Inspection report

CLIENT :- M/s . ASP chem. equipments Report Date : 8/10/2021


Vendor : M/s.Chempro & Pharmach Equipments P.O :- 1702/2021-22
Equipment : SS 316 Vent Condenser E-106 & E- Person Contacted :- Mr. Vikram Shulkla
206 (3.59 M2)
& MS Vent Condenser E-101, E-201 (3.59 M2)
Stage Inspection Location : Vasai , Gavraipada
Sr. No Description Remarks
Visited M/s. M/s.Chempro & Pharmach Equipments For
inspection Of SS 316 Vent Condenser E-106 & E-206 (3.59 M2)
& MS Vent Condenser E-101, E-201 (3.59 M2)

1) E-106 Progress Status


1) Shell With tubesheet ready with assembly – Refer Attached
Remark : Some under cut noticed near tubesheet to be Photograph
rectify and offer before hydro
2) Equipment dimensionally checked – Some deviation
found (N2 Nozzle should be 125 mm away from RHS
Tubesheet – Actual measured 115 mm ) Approval to be
taken
3) Bonnet shell not ready yet As per vendor it will be ready
by tomorrow (i.e 09/10/2021)
4) Moly test carried out at various area found ok Refer Attached
Photograph

2) E-206 Progress Status


1) Shell is ready With tubesheet bundle ready
Baffle spacing measured and found OK
Moly test carried out at various area found ok
Remark : Some under cut noticed near on nozzle area to
be rectify and offer before hydro & proceeding further
2) Equipment dimensionally checked – Some deviation
found (N2 Nozzle should be 125 mm away from RHS
Tubesheet – Actual measured 115 mm ) Approval to be
taken
3) Bonnet shell not ready yet will be ready by tomorrow
(i.e 09/10/2021)

3) E-101 Progress Status


1) Shell With tubesheet ready with assembly – Refer Attached
2) Equipment dimensionally checked – Some deviation Photograph
found (N6 & N2 Nozzle should be 105 mm away from
Tubesheet – Actual measured 90 mm & 93 mm
Respectively ) Approval to be taken
3) Bonnet shell not ready yet As per vendor it will be ready
by tomorrow (i.e 09/10/2021)
For M/s . ASP chem. Equipments For M/s.Chempro & Pharmach Equipments

Mr. AnkitSura Mr. Vikram Shulkla


Inspection report

E-201 Progress Status


4) 1) Shell With tubesheet ready with assembly –
2) Equipment dimensionally checked – Some deviation Refer Attached
found (N6 & N2 Nozzle should be 105 mm away from Photograph
Tubesheet – Actual measured 90 mm & 93 mm
Respectively ) Approval to be taken
Bonnet shell not ready yet As per vendor it will be ready by
tomorrow (i.e 09/10/2021)

There are some points discussed with vendor


1) Client to be confirm whether arc welding or filler wire to
be used for saddle support welding
2) Earthing boss will be provided by Client
3) Expansion should be done by M/s ASP Chem before
proceeding for hydro
4) Material Stamped “ “ For identification

For M/s . ASP chem. Equipments For M/s.Chempro & Pharmach Equipments

Mr. AnkitSura Mr. Vikram Shulkla