RENCANA ANGGARAN BIAYA

PROYEK : GRAND DUTA TANGERANG


PEKERJAAN : JALAN BETON DAN SALURAN
LOKASI : JALAN UTAMA DAN SALURAN DUTA LAGO

Harga Satuan Total Harga


NO. JENIS PEKERJAAN Sat Vol
(Rp). (Rp).
I PEKERJAAN PERSIAPAN
a Pembersihan lahan LS 1.00 10,000,000 10,000,000
b Mob demobilisasi LS 1.00 5,000,000 5,000,000
c Penyediaan air kerja LS 1.00 3,500,000 3,500,000
Sub total I 18,500,000

II PEKERJAAN JALAN BETON M 119.90


a Pengukuran + Patok + Leveling M2 959.20 3,500 3,357,200
b Timbunan sub grade + pemadatan M3 911.24 91,000 82,922,840
c Gelaran sub base B t=25cm M3 179.85 268,500 48,289,725
d Gelaran sub base A t=10cm M3 71.94 288,850 20,779,869
e Beton k-350 (t=0.2m) M2 143.88 1,980,000 284,882,400
Sub total II 440,232,034

III PEKERJAAN LAIN LAIN


a Cerukcuk bambu M 119.90 335,000 40,166,500
b Kansteen M 239.80 305,000 73,139,000
c Crossing beton k-225 l=80cm lapis wiremesh m6 M3 4.80 2,597,000 12,465,600
d Retaining wall M3 5.00 2,850,000 14,250,000
Sub total III 140,021,100

TOTAL 598,753,134
DIBULATKAN 598,750,000
PPN 10% 59,875,000
TOTAL 658,625,000

Tangerang, Oktober 2015


Diajukan

Kontraktor
COR BETON K - 350 READY MIX

HARGA SATUAN JUMLAH HARGA


URAIAN ANALISA SATUAN
Rp. Rp.
Beton K-350 1.0300 M2 875,000.00 901,250.00
Pekerja 2.5000 ORG 95,000.00 237,500.00
Tk. Batu Setengah Terampil 0.5000 ORG 100,000.00 50,000.00
Kep. Tukang Batu 0.2500 ORG 110,000.00 27,500.00
Mandor 0.5000 ORG 120,000.00 60,000.00
Alat Bantu Vibrator 1.0000 LOT 15,000.00 15,000.00
Plastik Cor 5.0500 M2 5,220.00 26,361.00
Pembesian 1M6 5.0500 M2 57,500.00 290,375.00
Pas.Begisting,Dowel ,Upah Kerja 5.0500 M2 25,000.00 126,250.00
Cutting Beton dan Grouting aspal/6m 5.0500 M1 25,000.00 126,250.00
Perawatan Beton 5.0500 M2 5,000.00 25,250.00

Jumlah 1,885,736.00
Jasa.5% 94,286.80
Jumlah 1,980,022.80
Dibulatkan 1,980,000.00