You are on page 1of 1

SE-315 Operations Research

Assignment # 01(CLO-2, PLO-3, C3)

Q# 1:

For the given network diagram

a. Construct a table which shows the relationship between the activities and their
predecessors.
b. Identify the following time estimates for each activity.
 Earliest Start Time(EST)
 Earliest Finish Time (EFT)
 Latest Start Time (LST)
 Latest Finish Time (LFT)
c. Identify the total float for each activity.
d. Identify the critical path.
e. Identify the project completion time.

Note: The duration of each given activity is in days.

Page 1 of 1

You might also like