Professional Documents
Culture Documents
In response, Eskom implemented the hard-wired The hard-wired DR programme requires that customers
Demand Response (DR) programme with various end reduce their contractual targeted load every weekday from
users. One of the users includes a prominent gold June to August 2013. The requested reduction period is
mining group in South Africa. Due to the nature of the between 17h00 and 20h00 to help reduce the evening
hard-wired DR programme, the projects investigated peak created by the domestic sector.
will entail the load reduction of larger loads during a
peak period of 17h00 to 20h00 [1]. This includes an The typical peak consumption of South Africa during the
additional load reduction during the 17h00 to 18h00 months of March, May and July can be seen in Figure 1.
timeslot as opposed to standard DSM initiatives. The spike in consumption on a typical winter day during
the evening peak can be in excess of 3000 MW [2], as
In order to determine the achievable load reduction, circled in red. This spike is due to the domestic sector
numerous tests and simulation models have been increasing electricity usage, and occurs daily from 17h00
utilised. Existing DSM projects already in operation to 21h00.
could also be altered to contribute to additional peak
period load reduction. However, practical limitations
on the hardware available would need to be addressed.
Focus was placed on pumping systems, refrigeration
plants, process mills, compressed air and winder
operations. Overall potential impact of this mining
group was determined as 19.4 MW during 17h00 to
18h00 and 19.5 MW during 18h00 to 20h00. This
could result in a possible R 4.2 million in incentives for
the three winter months of 2013.
1. INTRODUCTION
Case study 1
In the first case study, the pumping layout of the shaft was
changed to implement an additional pump station. The
control system was not allowed to automatically control
the pumps due to the changes in the system. Evening load
shift was done manually by control room operators.
Figure 3: Proposed winding profile with ore extracted Maintenance on the system, accompanied by a re-
throughout the entire day simulation of the system with updated constraints
indicated that additional load reduction could be achieved.
Refrigeration Plants
Reduced ambient temperatures during the winter months
enable the switching off of some of the refrigeration
plants during the off-peak periods to achieve additional
load reduction. In some instances the mines would switch
off some of their refrigeration plants for the whole of
winter. The effect of the lower cooling capacity on the
temperature in the mine is investigated to determine the
feasibility of the load reduction.
Process Mills
Energy management on precious metal plants is usually
disregarded due to the cost implications of lost Figure 5: Load reduction achieved during test phase of re-
production. A load reduction strategy would therefore implementation of automatic control
require careful planning. From the investigation it was
found that by stopping a different mill on each weekday By manually testing the simulated changes on the actual
during evening peak hours will result in 1% less time system, a load reduction of 6.73 MW was achieved, as
available for milling. The mills are running on at average indicated in Figure 5. The reduction was only tested
93% utilisation rate, therefore the 1% could be made up during the 18h00 – 20h00 timeslot, but the test indicated
through increased utilisation. However, a 2MW load clip that additional capacity would be available to achieve the
can be achieved (given in Figure 4). programme requirements of 17h00 to 20h00.
In conjunction with other peak clipping initiatives, a
demand reduction of 7 MW (17h00 – 18h00), 13 MW
14000
(18h00-19h00) and 14 MW (19h00-20h00) were possible.
12000
A payback of R 2.4 million would be possible over the
10000
three month period as a result from the kickback of the
Power [kW]
8000
6000
hard-wired DR programme. These initiatives included
4000
extraction fans, compressed air and cooling auxiliary
2000
projects.
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Case study 2
The second system investigated entailed the additional
WeekdayTime of day [hour]
Weekday proposed
17h00 to 18h00 timeframe to be included in a project that
was recently re-implemented as part of a maintenance
Figure 4: Load clip available on process mills
programme. Because all the data has already been the calculations, tests and simulations are tabulated in
processed for simulation, the possibility of an additional Table 1.
hour load shift could be verified with minimal effort. A
layout of the system is given in Figure 6. These savings are calculated under the assumption that
the shafts can be signed up as individual clients. In the
instances where the shafts had showed negative load
Surface Pre Surface Cooling Surface Fridge
shifts due to changes in mining schedules, the amount of
load reduction was taken as 0 MW. The majority of the
Cooling Dam Tower Plant
60
50
1.5 If all the potential savings are achieved, a potential
40
1
kickback from the utility to the value of R4.5 million can
30 be obtained. This is based only on the R1.2/kWh
20
10
0.5
incentive. Additional cost savings resulting from shifting
0 0 load out of more expensive Megaflex price tariffs to less
0 1 2 3 4 5 6 7 8 9 1011121314151617181920212223 expensive periods has been excluded.
Dam 1 % Hour Dam 2 %
Figure 7: Pumping system key performance indicators The three case studies were part of an investigation to
determine what the potential load reduction would be on a
In order to prepare the dams, the pumping procedure was whole mining group. During the investigation, the biggest
required to be shifted an hour earlier. With the morning electricity consumers were chosen where additional load
peak period, the inflow of water from the shaft was low. reduction could be achieved. Through various tests,
This resulted in pumping usually starting an hour after the simulations and calculations, the target was calculated as
morning peak period. By starting the pumping procedure 18.1MW (17h00-1800), 23.5 MW (18h00-19h00) and
directly after the morning peak, the dams was at adequate 21.5 MW (19h00-20h00). This would ultimately result in
levels to allow a three hour load shift during the evening a potential R4.5 million incentive from the utility to the
peak as required by the hard-wired DR programme. customer if al opportunities are pursued and implemented.
An additional 3 MW load reduction was achieved during With a proper time frame to implement the load
the 17h00 to 18h00 timeslot. This would produce a cost reduction, more extensive testing, scheduling and
saving of R 260 000 if implemented for the duration of reprogramming of systems could produce additional load
the hard-wired DR programme. reduction capacity.
7. REFERENCES
7. AUTHOR(S)