Operation Manual Chapter 2 Preparation for Operation

2.2 Start of Machine


1. Start of Machine
1) Turn the power breaker (CB1/CB0) to ON.

2) Turn the Control Power switch (SW10) to ON.

3) Perform a startup inspection for turning the servos ON. Check all items, press the [Check
All] button and then the [END] button.

4) Press the [Servomotor] button. (Start of motor)

5) Press the [Barrel Heater] button. (Energization of the heater is started.)

J-ADS 2-3
2. Checking the Mechanical Safety Device
1) Make sure that the message [Door Open] appears on the controller
screen when the operation side safety door is open. (When [Stopper is
not actuated] is indicated, check the shutter visually.)

3. Checking cooling water


1) Open the cooling water valve.
2) Check that no water leaks from the piping.

No. Name
1 Cooling water valve
4. The heating barrel is heated up to a molding temperature 20 to 30 minutes
after the [Barrel Heater] button is pressed.
1) Confirm that the [Cold-ST Prev] indication lamp is turned on. The cold
start prevention is cleared after the heating barrel is heated up for 25 to
30 minutes.