PROGRES PROJECT NODE B RIDAR ( BANGKINANG )

SEGMEN 2 ( CL-288 - JT 08 & JT 03 - BKG 195 )

Volume
No Jenis Pekerjaan Satuan Keterangan
Plan Realisasi
1 DD BM HDPE & DD-BM-HDPE m 3830 2830 CL-288 - JT 01
2 DD BM HDPE & DD-BM-HDPE m 3822 3822 JT 01 - JT 02
3 DD BM HDPE & DD-BM-HDPE m 766 766 JT 02 - JT 03
4 DD BM HDPE & DD-BM-HDPE m 2724 2724 JT 03 - JT 04
5 DD BM HDPE & DD-BM-HDPE m 3800 3800 JT 04 - BKG 195
6 DD BM HDPE & DD-BM-HDPE m 3040 3040 JT 03 - JT 05
7 DD BM HDPE & DD-BM-HDPE m 3835 3835 JT 05 - JT 06
8 DD BM HDPE & DD-BM-HDPE m 3806 3806 JT 06 - JT 07
9 DD BM HDPE & DD-BM-HDPE m 2688 2688 JT 07 - JT 08
TOTAL 28311 27311

1 DC-OF-SM-96D m 2830 0 CL-288 - JT 01


2 DC-OF-SM-96D m 3822 0 JT 01 - JT 02
3 DC-OF-SM-96D m 766 0 JT 02 - JT 03
4 DC-OF-SM-24D m 2724 0 JT 03 - JT 04
5 DC-OF-SM-24D m 3800 0 JT 04 - BKG 195
6 DC-OF-SM-96D m 3040 0 JT 03 - JT 05
7 DC-OF-SM-96D m 3835 0 JT 05 - JT 06
8 DC-OF-SM-96D m 3806 0 JT 06 - JT 07
9 DC-OF-SM-96D m 2688 0 JT 07 - JT 08

TOTAL 27311 0

1 HH 2 JT 08 - JT 07 bh 1 0 SEGMEN 2
2 HH 2 JT 07 - JT 06 bh 1 0 SEGMEN 2
3 HH 2 JT 06 - JT 05 bh 1 0 SEGMEN 2
4 HH 2 JT 05 - JT 03 bh 1 0 SEGMEN 2
5 HH 2 JT 03 - JT 04 bh 1 0 SEGMEN 2
6 HH 2 JT 03 - JT 02 bh 1 0 SEGMEN 2
7 HH 2 JT 02 - 01 bh 1 0 SEGMEN 2

TOTAL 7 0

1 TC-SM-12 BKG 195 bh 1 0 SEGMEN 2

TOTAL

1 SC-OF- SM-96D Bh 6 0 BKG 043


2 SC-OF- SM-24D Bh 1 0 BKG 195
3 SC-OF- SM-48D Bh 1 0 BKG 195
TOTAL 8 0

SEGMEN 2 ( BKG
1 DD-DA-S1 m 25 25 043 (JT 1-JT 08) &
BKG 195) )

SEGMEN 2 ( BKG
1 DD-BSS-S1 m 663,4 245 043 (JT 1-JT 08) &
BKG 195) )
4