:
[A] Front cover ( x1 M4x8)
[B] Rear cover ( x2 M4x8)
D074/D075/M044 3-128 SM
Multi Bypass Tray (D517)
LCIT Covers
The frame, covers, screws and sponge strip in this section are provided with the LCIT
accessories.
Installation
1. Remove the right stay [A] from the frame ( x2 M4x8).
2. Position the holes on the bottom of the frame with the positioning pins at the front and back,
and set the frame [A] on the left side of the unit.
3. Make sure that the holes and positioning pins are engaged at the front and back.
SM 3-129 D074/D075/M044
Multi Bypass Tray (D517)
D074/D075/M044 3-130 SM
Multi Bypass Tray (D517)
Installation
screws of the front frame plate.
10. Slide the front cover [B] down until the top is flat and level with the top of the top cover.
11. Fasten the front cover ( x2 M4x8).
12. Close the front door.
SM 3-131 D074/D075/M044
Multi Bypass Tray (D517)
14. Hang the keyholes in the bracket on the back of the rear cover [A] onto the shoulder screws
of the rear frame plate [B].
15. Slide the cover [A] down so that the cover joints are at the same level.
16. Fasten the rear cover ( x2 M4x8).
D074/D075/M044 3-132 SM
Multi Bypass Tray (D517)
18. Peel the tape from the back of the sponge strip if the sponge strip has not been attached to
Installation
the LCIT.
19. Attach the sponge strip [A] to the left edge of the frame.
20. Close the bypass unit [B].
SM 3-133 D074/D075/M044
Multi Bypass Tray (D517)
2. Store the tab sheet fence [A] as shown. Also store the end fence [B] here if the customer
does not need to use it at this time.
D074/D075/M044 3-134 SM
Multi Bypass Tray (D517)
Installation
1. Attach the number decals to the front of the unit as shown above.
SM 3-135 D074/D075/M044
Multi Bypass Tray (D517)
D074/D075/M044 3-136 SM
Buffer Pass Unit Type 5010 (D548)
Installation
No. Description Q'ty
1. Screws 6
2. Leveling Shoes 4
5. Mylars 4
SM 3-137 D074/D075/M044
Buffer Pass Unit Type 5010 (D548)
3.7.2 INSTALLATION
The unit must be connected to a power source that is close to the unit and easily
accessible.
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedures.
The buffer pass unit is unstable and can fall over easily. To avoid personal injury or
damage to the unit, use caution when you pull out the buffer pass unit drawer until the
unit has been docked to the main machine.
The power cord that comes with the buffer pass unit is for use with this equipment only.
Do not use it with other appliances. Doing so could result in fire or electric shock.
Unpacking
D074/D075/M044 3-138 SM
Buffer Pass Unit Type 5010 (D548)
Installation
1. Remove the right cover of the buffer pass unit ( x6).
SM 3-139 D074/D075/M044
Buffer Pass Unit Type 5010 (D548)
2. On the right side of the Buffer Unit, remove the entrance guide [A] ( x2).
3. One mylar is attached to the underside of the upper plate of the Buffer Unit entrance guide
[A].
Select one mylar and remove the tape.
Position the mylar as shown and attach it to the underside of the upper plate.
4. One mylar is attached to the topside of the bottom plate of the Buffer Unit entrance guide
[B].
D074/D075/M044 3-140 SM
Buffer Pass Unit Type 5010 (D548)
Sponges
Installation
1. Remove the tape from each sponge strip and attach them to the right side of the unit as
shown above.
The two yellow sponge strips in the illustration are provided as accessories with
the main machine. The other strips are accessories provided with this peripheral
unit.
2. After attaching all sponges, use a sharp cutter to cut the sponge on the corner at [A].
SM 3-141 D074/D075/M044
Buffer Pass Unit Type 5010 (D548)
D074/D075/M044 3-142 SM
Buffer Pass Unit Type 5010 (D548)
3. Push in the lock lever and fasten it with the screw just removed ( x 1).
Installation
4. Connect the I/F cable of the buffer pass unit to the socket of the main machine.
SM 3-143 D074/D075/M044
Buffer Pass Unit Type 5010 (D548)
Work carefully! The unit is unstable with the drawer pulled out and can tip over
easily before it is docked to the main machine.
4. Remove the clamp bracket [B] ( x 2).
5. Remove the four shipping brackets [D] ( x 1 each).
6. Push in the buffer pass unit drawer [C].
7. Close the front door.
D074/D075/M044 3-144 SM
Buffer Pass Unit Type 5010 (D548)
1. Attach the docking bracket provided with the downstream peripheral to the left side [A] of
the buffer pass unit ( x4).
Downstream Unit Mylars
Two mylars must be attached to the upper and lower plates on the entrance guide
of the downstream unit.
1. Remove the entrance guide of the downstream unit ( x2).
Installation
2. One mylar is attached to the underside of the upper plate of the downstream unit entrance
guide [A].
Select one mylar and remove the tape.
Position the mylar as shown and attach it to the underside of the upper plate.
3. One mylar is attached to the topside of the bottom plate of the downstream entrance guide
[B].
Select one mylar and remove the tape.
Position the mylar as shown and attach it to the topside of the lower plate.
4. Re-attach the entrance guide, and then re-attach the right cover.
5. Re-attach the entrance guide to the downstream unit ( x2).
SM 3-145 D074/D075/M044
Buffer Pass Unit Type 5010 (D548)
2. Approximately 30 mm (1 in.) from the plug, attach the caution decal [A] for multi power
sources to power plug [B] (NA) or [C] (EU) of the main machine.
1. Set the leveling shoes and adjust the height of the unit. ( p.3-218)
2. Load some B4 paper in the 2nd tray of the main machine, and make several copies.
3. Check paper skew and side-to-side registration and correct if necessary. ( p.3-220)
D074/D075/M044 3-146 SM
Cover Interposer Tray (D518)
3.8.1 ACCESSORIES
Check the quantity and condition of the accessories in the box against the following illustration
and list.
Installation
No. Description Q'ty
2. Front Cover 1
3. Spacer 1
6. Sponge Strip 1
7. Leveling Shoes 4
8. Joint Bracket 1
9. Screw (M4x8) 4
SM 3-147 D074/D075/M044
Cover Interposer Tray (D518)
3.8.2 INSTALLATION
The unit must be connected to a power source that is close to the unit and easily
accessible.
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedures.
Tapes
1. Remove all the tape and shipping materials from the tray unit [A].
2. Remove all tape and shipping material [B] from the transport unit [C].
3. Remove tape and covers from both connectors [D].
D074/D075/M044 3-148 SM
Cover Interposer Tray (D518)
Installation
1. Peel the tape from the back of the sponge strip [A] and attach it as shown.
2. Attach the relay guide plate [B] ( x2).
3. Remove the ground plate [C] from the bottom cross-piece ( x2).
4. Turn the ground plate over.
5. Reattach the ground plate with the same screws as shown ( x2).
Procedure 2
1. Attach the relay guide plate and ground plate as described in "Procedure 1" above.
SM 3-149 D074/D075/M044
Cover Interposer Tray (D518)
2. Remove the tape from each sponge strip and attach them to the right side of the unit as
shown above.
The two yellow sponge strips in the illustration are provided as accessories with
the main machine. The horizontal sponge strip is provided with the Cover
Interposer Tray.
3. After attaching all sponges, use a sharp cutter to cut the sponge on the corner at [A].
Docking
1. If the upstream unit is the main machine, remove the interface connector cover.
2. Attach the joint bracket [A] to the upstream unit ( x4).
D074/D075/M044 3-150 SM
Cover Interposer Tray (D518)
Installation
6. Open the front door [A] of the cover interposer tray.
7. Remove the screw of the lock bar [B]. Keep this screw.
8. Pull out the lock bar until it stops.
9. Push the unit [C] against the upstream unit so that the lock bar is below the joint bracket
[D].
10. Connect the unit’s cable [E] to the upstream unit.
11. Push in the lock bar [B] and fasten it with the screw removed in Step 7.
12. Close the front door.
The tray unit of the cover interposer tray is supported by both the cover interposer
transport unit and the top of the downstream peripheral unit.
The next peripheral device downstream must be docked to the cover interposer tray
relay unit (the base) before the cover interposer tray unit can be installed.
Go to the appropriate section to dock the next downstream peripheral unit before installing the
tray unit of the cover interposer tray:
Multi Folding Unit ( p.3-157)
Ring Binder ( p.3-166)
High Capacity Stacker ( p.3-181)
Finishers ( p.3-192)
SM 3-151 D074/D075/M044
Cover Interposer Tray (D518)
Never attempt to mount the tray unit of the cover interposer tray until the next
downstream peripheral unit has been docked to the transport unit (base) of the cover
interposer tray.
To prevent bending the frame of the tray unit and damaging its alignment, always
remove the tray unit from the cover interposer tray transport unit at the following times:
1) Before disconnecting either the cover interposer tray or the next downstream
peripheral unit, or 2) Before doing any maintenance on either the cover interposer tray
or the next downstream peripheral unit.
D074/D075/M044 3-152 SM
Cover Interposer Tray (D518)
Installation
7. Remove the front inner cover [A] from the tray unit ( x2).
8. Fasten the tray unit to the top of the transport unit with the knob screws [B] ( x2).
9. Attach the base cover [C] (Flat knob screw; x1).
Make sure the holes in the cover match the positions of the reference pins.
10. Use the two "L" hinges to attach the door [D] to the front inner cover [A].
It is easier to connect the door to the front inner cover before re-attaching the cover
to the tray unit.
11. Re-attach the front inner cover [A] (with door attached) ( x2).
12. If the Buffer Pass Unit is installed, remove its rear cover.
SM 3-153 D074/D075/M044
Cover Interposer Tray (D518)
14. With the rear covers of both the buffer pass unit and cover interposer unit removed, use a
short screwdriver to loosen bracket [A] ( x2).
15. Fasten the bracket to the buffer pass unit at [B] ( x1).
16. Tighten the screws ( x3).
17. Re-attach the rear covers.
18. Attach the shoulder screws to the front of the unit ( x2).
D074/D075/M044 3-154 SM
Cover Interposer Tray (D518)
Installation
19. Set the spacer [A].
Hang wide ends of the keyholes of the side of the spacer over the heads of the
shoulder screws.
Slide the spacer up to set the heads of the shoulder screws in the narrow end of the
keyholes [B] and [C].
SM 3-155 D074/D075/M044
Cover Interposer Tray (D518)
1. Set the leveling shoes and adjust the height of the unit. ( p.3-218)
2. Load some B4 paper in the 2nd tray of the main machine, and make several copies.
3. Check paper skew and side-to-side registration and correct if necessary. ( p.3-220)
D074/D075/M044 3-156 SM
Multi Folding Unit (D521)
3.9.1 ACCESSORIES
Check the quantity and condition of the accessories in the box against the following illustration
and list.
Installation
No. Description Q'ty
1. Joint Bracket 1
2. Paper Guide 1
4. Ground Plate 1
5. Screws M3x6 2
6. Screws M3x6 2
7. Screws M4x14 4
8. Leveling Shoes 5
9. Power Cord*1 1
*1
: In China, do not use the power cord provided with this unit. Contact your supervisor and use
the power cord specified for use in China.
SM 3-157 D074/D075/M044
Multi Folding Unit (D521)
3.9.2 INSTALLATION
The unit must be connected to a power source that is close to the unit and easily
accessible.
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedures.
Tapes
1. Remove all tape and packing material from the front, left, rear, and right sides.
D074/D075/M044 3-158 SM
Multi Folding Unit (D521)
Installation
1. Attach the paper guide [A] ( x2 M3x6).
2. Peel the tape from the sponge strip [B] and attach the strip to the top right edge of the unit.
Procedure 2
3. Attach the paper guide as described in "Procedure 1" above.
SM 3-159 D074/D075/M044
Multi Folding Unit (D521)
4. Remove the tape from each sponge strip and attach them to the right side of the unit as
shown above.
The two yellow sponge strips in the illustration are provided as accessories with
the main machine. The horizontal sponge strip is provided with the Multi Folding
Unit.
5. After attaching all sponges, use a sharp cutter to cut the sponge on the corner at [A].
Ground Plate
1. Attach the ground plate [A] to the lower right edge of the unit ( x2 M3x6).
D074/D075/M044 3-160 SM
Multi Folding Unit (D521)
Docking
Installation
1. Fasten the joint bracket [A] to the left side of the upstream unit ( x4 M4x14).
SM 3-161 D074/D075/M044
Multi Folding Unit (D521)
If you are docking to the main machine, you must first remove the plastic cap at the
I/F cable connection point.
9. Remove:
[A] Rear upper cover ( x4)
[B] Rear lower cover ( x3)
D074/D075/M044 3-162 SM
Multi Folding Unit (D521)
The following parts require removal only if the upstream unit is the Cover
Interposer Tray (D518).
These parts must be removed so that the tray unit of the Cover Interposer Tray will
fit on top of the Multi Folding Unit.
Installation
2. Remove:
[A] Bracket ( x1)
[B] Cross-piece ( x2)
[C] Metal plate from the door ( x2)
3. After removing [B] and [C], reattach [A].
SM 3-163 D074/D075/M044
Multi Folding Unit (D521)
Power Cord
1. Insert the power cord socket [A] into the power connection point.
In China, do not use this power cord provided with this unit. Contact your
supervisor and use the power cord specified for use in China.
2. Connect the power supply cord plug to a power outlet.
1. Set the leveling shoes and adjust the height of the unit. ( p.3-218)
2. Load some B4 paper in the 2nd tray of the main machine, and make several copies.
3. Check paper skew and side-to-side registration and correct if necessary. ( p.3-220)
D074/D075/M044 3-164 SM
Multi Folding Unit (D521)
5. Attach the mylar to the top of the downstream paper guide as shown above (top view).
Installation
1. Set the auxiliary tray [A] or flexible page depressor [B] when required.
SM 3-165 D074/D075/M044
Ring Binder (D519)
3.10.1 ACCESSORIES
Check each accessory against the list below to make sure that you have everything.
1. Docking Bracket 1
3. Sponge Strip 1
4. Power Cord 1
5. Ring Opener 1
9. Leveling Shoes 4
D074/D075/M044 3-166 SM
Ring Binder (D519)
Installation
3.10.2 BEFORE YOU BEGIN
SM 3-167 D074/D075/M044
Ring Binder (D519)
The unit must be connected to a power source that is close to the unit and easily
accessible.
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedure.
1. Remove all visible tapes, cushion, two accessory boxes, and wrapping material attached to
the outside of the unit.
2. Remove:
[A] Brace x1 ( x4)
[B] Brace x1 ( x4)
Do not discard these braces. They must be reattached to the unit before it is
moved or shipped to another location.
D074/D075/M044 3-168 SM
Ring Binder (D519)
Installation
3. Open the right door and left door.
4. Remove all tapes and packing material.
5. Remove the brace and red tag [A] ( x2).
6. Pull the binder unit [A] out of the unit until it stops.
7. Remove the tape [B] on top of the unit.
8. Pull down the ring cartridge handle and cover [C].
9. Pull the ring cartridge out and remove the cushion [D].
10. Push the ring cartridge in and close its cover.
11. Push the binder unit into the unit.
12. Close the left front door and right front door.
SM 3-169 D074/D075/M044
Ring Binder (D519)
D074/D075/M044 3-170 SM
Ring Binder (D519)
Installation
2. Remove the tape from each sponge strip and attach them to the right side of the unit as
shown above.
The two yellow sponge strips in the illustration are provided as accessories with
the main machine. The horizontal sponge strip is provided with the Ring Binder.
3. After attaching all sponges, use a sharp cutter to cut the sponge on the corner at [A].
SM 3-171 D074/D075/M044
Ring Binder (D519)
D074/D075/M044 3-172 SM
Ring Binder (D519)
Installation
1. Set the leveling shoes (x4) under the feet of the unit.
2. Open the right front door and left front door.
3. Place a level on the frame.
4. Use a wrench to turn the nut at each foot until the machine is level.
4. Set the ring supply level indicator [1] behind the tabs on the side of the ring supply cartridge
[2].
SM 3-173 D074/D075/M044
Ring Binder (D519)
The breaker switch is at the bottom of the left rear corner near the power cord.
When it is set to the right, you should see a straight line (-).
3. Connect the power cord to the finisher, then connect the other end to a power supply outlet.
4. Use the sharp point of a pen [B] or similar tool to push in the breaker switch until it snaps to
the off position. (You should see "0".)
5. If the breaker does not snap to the off position:
Check that the power cord is correctly connected to the finisher and power supply.
Push the breaker switch again to see if it snaps to the off position.
If the breaker switch does not snap to the off position, it must be replaced.
6. Be sure to reset the breaker switch to the on (-) position.
D074/D075/M044 3-174 SM
Ring Binder (D519)
Installation
2. If the finisher is connected to the left side of the ring binder, disconnect it and pull it away
from the left side of the ring binder.
3. Execute a run by feeding paper (A4 or LT) from Tray 2 of the host machine (punching only,
no ring binding).
4. During the run, each sheet of paper briefly protrudes about 5 to 10 mm before it switches
back into the ring binder and feeds to the punch unit, as shown above.
There are two scales on the left side of the ring binder below the paper exit.
The rear scale [1] is for LT-size paper and the front scale [2] is for A4-size paper. Be
sure to read the correct scale for the paper size in use.
5. Check the position of the paper on the scale to determine if the paper is centered.
Read the rear scale for LT-size paper and the front scale for A4-size paper.
The scale lines are spaced 1 mm apart.
The edges of the paper should be at the center line and not deviate more than ±2
mm.
SM 3-175 D074/D075/M044
Ring Binder (D519)
[B] Leading/trailing edges offset to the rear more than 2 mm. Adjustment required.
[C] Leading/trailing edges offset to the front more than 2 mm. Adjustment required.
6. If the edge of the paper is on the scale at the center [A], no adjustment is required.
-or-
If the edge of the paper is ±2 mm off the center line on the scale, adjustment is required. Do
the procedure in the next section.
Correcting Side-to-Side Registration: Bracket Adjustment
1. Disconnect the ring binder from the upstream unit.
2. On the docking bracket attached to the upstream unit, loosen screws , , , and .
3. Remove bracket [A] ( x1), rotate it 90 degrees, and re-fasten the screw. Changing the
position of this bracket aligns the oval cut-out horizontally and frees the joint bracket so it
D074/D075/M044 3-176 SM
Ring Binder (D519)
Installation
Checking and Correcting Skew
Checking for Paper Skew
Do this check to confirm that the paper is not skewed in the paper path.
1. Make sure that the I/F cable of the ring binder unit is connected.
2. If the finisher is connected to the left side of the ring binder, disconnect it and pull it away
from the left side of the ring binder.
3. Execute a straight-through run (no ring binding, no punching) with A3 or DLT from Tray 2 of
the host machine.
4. During the run, each sheet of paper exits the side of the ring binder, as shown above.
There are two scales on the left side of the ring binder below the paper exit.
The rear scale [1] is for DLT-size paper and the front scale [2] is for A3-size paper. Be
sure to read the correct scale for the paper size in use.
5. Check the position of the paper on the scale to determine if the paper skews as it exits.
Read the rear scale for DLT-size paper and front scale for A3-size paper.
The scale lines are spaced 1 mm apart.
The paper must not deviate more than ±2 mm on the scale.
SM 3-177 D074/D075/M044
Ring Binder (D519)
Trailing edge skew to the front, total skew more than ±2 mm. Adjustment
[B]
required.
Trailing edge skew to the rear, total skew more than ±2 mm. Adjustment
[C]
required.
Correcting Skew
1. Disconnect the ring binder from the upstream unit.
2. Remove the spacers from the right side of the ring binder at the base ( x2).
D074/D075/M044 3-178 SM
Ring Binder (D519)
Installation
3. On the docking bracket attached to the upstream unit, loosen the screws.
4. Insert a spacer and tighten the screws.
If the trailing edge is skewing toward the front of the machine, insert a spacer [A] under the
rear end of the bracket and tighten the screws.
-or-
If the trailing edge is skewing toward the rear of the machine, insert a spacer [B] under the
front end of the bracket and tighten the screws.
5. To another run to check the adjustment. If skew is still present, insert another spacer.
SM 3-179 D074/D075/M044
Ring Binder (D519)
Always grip handle Mc8 when pulling out or pushing in the binder unit.
Never touch any other surface of the binder unit when it is moving on its rails.
To avoid injury to the fingers, never push on the top of the binder unit to slide it
back into the finisher as shown above.
Never store paper, extra rings, manuals or any other material below the output tray.
Obstacles in this area (shown in red in the illustration below) will interfere with the raising
and lowering of the tray and cause an error.
D074/D075/M044 3-180 SM
High Capacity Stacker (D515)
3.11.1 ACCESSORIES
Check the quantity and condition of the accessories in the box against the following illustrations
and lists.
High Capacity Stacker (D515)
Installation
No. Description Q'ty
1. Power Cord*1 1
2. Leveling Shoes 4
3. Ground Plate 1
6. Joint Bracket 1
7. Sponge Strip 1
8. Paper Guide 1
9. Screws M4x8 2
SM 3-181 D074/D075/M044
High Capacity Stacker (D515)
*1: In China, do not use this power cord provided with this unit's accessories. Contact your
supervisor and use the power cord specified for use in China.
*2: A lock is not provided.
Roll-Away Cart Type 5010 (D456-17)
1. Paper Tray 1
4. Screws M10x25 2
3.11.2 INSTALLATION
The unit must be connected to a power source that is close to the unit and easily
accessible.
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedure.
D074/D075/M044 3-182 SM
High Capacity Stacker (D515)
Shipping Tapes
Installation
1. Remove all visible tape from the front [A] and back [B].
2. Open the front panel [A] and remove all visible tapes.
3. Open the front door [B] and remove all visible tapes.
SM 3-183 D074/D075/M044
High Capacity Stacker (D515)
1. Remove the tape from the sponge strip [A] and attach the strip to the top right edge of the
unit.
The sponge strip closes the gap between the High Capacity Stacker and the
upstream unit to prevent paper or other objects from falling between the units.
2. Fasten the paper guide [B] to the right side of the unit ( x2).
D074/D075/M044 3-184 SM
High Capacity Stacker (D515)
3. Attach the ground plate [A] to the bottom right edge of the unit ( x2 M3x6).
If the High Capacity Stacker will be docked to the left side of the main machine,
more sponge strips must be attached.
Procedure 2
1. Attach the paper guide and ground plate as described in "Procedure 1" above.
Installation
2. Remove the tape from each sponge strip and attach them to the right side of the unit as
shown above.
The two yellow sponge strips in the illustration are provided as accessories with
the main machine. The horizontal sponge strip is provided with the High Capacity
Stacker.
3. After attaching all sponges, use a sharp cutter to cut the sponge on the corner at [A].
SM 3-185 D074/D075/M044
High Capacity Stacker (D515)
Docking
If this unit is to be installed on the left side of the Multi Folding Unit, use three
M4x20 screws and one M4x14 screw.
The screw [B] (front-lower) must be "M4x14". The other three screws must be
"M4x20". Otherwise, these screws may interfere with the upstream unit.
M4x20 screws are provided with the Multi Folding Unit.
2. Open the front door.
D074/D075/M044 3-186 SM
High Capacity Stacker (D515)
Installation
4. At the front right corner, remove the screw of the lock bar [A] ( x1 M3x6). Keep this
screw.
5. Pull the lock bar toward you until it stops.
6. Slowly push the unit [B] against the left side of the upstream unit (or main machine) so that
the lock bar is directly and squarely under the arms of the joint bracket [C].
7. Push the lock bar in completely so that it slides up into the notches in the arms on both
ends of the joint bracket.
8. Fasten the lock bar by re-attaching the screw removed in Step 4. ( x1).
9. Attach the I/F cable [D] to the upstream unit.
SM 3-187 D074/D075/M044
High Capacity Stacker (D515)
Lock Hasps
D074/D075/M044 3-188 SM
High Capacity Stacker (D515)
Height Adjustment
Installation
1. Set the leveling shoes [A].
2. Adjust the height of the unit and make sure that it is level.
In China, do not use this power cord provided with this unit's accessories. Contact
your supervisor and use the power cord specified for use in China.
2. Set the leveling shoes and adjust the height of the unit. ( p.3-218)
3. Load some B4 paper in the 2nd tray of the main machine, and make several copies.
4. Check paper skew and side-to-side registration and correct if necessary. ( p.3-220)
SM 3-189 D074/D075/M044
High Capacity Stacker (D515)
Docking: Downstream
1. Align the holes in the brackets of the paper tray [A] with the studs on the tray base [B].
2. Set the holes over the studs.
3. Set the paper press lever [C] into the recessed cut-out in the paper tray.
4. Insert the ends of the tray cart handle [D] into the handle holes. One end of the handle
passes through the paper press lever on the paper tray.
D074/D075/M044 3-190 SM
High Capacity Stacker (D515)
Installation
6. Fasten the end of each handle ( x 1 each, M10x25).
7. Make sure that both screws [E] are fastened securely.
8. Set the cart upright on its casters.
SM 3-191 D074/D075/M044
Finishers (D512/D513)
3.12.1 ACCESSORIES
Check the quantity and condition of the accessories in the box against the following illustration
and list.
5. Leveling Shoes 4
6. Ground Plate 1
D074/D075/M044 3-192 SM
Finishers (D512/D513)
7. Power Cord*1 1
8. Joint Bracket 1
9. Sponge Strip 1
Installation
13. Auxiliary Tray – Coated Thin Paper 1
*1
: In China, do not use this power cord provided with this unit's accessories. Contact your
supervisor and use the power cord specified for use in China.
3.12.2 INSTALLATION
The unit must be connected to a power source that is close to the unit and easily
accessible.
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedure.
The shipping plates prevent the staple unit from moving during transport. The plates
should be kept and re-attached before the unit is transported to another location.
SM 3-193 D074/D075/M044
Finishers (D512/D513)
1. Remove all tapes and packing material from the external coves.
D074/D075/M044 3-194 SM
Finishers (D512/D513)
Installation
4. Loosen the screws of the caster cover [A] ( x2).
5. Push the caster [B] down until it touches the floor.
6. With the caster touching the floor, tighten the caster cover screws.
This prevents the unit from tipping over when you pull out the staple unit.
7. Grip handle [A] and slowly pull the staple unit out until it stops.
8. Remove:
[B] All tapes, retainers
[C] Tag, wire, shipping plate ( x2)
[D] Tag, wire, shipping plate ( x2)
9. Re-attach screw [E] where it was removed.
SM 3-195 D074/D075/M044
Finishers (D512/D513)
10. Remove:
[A] Tapes, retainer
[B] Tapes
1. Attach the ground plate [A] to the bottom right edge of the unit ( x2 M3x6).
D074/D075/M044 3-196 SM
Finishers (D512/D513)
Installation
2. Attach the paper guide [A] ( x2 M3x6).
3. Peel the tape from the sponge strip [B] and attach the strip to the top right edge of the unit.
Procedure 2
1. Attach the paper guide and ground plate as described in "Procedure 1" above.
2. Remove the tape from each sponge strip and attach them to the right side of the unit as
shown above.
The two yellow sponge strips in the illustration are provided as accessories with
the main machine. The horizontal sponge strip is provided with the Finisher.
3. After attaching all sponges, use a sharp cutter to cut the sponge on the corner at [A].
SM 3-197 D074/D075/M044
Finishers (D512/D513)
1. Attach the booklet tray [A] to the notch in the left cover (no screws).
2. Attach the shift tray [B] to the left side of the unit ( x4 M3x8).
Docking
D074/D075/M044 3-198 SM
Finishers (D512/D513)
Installation
2. Open the front door [A] of the unit.
3. At the front right corner, remove the screw of the lock bar [B] ( x1 M3x6). Keep this
screw.
4. Pull the lock bar toward you until it stops.
5. Slowly push the unit [C] to the left side of the upstream unit (or main machine) so that the
lock bar is directly and squarely under the arms of the joint bracket [D].
6. Attach the I/F cable [E] to the upstream unit.
SM 3-199 D074/D075/M044
Finishers (D512/D513)
13. Fasten the lock bar by re-attaching the screw removed in Step 3. ( x1)
14. Remove:
[A] Rear upper cover (Capsx2, x5)
[B] Rear lower cover ( x4)
D074/D075/M044 3-200 SM
Finishers (D512/D513)
Auxiliary Trays
1. Instruct the operator about when to use these auxiliary trays, as explained below.
Installation
Before feeding glossy paper, pull out the extension [A] of the shift tray and mount the
glossy paper auxiliary tray [B].
Before feeding Z-folded paper from the Multi Folding Unit, set the Z-fold auxiliary tray
[C] on the shift tray.
Before feeding coated thin paper from the Multi Folding Unit, set the coated thin paper
auxiliary tray [D].
In China, do not use this power cord provided with this unit's accessories. Contact
your supervisor and use the power cord specified for use in China.
2. Set the leveling shoes and adjust the height of the unit. ( p.3-218)
3. Load some B4 paper in the 2nd tray of the main machine, and make several copies.
4. Check paper skew and side-to-side registration and correct if necessary. ( p.3-220)
SM 3-201 D074/D075/M044
Finishers (D512/D513)
Accessories
Check the quantity and condition of the accessories in the box against the following illustration
and list.
2. Punch Unit 1
6. Punch-out Hopper 1
7. Harness: Long 1
9. Spring 1
D074/D075/M044 3-202 SM
Finishers (D512/D513)
3.12.4 INSTALLATION
Make sure that the main machine is switched off and that its power cord is
disconnected before doing the following procedure.
Shipping Materials
Installation
1. Remove motor protector plate [A] ( x4).
Rear Cover
SM 3-203 D074/D075/M044
Finishers (D512/D513)
D074/D075/M044 3-204 SM
Finishers (D512/D513)
Installation
4. Insert the harness connectors [A] through the hole [B].
5. Make sure the harness connectors are through the hole completely and visible at the rear
of the machine.
6. Set and fasten the punch registration unit [C] ( x4, 2 screws each at front and back).
SM 3-205 D074/D075/M044
Finishers (D512/D513)
D074/D075/M044 3-206 SM
Finishers (D512/D513)
2.
3. Attach the punch mechanism [A] to the rails of the punch unit ( x1).
If you are installing the punch unit for Europe [1], connect the harness [B] ( x1,
Installation
x2).
The punch unit for North America [2] has no punch switching motor, so this harness is
not required.
4. At the front, insert the punch unit [A] into the finisher and fasten it ( x4).
5. Remove the shoulder screw with red tag [B], and detach the tag and wire.
6. After removing the screw from hole , re-attach it at hole .
SM 3-207 D074/D075/M044