CONSTRUCTION OF PHCC NGELSHENGELE

& MEDICAL OUTREACHES


ACTIVITIES FOR 8 MILESTONES

Milestone Activity Expected Progress Milestone Activity Details

1 a. Produce Needs Assessment Report a. Assessment of communities and people in Fune


Needs and Gujba LGA in YOBE State.
Assessment b. Health needs assessment of named communities
c. Assessment of PHCC structure in Ngelshengele
d. Assessment of sanitation facilities and current
hygiene practices.
e. Analysis of the nutrition situation of IDPs and host
communities in Fune and Gujba LGAs
f. Psychosocial needs assessment
a. Stakeholder engagement
Stakeholder b. Letter of acceptance from Yobe State Govt a. Identify and engage existing community-based
Engagement received via Primary Healthcare Board structures (NGOs) and relevant stakeholders in the
communities
b. Collaboration meetings with existing
community-based structures and relevant
stakeholders in the communities, including:
i. Executive Secretary, Yobe State Primary
Healthcare Management Board
ii. Director Planning, Yobe State Primary
Healthcare Management Board
iii. Chairman, Ngelshengele Local Govt
iv. PMO, Ngelshengele Primary Health Care Centre
v. Medical Director, General Hospital
Ngelshengele
c. Preliminary engagements with Medical personnel,
PHC and CHW for training
d. Preliminary engagement with relevant
stakeholders for planning of Medical Outreaches
e. Letter of acceptance from Yobe State Govt
received via Primary Healthcare Board
a. Inspection of proposed site for PHC a. Visit to Ngelshengele PHCC with Construction
Construction b. Design for new PHCC Team
c. Water tank and water for construction b. Inspection of proposed site for PHC
d. Temporary shed for materials c. Initiate design for new PHCC
e. Construction materials/ d. Recruiting of construction personnel for site –
local content
e. Mobilization to pre-construction team to the
proposed site
f. Provision of water tank and water for construction
g. Erecting of temporary shed for materials
h. Purchase of some of the materials for construction

a. Relume Office in Yobe a. Setting up of office in Yobe State


Others b. Mobilisation of Car Hire vehicles for transportation
to and from site
c. Mobilise security company for staff and materials
on site
d. Initial deposit for purchase of medical equipment

2 Construction
a. Construction Materials a. Prepare site for construction
b. Purchase of materials for construction
c. Commence substructure for PHCC building
● Excavation of foundation trench
● Fabrication and installation of
reinforcement for foundation
● Laying of concrete foundation

PHC a. Purchased drugs and items for initial a. Purchase of medical equipment, drugs and
Equipment, outreaches (part payment made) supplies - Batch 1
Drugs,
Furniture

a. Trained medical personnel in preparation a. Training of medical personnel commences


Medical for the first medical outreach. b. Training includes Primary Health Care Workers and
Outreach b. Medical Outreach 1 completed. Community Health Workers for participation in the
c. Drugs distribution to patients in need. outreach and for sustainability
c. Medical outreach Phase 1 - CHWs visit
communities, distribute vitamins and refer the sick
to central outreach
Community based Screenings, Psychosocial
support for SGBV, Sexual and reproductive health
care services
d. Community based Campaigns - Nutritional
education, health education campaign, execution
of Shell resilience module
e. Mobile clinic for use by CHWs

a.

3
Construction
a. Completed block works. a. Construction continues

● Begin block work.


● Internal works - PHCC Internal walls modification
a. Purchased items stored in warehouse in a. Payment for drugs, clinical furniture, medical
PHC Lagos - clinical furniture, medical equipment, Laboratory equipment and medical
Equipment, equipment, Laboratory equipment and supplies – Batch 2
Drugs, medical supplies b. Commissioning of locally produced furniture in
Furniture Yobe State

a. Trained medical personnel in preparation a. Training of medical personnel continues


Medical for the second medical outreach. b. Medical outreach Phase 1 continues
Outreach b. Medical Outreach 2 completed. c. Community based Campaigns continue -
c. Drugs distribution to patients in need. Nutritional education, health education campaign,
d. Erected banners in strategic locations and execution of Shell resilience module
distribution of consumable completed d. Medical Outreach Phase 2 commences for referred
patients - Central outreach (on appointment only)

e. Covid-19 Prevention campaign and distribution of


prevention items starts

f. Sanitation Campaigns and distribution of


consumables commence

g. Community based Campaigns - Nutritional


education, health education campaign, execution
of Shell resilience module
h. Mobile clinic for use by CHWs
4 a. Completed roofing works a. Construction of roof -
Construction b. Completed Plumbing works. ● Support beam,
c. Completed Tiling works. ● Woodwork/Skeleton,
● Outer roof & roof ceiling
b. Plumbing works; installation of toilets, showers
and sinks
c. Tiling of floor and toilets.

a. Warehousing in Lagos of more purchased d. Purchase of Drugs for PHCC and other items -
PHC items Batch 3
Equipment, b. Transportation of all items purchased so
Drugs, far to Yobe state
Furniture c. Warehousing of transported items in
warehouse in Yobe
a. Medical Outreach 3 Completed a. Medical outreach Phase 1 - CHWs visit
Medical b. Completion of stipulated Community communities, distribute vitamins and refer the sick
Outreach based programs to central outreach continues
c. Drugs distribution to patients in need. b. Community based Screenings, Psychosocial
d. Erected banners in strategic locations and support for SGBV, Sexual and reproductive health
distribution of consumable completed care services continues
c. Community based Campaigns - Nutritional
education, health education campaign, execution
of Shell resilience module continues
d. Covid-19 Prevention & Sanitation Campaigns and
distribution of consumables continues
e. Mobile Clinic for use by CHEWs

5 Construction a. Completed installation of doors, windows a. Installation of windows, doors and frames.
and frames. b. Electrical works; wiring and fittings installation.
b. Completed electrical works and fittings.

PHC a. Further purchased items stored in a. Purchase of Drugs for PHCC


Equipment, warehouse in Lagos - clinical furniture, b. Medical Equipment, Laboratory Equipment &
Drugs, medical equipment, Laboratory equipment Accessories for PHCC
Furniture and medical supplies Batch 4

Medical a. Trained medical personnel in preparation a. Training of Medical Personnel, PHC and CHEWs
Outreach for the third medical outreach. for deployment and sustainability continues
b. Completion of stipulated Community b. Training in Psychosocial support for SGBV, Sexual
and reproductive health care services continues
based programs.
c. Medical outreach Phase 1 - CHWs visit
c. Drugs distribution to patients in need. communities, distribute vitamins and refer the
d. Medical Outreach 4 completed. sick to central outreach continues
d. Community based Screenings, Psychosocial
support for SGBV, Sexual and reproductive health
care services continues
e. Medical Outreach Phase 3 - Surgeries &
interventions commences
f. Community based Campaigns - Nutritional
education, health education campaign, execution
of Shell resilience module continues
g. Mobile Clinic for use by CHEWs

6 Construction a. Pre-painting and Post-painting works


completed. a. Internal and external walls finishing for painting.
b. Site clean up completed. b. Commence painting of all walls
c. Demobilisation of workers and equipment
done.
c. Preparation of Final as built drawings
d. Commissioning and handover of newly
d. Demolition of temporary structure erected for
constructed PHCC building.
personnel and materials
e. Commissioning and handover
f. Construction personnel and equipment
demobilisation

PHC b. Warehousing in Lagos of more purchased a. Medical Equipment, Laboratory Equipment &
Equipment, items Accessories for PHCC
Drugs, c. 2nd Transportation of all items purchased
Furniture so far to Yobe state
d. Warehousing of transported items in
warehouse in Yobe
Medical a. Medical Outreach 5 Completed d. Medical outreach Phase 1 - CHWs visit
Outreach b. Completion of stipulated Community communities, distribute vitamins and refer the
based programs sick to central outreach continues
e. Community based Screenings, Psychosocial
c. Drugs distribution to patients in need.
support for SGBV, Sexual and reproductive health
care services continues
f. Medical Outreach Phase 2 - Central outreach (on
appointment only) continues
g. Medical Outreach Phase 3 - Surgeries &
interventions continues
h. Community based Campaigns - Nutritional
education, health education campaign, execution
of Shell resilience module continues
i. Mobile Clinic for use by CHEWs

7 PHC a. Balance payment for all purchased Drugs, a. Purchase of Drugs for PHCC
Equipment, Medical Equipment, Laboratory Equipment
Drugs, & Accessories for PHCC
Furniture

Medical a. Erected banners in strategic locations and a. Covid-19 Prevention & Sanitation Campaigns and
Outreach distribution of consumable completed distribution of consumables

8 COMMISSIONI COMMISSIONING OF PROJECT & SUBMISSION OF


NG OF REPORT
PROJECT & a. PLANNED INTERVENTION FOR HEALTH FOR
INTERNALLY DISPLACED PERSONS AND a. Handover of any remaining drugs to the pharmacy
SUBMISSION
VULNERABLE HOUSEHOLDS IN YOBE STATE of Ngelshengele PHCC
OF REPORT
FOR YEAR 2021 COMPLETED. b. Commissioning of Project and Handover
c. Preparation of Project Report
d. Preparation of Documentary Video
e. Preparation of Photo Album
f. Submission of Project Report, Documentary Video
and Photo Album