You are on page 1of 7

2000 AACE INTERNATIONAL TRANSACTIONS

CDR.09

The Window Methods of


Analyzing Delay Claims

George E. Baram, PE CCE

elay and schedule analyses are addressed heav- contracts, and contractors are appreciating more and more

D ily in many publications, literature, and books,


with many different techniques, methods, and
procedures, all for the purpose of finding the
delay and its effect on a project.
Generally, one can categorize all of these methods or
the value and benefits of using these methods on their proj-
ects.
Although the natural objective use of the CPM as a tool
is to run and control ongoing projects, it can be used in ret-
rospect on completed projects with proper historical (as-
techniques into two major categories: a forward approach built) data and properly reported progress.
and a backward approach. The forward approach starts The key issues that made the CPM a credible approach
from the beginning of the project (say the first available or to be used on ongoing projects are the same ones that justi-
approved schedule) and continues forward toward the end fy using it on completed projects.
of the project using the available data and schedules.
Examples of these methods are the impacted as-planned, • The forward future approach in the look-ahead
the entitlement schedule, the as-planned versus as-built planned period.
comparison, and the different Window methods, which will • The ability to project and modify the planned period.
be described in this article. • The ability to perform the above two items in and for
In the other category, the backward approach, the ana- different periods—as often as needed (monthly, weekly,
lyst starts from the end of the project and moves backward bimonthly).
toward the beginning of the project using mainly the as- • The ability to modify and adjust the network (both
built information. This as-built information can take the minor and major adjustments) to reflect actual changes
shape of an as-built schedule, which is supposed to reflect in sequence of erection, resources, changes, and extras.
the actual sequence and duration of the tasks described. • The ability to create an integrated cost/resource/sched-
Examples are the collapsed method (collapsed as-built) and ule model that can be used to track progress and per-
the but-for method. formance.
There are many pros and cons associated with each of
these approaches, and many claim analysts and practition- In summary, the CPM schedule is dynamic in nature
ers agree very little on which method is superior to the oth- because it changes continually. As will be described later,
ers, needless to say also as to its application. the window methods of delay analysis are best suited to sat-
In fact, one cannot generalize on the superiority of any isfy the above crucial issues.
of the previously mentioned methods. Every one of these
has its own merit and justification. However, the credibility
and acceptability in adopting a technique lies in applying it The Window Methods—General
to the case at hand in an objective and factual manner. Simply put, the objective of any window method of
The focus of this article is on the window based meth- delay analysis is:
ods of delay analysis, their similarities and differences, as
well as their applications. a. to reconstruct the progress on a project in predeter-
mined time frames (window periods) in accordance
with the planned schedule;
Why Window Methods? b. to measure it against an established threshold; and
The evolution and acceptance of the CPM technique c. to assess or evaluate the differences.
in handling construction projects is presently at its highest
level. Owners are requesting the use of the CPM in their The two major entities (legal entities) used in perform-
CDR.09.1
2000 AACE INTERNATIONAL TRANSACTIONS
ing a window-based delay analysis are the as-planned sched- Some circumstances may require more or less criteria
ule and the as-built schedule. However, there are different than the above to be satisfied, but in general these are the
ways of presenting these elements in addition to arguing prerequisites for a valid as-planned schedule in a delay
their acceptance. analysis.
The other entry required in performing any of the win- As-planned schedules used throughout the progress of a
dow techniques is the progress achieved during the course project are usually produced in the form of schedule
of the project, within periodical time frames. This includes updates at the end of every month. Each schedule update
actual start and completion dates of performed tasks, the represents the status of the job at the cut-off date (data date),
percentage of completion, and any incidents or delays that in terms of historical data (actual dates and percentages
interrupted or hindered the performance (strikes, extra completed), and the projected period as anticipated by the
work, stop work, etc.). contractor in terms of new estimated duration and logical
In the following section, a brief review on the entries connections.
commonly required to perform a window based delay analy- As-planned schedules should be checked and verified
sis will be introduced, along with the pros and cons of using to satisfy the above mentioned criteria. The next step is to
them properly. evaluate the validity of the resulting critical path in the final
prepared CPM schedule. This requires some experience on
the part of the analyst in the type of project, and probably
Window Methods—Common Input and Steps to Follow consultation with the client (contractor or owner), keeping
• Evaluating and preparing the as-planned schedule; in mind that the validity and reasonability of this critical
• development of the as-built schedule; path has to be defended.
• identifying and quantifying known delays; and
• identification of significant milestone dates (window
periods). A Word About the Use of Constraints
A very common issue in today’s construction schedul-
ing is the use of constraints, sometimes called plugs, in
Evaluating and Preparing the As-Planned Schedule scheduling certain activities. This problem became very
The planned schedule used for a specific window peri- common due to the availability of sophisticated comput-
od is most credible if it reflects the planned sequence and erised scheduling software. Such tools allow the user to
duration for the period itself. This window baseline, some- schedule as a bar-chart-schedule, by forcing some activities
times called the then current schedule, may be available in to start and complete on a certain date(s). This is in contrast
a CPM electronic form as an update at certain point. to real or natural CPM scheduling, where the logical con-
Otherwise, it has to be reconstructed from contemporane- nections along with the duration of the activities decide
ous relevant schedule documents [1, 2, 4, 7]. when each activity should start and be completed.
Selecting and agreeing on the as-planned schedule as a Some of the constraints are valid, such as dates of mate-
basis of the delay analysis is a major first step in conducting rial or equipment delivery, winter constraints, etc. Other
a window-based delay analysis. There are certain considera- types of constraints may distort the networking nature of the
tions the analyst has to take into account in accepting and CPM if applied improperly, such as late constraints or
preparing the as-planned schedule. This topic has been cov- mandatory start or finish, or even total float or free float con-
ered extensively in many related publications, including two straints. These constraints usually yield unclear, illogical
of the author’s [1, 2, 6], however, the following is a summa- positions of some activities with a totally misleading artifi-
ry of the important items that the analyst should consider cially forced critical path and erroneous float calculation. It
during this process: is beyond the scope of this article to discuss the effect of arti-
ficial constraints and their alternatives [2]. These are usual-
• it must be agreed upon by both parties; ly documented in the manual of the utilized scheduling
• it must be substantiated; software.
• it must be complete; However, contractual constraints should be used in
• it must reflect the intended plan of executing the job by preparing the as-planned schedule or updates. These are
the contractor; mainly interim or agreed upon milestones, procurement,
• it must be supported by source documents; weather, or resource related constraints.
• it must be error free in terms of logical connections
and/or duration of activities; and
• it must reflect the contractual agreement (milestones). Constructing the As-Built Schedule
Whether it is compiled from many available contem-
Many of the above cited points are self-explanatory, poraneous documents, or from schedule updates, the as-
with the exception of the last two items, where the analyst built time line should reflect the actual sequence of work
may require certain skills in dealing with them, for example, that took place on the project. There are many challenges
a clear error or mistake in the logical sequence or duration and difficulties in producing a credible as-built schedule
has to be corrected and reported in the analysis. that can be used for the window based delay analysis.
Similar to the as-planned schedule and due to the limited

CDR.09.2
2000 AACE INTERNATIONAL TRANSACTIONS
scope of this article, the following recommendations are to Identification of Significant Milestone Dates (Window
be considered when preparing the as-built schedule [1, 4, Periods)
5]: The selection of dates to represent the cut-off times that
divide the project into segments is very crucial to success-
• it must be substantiated; fully establishing the delay in the project and later on eval-
• it must be complete; uating its causes and effects. The selection should be made
• it must reflect the facts; with the intent to isolate the major known problems. These
• it must be supported and backed up by the proper doc- would typically include the following.
uments; and
• it must match (to a reasonable degree) the as-planned • Before and after the issuance of a major change or
schedule. group of changes that may have an effect on the com-
pletion of the project (giving rise to extra work, suspen-
Care and objectivity are needed in linking the as-built sion of work, etc.).
to the as-planned schedule (scope of work, resources used, • The time of major known delay or delays (start and end
and extras). of the delay).
The as-built schedule can be constructed from the fol- • Issuance of a major schedule revision (major changes
lowing sources: in duration and/or logic, addition and/or deletion of
activities, etc.).
• daily foremen/superintendents’ diaries; • Before and/or after a force majeure event (strike, flood,
• daily timesheets; earthquake, etc.).
• minutes of project meetings; • Before the onset and at the end of severe climate con-
• schedules, updates, and progress reports; ditions (severe winter, rainy season, etc.).
• cost reports; and • Before and/or after the issuance of an acceleration
• other (correspondence, letters, and memos). order (giving rise to an increase in workforce, overtime,
double shift, etc.).
Based on the schedule update breakdown and descrip-
tion of every activity, the actual start and completion of The above are some examples generally applied in the
every activity should be extracted from the previously men- selection of a window period. The circumstances and events
tioned sources, along with any interruption and/or stoppage that actually take place during the job progress and their rel-
of work in the activity, to then be plotted on a daily or week- evance to the delay will dictate a better, more useful period
ly time scale. selection.
The final output of integrating all of the above sources
is a detailed as-built schedule broken down by activity level
details matching the as-planned (or updates), that can then THE WINDOW METHODS
be used to perform the mechanics of the window analysis,
as well as to assess any delays incurred within certain win-
dow periods. The Window Snapshot Analysis Method
The snapshot analysis technique consists of two major
steps: the first is to determine the amount of delay that
Identify and Quantify Known (Agreed Upon) Delays occurred on a project, and when the delay occurred; the
Depending on the case and the availability of informa- second is to determine the cause or causes of the delay.
tion, delays may already be known to the players (owner, The analysis uses the available schedules (mainly from
contractor, etc.) and agreed upon in terms of their accept- the contractor), called original or as-planned schedules, the
ance and duration. Examples are strikes, stop work orders, actual or as-built schedule as it is compiled from different
delays in delivery of major equipment, etc. In other cases, sources (as explained earlier) and any revised schedules that
delays may be embedded in activity duration in the form of may have been issued and/or used during the execution of
stretched and long duration where the cause of the delay the project.
and the delay period itself may be unknown. This could be In order to analyze the delays (or acceleration) on a
a delay resulting from slow performance, loss of productive project, the project duration is divided into a number of
work, or a sequential delay to a previous known/unknown time periods (windows). For each time period, the amount
delay, etc. of delay that occurred is determined and the causes of the
The objective of any delay analysis, whether it is win- delay are then assessed.
dow or non-window based, is to find the delay, quantify it, The breakdown of the project duration into time peri-
determine its effect on other work, and apportion or allocate ods is achieved through the selection of a series of dates.
responsibility to the party causing the delay. Each date represents the end of one period and the begin-
Knowing the delay up front may save a lot of effort and ning of the subsequent period. The dates are selected to
may justify using different methods that fit the case. coincide with major project milestones, including the
implementation of significant changes in planning, in order
to isolate major known delays or group of delays.

CDR.09.3
2000 AACE INTERNATIONAL TRANSACTIONS
Generally, the planned completion date, according to nation of the snapshot’s window period should be made to
the schedule in force at the beginning of a period, is com- determine the slippage, delays, or extended duration
pared with the projected completion date at the end of that incurred within this window and to assess its effect or possi-
period, giving rise to the delays (if any) in the interim. The ble effect on the overall project.
difference between these dates is the delay to the project The next step is to back-up the findings by using:
that occurred during the period. Once the length of the
delay that occurred during the period is known, its causes • provided as-built information;
are assessed. • correspondence;
If the updated schedule is no longer considered valid • drawings log and turnaround time;
because of changes in planning, then the schedule is • costing records;
accordingly revised and this revised schedule is used for the • Workhours (worker data); and
subsequent period. The difference between the completion • others.
dates projected by the updated schedule and the correspon-
ding revised schedule is an indication of the amount of This can be achieved through a detailed narrative
acceleration (or relaxation) achieved by the changes in explanation of every delay detected or examined within the
planning. window period, supported (if needed) by a detailed state-
This procedure should be repeated for the number of ment of facts to substantiate the conclusions.
snapshot dates (or periods) selected, and for every period the
resulting delay, acceleration or on-time progress is evaluat-
ed in a second phase, assessing the result of the analysis. The Window Time Impact Analysis (TIA)
This method is based on the analysis of delaying events
at the time they occur. Hence, there are two crucial differ-
Steps to Follow ences between this technique and the above mentioned
• Based on the schedule updates and the frequency of snapshot technique.
their availability, determine the time frame periods The first difference is that in the case of TIA, the iden-
(usually 1 to 2 months). tification and quantification of the delay-causing events
• Start with the schedule update available at the begin- should be made before performing the analysis. The delay
ning of the examined project time frame and consider analysis will be restricted to determining the effect of these
it as the first as-planned schedule for the first period events.
(provided that prerequisites for a valid as-planned The other important difference is in the selection of the
schedule are satisfied as per the earlier section on eval- window periods. In the snapshot method, the windows are
uating and preparing the as-planned schedule). determined by the availability of a schedule update at the
• Copy the schedule update available at the beginning of end of each period, while in this approach it is the delaying
the period. event itself that dictates the beginning or the end of a peri-
• Status the copy created above at the end of the period od.
from the information available in the next schedule The TIA approach calls for inserting a delaying event or
update. events (if within a reasonably short time frame) into a status
• Run the new schedule at the end of the period—the schedule, that reflects the status of the project at the specif-
result is a snapshot schedule. ic time of these events. A concern arises here, since the sta-
• Compare the resulting snapshot schedule at the end of tus schedule is usually not contemporaneously available
the period with the planned schedule (update) at the (unless a delaying event coincides with a schedule update).
beginning of the same period. However, the status schedule is probably constructable from
• Examine and assess the resulting delays (as described in contemporaneous documents.
the following section).

Steps to follow
Assessing the Delays Resulting From the Snapshot • Assemble a list of delay-causing events in chronological
Analysis order—identify the type of delay for each (excusable,
Assessing delays for the window periods is not a matter compensable, etc.).
of mechanics or science that can be automated. It relates to • Select the as-planned schedule that corresponds to the
the facts and circumstances surrounding the progress of the first delay-causing event.
project and it differs from one project to another. In gener- • Update or status the above as-planned schedule at the
al, it requires the analyst to familiarize himself/herself with time of the first delay-causing event starts—this is the
the job, understand it, and address the incidents and/or status schedule.
problems that occurred within the examined period in a • Insert the first delay-causing event into the status sched-
comprehensive fashion. ule and run the schedule—this is the impacted status
As a general guideline, the analyst should examine all schedule.
delays resulting from the snapshot period and explain each • The difference between the resulting completion dates
one in terms of cause and effect. In other words, an exami- of the impacted status schedule and the status schedule

CDR.09.4
2000 AACE INTERNATIONAL TRANSACTIONS
(if any) is the result of the inserted event. the pure comparison of two schedule updates within a given
• Repeat the process for the other events. time frame. One represents the planned schedule for select-
• Sum up the results. ed activities at the beginning of the period and the other
represents the as-built schedule for the same selected activ-
The success of this method is dependent on employing ities, within the same period.
it contemporaneously and at the time the delay event The selected activities are usually the critical and near
occurred. In other words, it is much easier to establish the critical activities extracted from the planned schedule. The
status of the job from available documents on an ongoing corresponding as-built is usually generated from the avail-
project than on a completed project. However, this method able contemporaneous documents including schedule
is widely used as an after-the-fact approach and is being updates.
accepted as the preferred approach in many jurisdictions Although it appears to be a very simple and straightfor-
and on many cases [7]. ward approach using the CPM critical path using the
The resulting effect of any inserted delay-causing event updated schedules (hence the dynamic nature is consid-
will be compared to the status schedule for the final assess- ered). It has some hidden assumptions and drawbacks that
ment within a specific period. The approach for the assess- may require the analyst to revise and sometimes reverse
ment the delay(s) is similar to what was described in the his/her course.
snapshot section. For example, by relying heavily on the planned critical
TIA is a very credible and manageable technique if path and adopting it throughout the window period, one is
applied to small projects with a limited number of delay assuming that the critical path is fixed for the whole period.
events. However, it may become very difficult, if not impos- This may be true if critical paths are the same at both the
sible, when applied on large networks with many delaying beginning and the end of the examined period, a rare case.
events (excusable or non-excusable). This method treats delay analysis more as a science
than as an art. The acceptance and credibility of this
approach lies in the critical path being approved as the
The Window Impacted Then Planned Schedule actual, real or followed, critical path [8].
This method is a modification or revision to the popu- Its best application may be in cases where little or no
lar and traditional method called impacted as-planned shift in the critical path took place or in cases where sched-
schedule or sometimes schedule entitlement method. ule updates are available within very short periods, as week-
In this approach, only a window impacted planned ly or biweekly look-ahead schedules.
period is examined as opposed to the traditional approach
that adopts the construction project as one large window
covering the whole period. This modified version segments The Window As-Built But-For Analysis
the total period into smaller ones, allowing for the use of One of the easy to explain and understand methods of
intermediate schedule updates which reflect the real plan analysing delay is the but-for technique [2, 4, 8]. Although
and status and the dynamic nature of the schedule. there are many arguments for and against using this tech-
In summary, it uses the as-planned schedule update for nique, it is still a broadly used and very much alive method.
a given period and effects it with the available delay-causing In summary, the purpose of this technique is to find out
events for the same period. the effect of one party’s portion of the total delay to the
In a sense, it is very similar to the time impact analysis schedule, leaving the rest of the delay to the other party. In
method, except that we do not have to produce a status other words, but-for the owner-caused delay, the contractor
schedule at the time the delay-causing event took place. On would have completed the project on time (or on a specific
the other hand, the drawback is the limitation imposed by date).
the frequency of schedule updates, that may or may not If this technique is applied to the total period of the
coincide with a delay event. The examined window closes at project, with all the delays of one or the other party taken
the beginning of the next window with the availability of a into account, why not apply it in a periodical fashion. One
new schedule update. would isolate a window period and construct the as-built for
This approach is best used for inserting a group of that period, then collapse the delay(s) (say owner-caused
delay-causing events (if related and within a reasonable time delays) that took place within the same period. The differ-
frame coinciding with the examined window) into one ence between the completion date resulting from this col-
schedule and assessing its effect, as a group of say, excusa- lapsed schedule and the completion date of the schedule in
ble/compensable delays, on the completion of the schedule. effect for that period is the contractor’s responsibility.
Its application and procedure (steps to follow) is very Easier said than done. In fact there are many technical
similar to the TIA method. difficulties and assumptions made in this approach. This is
true whether it is used for the total project or for a specific
window period.
The Window Direct Critical and Near Critical Path First of all, the establishment of the as-built schedule,
Comparison in matching details to the planned schedule for the same
An interesting approach used and published recently period, is not an easy task. Then, there is the challenge of
under the window method of delay analysis umbrella [5] is collapsing the schedule based on the actual critical path for
the period. Here the analyst is dealing with the historical
CDR.09.5
2000 AACE INTERNATIONAL TRANSACTIONS
period (as-built), and to collapse a historical period one has c. the skills of the team or the analysts in applying the
to reverse it into a projected period with the historical data technique; and
fully projected in it as if it were planned data. This has to d. last but not least, the presentation itself, whether it is
be done in order to calculate a more reasonable critical path prepared as a first phase settlement negotiation or as a
that reflects the actual data. This requires a lot of subjective final report to a panel of experts, judge, jury, DRB,
input in terms of logical connections, revisions, and scope mediation or others.
changes that took place within the window [8].
In any of the methods explained in this article, a rea-
sonable and fair analysis should be based on the available
Combining TIA and the Snapshot Techniques facts, objectivity, fair and documented assumptions (if any),
This method is more like a global apportionment complete and impartial analysis, and consideration for actu-
approach within a window period than a pure delay analysis al progress and sequence of work.
technique. The window based techniques, if applied properly, sat-
In summary, this approach uses a combination of the isfy the above expectations.
window snapshot analysis at the end of the examined period
and the time impact analysis at the beginning of the period
[3]. These are two of the most credible and acceptable REFERENCES
techniques.
1. Baram, G.E. Construction Claims—Documenting and
Presenting the Facts. 1992 AACE International
The Steps Transactions, Morgantown, WV: AACE International,
a. The snapshot at the end of the examined window peri- 1992.
od reflects the total progress achieved at the end of the 2. Baram, G.E. Construction Delays—Issues Not to Be
period, with all delays, interruptions, and changes that Taken For Granted. 1994 AACE International
actually took place during the period. Hence, the total Transactions, Morgantown, WV: AACE International,
delay resulting from the snapshot is the responsibility of 1994.
all parties who performed work within the period, 3. Baram, G.E. Concurrent Delays—What Are They and
including owner-caused delays. How To Deal With Them? 2000 AACE International
b. Delays, say owner-caused delays, are compiled from dif- Transactions, Morgantown, WV: AACE International,
ferent source documents including schedules, minutes 2000.
of meetings, daily logs, etc. Then, each and every one 4. Bramble, B.B, and M.T. Callahan, editors.
of these delays is allotted to an activity on the schedule Construction Delay Claims. John Wiley & Sons,
(in some cases it can be added as a new activity or part 1987.
of an inserted fragnet). 5. Pickavance K. Delay and Disruption in Construction
c. The next step is to affect the baseline schedule at the Contracts LLP, 1997.
beginning of the period with the owner-caused delays. 6. Popescu, C. Selecting As Planned Base in Project
This can be achieved through proper integration of the Disputes. 1991 AACE International Transactions,
owner’s identified delays to the schedule. Morgantown, WV: AACE International, 1991.
d. The results of this window time impact will give the 7. Wickwire, J.M., T.J. Driscoll, and S.B. Hurlburt, edi-
total duration of all the owner-caused delays within the tors. Construction Scheduling: Preparation, Liability,
examined window. And Claims. John Wiley & Sons—Construction Law
e. The difference in completion dates between d and a Library, 1991.
above is the contractor’s portion of the total delay with- 8. Zack, J.G. Jr. But-For Schedules—Analysis and Defense
in the window. 1999 AACE International Transactions, Morgantown,
WV: AACE International, 1999.

t has often been said that the credibility in using a

I delay analysis technique is in applying it. Although


the focus in this article was on the window based
techniques, there are some other methods and proce-
dures that can be credibly used.
Choosing one method over another depends on many
George E. Baram, P.Eng. CCE
Revay and Associates Limited
4333 St. Catherine St. West, Suite 500
Montreal, Quebec, Canada H3Z 1P9

factors, including: E-mail: gebaram@total.net

a. the availability of the information (detailed and com-


plete as opposed to summary and incomplete informa-
tion);
b. the size and complexity of the project and the related
network, and the time limitations in performing the
analysis (hence the cost involved);
CDR.09.6

You might also like