Professional Documents
Culture Documents
On September 16, 2010 TVA released a Draft IRP for public review and
comment.
After 3 months of refining the IRP’s proposed strategy, TVA released its
final Integrated Resource Plan on March 4, 2011.
TVA’s Board of Directors is scheduled to adopt the IRP at the April 14th
Board meeting.
TVA has committed to reiterating the IRP process no later than 2015.
What is Integrated Resource
PAGE 2
Planning (IRP)?
• Modeling process used by utilities to determine:
– The best possible mix of supply side (such as new power
plants) and demand side (such as energy efficiency)
resources to meet future energy demand at the least cost
and least risk.
Through the SRG, SACE provided input into several aspects of the IRP
process, including:
How aggressively TVA should invest in energy efficiency;
Whether TVA should idle coal-fired generation in favor of investing in costly
pollution control measures;
How aggressively TVA should be pursuing renewable energy resources;
Whether increased nuclear capacity is a necessary part of TVA’s future
generation requirements.
Resource planning in a nutshell:
Fossil Asset – No fossil fleet reductions – 2,000 MW total fleet – 3,000 MW total fleet – 7,000 MW total fleet – 5,000 MW total fleet
Layup reductions by 2017 reductions by 2017 reductions 2017 reductions by 2017
– No new additions – Same as Planning – Add one pumped storage – Same as Planning – Same as Planning
Energy Storage
Strategy A unit Strategy C Strategy A
– No new additions after – First unit online no earlier – Same as Planning – Same as Planning – First unit online no earlier
WBN2 than 2018 Strategy B Strategy B than 2022
Nuclear – Units at least 2 years apart – Units at least 2 years apart
– Additions limited to 3 units
– No new additions – New coal units are outfitted – Same as Planning – Same as Planning – No new additions
with CCS Strategy B Strategy B
Coal – First unit online no earlier
than 2025
Gas-Fired Supply – No new additions – Meet remaining supply – Same as Planning – Same as Planning – Same as Planning
(Self-Build) needs with gas-fired units Strategy B Strategy B Strategy B
– No limit on market – Purchases beyond current – Same as Planning – Same as Planning – Same as Planning
Market purchases beyond current contracts and contract Strategy B Strategy B Strategy B
Purchases contracts and contract extensions limited to 900
extensions MW
– Potentially higher level of – Complete upgrades to – Increase transmission – Same as Planning – Potentially higher level of
transmission investment to support new supply investment to support new Strategy C transmission investment to
support market purchases resources supply resources and support renewable
– Transmission expansion (if ensure system reliability purchases
Transmission needed) may have impact – Pursue inter-regional – Transmission expansion (if
on resource timing and projects to transmit needed) may have impact
availability renewable energy on resource timing and
availability
• EE/DR and renewable inputs were “unhinged,” allowing the model to choose among
the various packages.
The Final IRP’s key directives:
Component Range provided Timeframe
Coal Capacity Idled 2,400 – 4,700 MW By 2017
In almost every case, the difference between idling 2,400 MW and 4,700 MW is less
than 5% in the respective cost or risk metric. In several instances, this difference
actually favors higher levels of coal-fired idling
Pursuing 4,700 MW of coal-fired idling does not to add significant levels of either
cost or risk to TVA’s long-term strategy.
Issue: Renewable Energy
• The Final IRP completely misses the mark on
renewables, recommending between 1,500 and 2,500
MW of renewable energy by 2020.
Solar 3% 75 MW
Landfill Gas 1% 25 MW
Cofiring 5% 125 MW
• Example: TVA has input excessively high cost estimates for RE resources.
– TVA’s estimated cost of in-Valley solar is approximately 30 cents/kWh,
nearly twice what we’re seeing for large solar installations.
• Example: TVA did not consider well-documented declining cost trends for
renewables.
• Based on these estimates, the difference between 11,400 GWh and 14,400
GWh in 2020 equates to:
– Approximately 1,500 MW of additional avoided capacity needs
– Approximately $174 million in additional customer savings in 2020 alone
• This includes the 1,150 MW Watts Bar Unit 2 that is expected to come
online in 2013.
• After Watts Bar, Bellefonte units 1 and 2 could come online in between
2018 and 2022.
• Under high-growth scenarios, the IRP would add potentially two more,
supposedly AP100 model, nuclear reactors in 2024 and 2026.
• The IRP simply does not make the case that TVA needs to assume the
costs and risks associated with expanding its nuclear portfolio.
Anticipated capital expenditures to add nuclear
capacity beyond Watts Bar 2
Capitol 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Total
($MM)
BLN1 $205 $158 $149 $623 $775 $773 $938 $666 $452 $98 $4,836
BLN2 $76 $312 $505 $585 $637 $685 $583 $345 $3,728
Total $205 $158 $149 $699 $1,087 $1,278 $1,523 $1,303 $1,137 $681 $345 $8,564
• TVA is concerned that it may lose valuable nuclear crews if they can’t be
rolled directly from WB to BLN.
• Because BLN reactors are a 40-year old design that has never been
licensed in the US, the NRC may not approve construction of this design
beyond 2020.
• Additional resource:
– www.cleanenergy.org
– www.tva.com/environment/reports/irp/index.htm
This presentation was brought to you by