CLIENTE: LIMAGAS S.

A
PROYECTO:CERCO PERIMETRICO H=3.40 m
CALLAO Tarjeta Página : Costo al
S10 CCCEIC CERCO PERIMETRICO H=3.40 - LIMAGAS

1.0 TRABAJOS PRELIMINARES UNIDAD METRADO P.U PARCIAL SUBTOTAL


1.1 LIMPIEZA DE TERRENO MANUAL M2 1,276.96 2.70 3,447.79
1.2 TRAZO Y REPLANTEO CON EQUIPO M2 1,276.96 2.53 3,230.71
1.3 EXCAVACION MANUAL DE CIMIENTO M3 456.51 43.00 19,629.93
1.4 RELLENO COMPACTADO CON MATERIAL PROPIO M3 249.01 20.74 5,164.47
1.6 NIVELACION Y APISONADO CON MAQUINA M2 415.01 3.28 1,361.23 32,834.13
2.0 CONCRETO SIMPLE
2.1 CIMIENTOS CONCRETO CICLOPEO 1:10+30% PG M3 207.51 196.45 40,765.34
2.12 ACERO EN CIMIENTO CORRIDO Fy=4200 KG/CM2 KG 1,431.71 4.73 6,771.99
2.3 CONCRETO LIQUIDO EN SOBRECIMIENTO FC=175 KG/CM2 M3 60.49 332.79 20,130.47
2.4 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO M2 630.08 28.58 18,007.69
3.0 CONCRETO ARMADO
3.1 ACERO GRADO 60 EN SOBRECIMIENTO DE BLOQUE DE CONCRETO KG 1,838.07 4.73 8,694.07
3.2 ACERO GRADO 60 EN MURO DE BLOQUE DE CONCRETO KG 4,195.02 4.73 19,842.44
3.3 MURO DE BLOQUE DE CONCRETO 14x39x19 M2 2,134.06 59.03 125,973.56
3.4 CONCRETO LIQUIDO EN MUROS, MEZC C:A:P 1:2 1/2: 1 1/2, SLUMP=10", F'C= 175 kg/c M3 53.56 332.79 17,824.23
3.5 CONCRETO PARA BASE DE PUERTA f´c= 175 Kg/cm2 M3 2.10 223.34 469.01
3.6 SOLAQUEO DE SOBRECIMIENTO M2 2,134.06 14.10 30,090.25 288,569.05
3.7 COLUMNAS DE CONCRETO PARA PUERTA
3.7.1 CONCRETO EN COLUMNAS F'C=210 KG/CM2 M3 2.20 401.78 883.92
3.7.2 ACERO GRADO 60 EN COLUMNAS KG 321.41 4.81 1,545.98
3.7.3 ENCOFRADO Y DESENCOFRADO PARA COLUMNAS M2 28.60 41.95 1,199.77
3.7.4 TARRAJEO DE SUPERFICIE DE COLUMNAS CON CEMENTO-ARENA M2 28.60 31.13 890.32 4,519.99
5.0.0 PUERTA METALICA H=5.00m
5.1.0 PINTURA EN PUERTAS METALICAS M2 8.40 22.74 191.02
5.2.0 DESMONTAJE DE PUERTA METALICA GLB 1.00 4,500.00 4,500.00
5.3.0 MONTAJE DE PUERTA METALICA H=5.00m GLB 1.00 1,200.00 1,200.00 5,891.02

COSTO DIRECTO 331,814.18


GASTOS GENERALES 23,226.99
UTILIDADES 23,226.99
===========
SUBTOTAL 378,268.17
IGV 71,870.95
===========
TOTAL PRESUPUESTO 1 ###

COSTO DE CERCO H=3.40m POR METRO LINEAL (LONTITUD=638.48 S/.705.02


CLIENTE: LIMAGAS S.A
PROYECTO:CERCO PERIMETRICO H=3.40 m
CALLAO Tarjeta Página : Costo al
S10 CCCEIC CERCO PERIMETRICO H=3.40 - LIMAGAS

GASTOS GENERALES
UND P.U PARCIAL
GASTOS DE OBRA Y PERSONAL TECNICO GLB 22,226.99
GASTOS POR TRAMITE DE LICENCIA DE CONSTRUCCION GLB 1000

COSTO DIRECTO DE G.G 23,226.99


CLIENTE: LIMAGAS S.A
PROYECTO:EXPLANACION DE TERRENOSUPERFICIALMENTE + TRASLADO DE PUERTA METALICA

S10 CCCEIC CALLAO CERCO PERIME


Tarjeta Página : Costo al 1
6.0.0 EXPLANACION p.u
6.1.0 CORTE SUPERFICIAL CON MAQUINARIA M3 32,650.55 1.03 33,630.07 1.03
6.3.0 NIVELACION INTERIOR APISONADO MANUAL M2 46,643.64 1.49 69,499.02 103,129.09 1.61

COSTO DIRECTO 103,129.09


GASTOS GENERALES 7,219.04
UTILIDADES 7,219.04
===========
SUBTOTAL 117,567.16
IGV 22,337.76
===========
TOTAL PRESUPUESTO 1 46643.64 139,904.92

COSTO DE EXPLANACION POR METRO CUADRADO (AREA=46,643.64 m2) S/.3.00

antes 147498.14
despues ###
2.99944266 7593.2114
CLIENTE: LIMAGAS S.A
PROYECTO:CERCO PERIMETRICO H=3.40m

RESUMEN DE METRADOS

Descripción METRADO UNIDAD

1.0 TRABAJOS PRELIMINARES


1.1 LIMPIEZA DE TERRENO MANUAL 1276.96 M2
1.2 TRAZO Y REPLANTEO CON EQUIPO 1276.96 M2
1.3 EXCAVACION MANUAL DE CIMIENTO 456.51 M3
1.4 RELLENO COMPACTADO CON MATERIAL PROPIO 249.01 M3
1.6 NIVELACION Y APISONADO CON MAQUINA 415.01 M2
2.0 CONCRETO SIMPLE
2.1 CIMIENTOS CONCRETO CICLOPEO 1:10+30% PG 207.51 M3
2.2 ACERO EN CIMIENTO CORRIDO Fy=4200 KG/CM2 1431.71 KG
2.3 CONCRETO LIQUIDO EN SOBRECIMIENTO FC=175 KG/CM2 60.49 M3
2.4 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO 630.08 M2
3.0 CONCRETO ARMADO
3.1 ACERO GRADO 60 EN SOBRECIMIENTO DE BLOQUE DE CONCRETO 1838.07 KG
3.2 ACERO GRADO 60 EN MURO DE BLOQUE DE CONCRETO 4195.92 KG
3.3 MURO DE BLOQUE DE CONCRETO 14x39x19 2134.06 M2
3.4 CONCRETO LIQUIDO EN MUROS, MEZC C:A:P 1:2 1/2: 1 1/2, SLUMP=10", F'C= 175 kg/cm2 53.56 M3
3.5 CONCRETO PARA BASE DE PUERTA f´c= 175 Kg/cm2 2.10 M3
3.6 SOLAQUEO DE SOBRECIMIENTO 2134.06 M2
3.7 COLUMNAS DE CONCRETO PARA PUERTA
3.7.1 CONCRETO EN COLUMNAS F´C=210 KG/CM2 2.20 M3
3.7.2 ACERO EN COLUMNAS FY=4200 KG/CM2 321.41 kg
3.7.3 ENCOFRADO EN COLUMNAS 28.60 M2
3.7.4 TARRAJEO EN COLUMNAS 28.60 M2
5.0 PUERTA METALICA H=5.00m
5.1 PINTURA EN PUERTAS METALICAS 8.40 M2
5.2 DESMONTAJE DE PUERTA METALICA 1.00 GLB
5.3 MONTAJE DE PUERTA METALICA 1.00 GLB
CLIENTE: LIMAGAS S.A
PROYECTOCERCO PERIMETRICO H=3.40 m

DETALLE DE METRADOS

Descripción CANTIDAD LARGO ANCHO ALTO PARCIAL TOTAL Unidad

1.0 TRABAJOS PRELIMINARES


1.1 LIMPIEZA DE TERRENO MANUAL 1276.96 M3
1 194.52 2 389.04
1 375.11 2 750.22
1 68.85 2 137.7

1.2 TRAZO Y REPLANTEO CON EQUIPO 1276.96 M2


1 194.52 2 389.04
1 375.11 2 750.22
1 68.85 2 137.7

1.3 EXCAVACION MANUAL DE CIMIENTO 456.51 M3


1 194.52 0.65 1.1 139.0818
1 375.11 0.65 1.1 268.20365
1 68.85 0.65 1.1 49.22775

1.4 RELLENO COMPACTADO CON MATERIAL PROPIO 249.01 M3


1 194.52 0.65 0.6 75.8628
1 375.11 0.65 0.6 146.2929
1 68.85 0.65 0.6 26.8515

1.5 ELIMINACION MASIVA DE MATERIAL EXCEDENTE M3


1.6 NIVELACION Y APISONADO CON MAQUINA 415.01 M2
1 194.52 0.65 126.438
1 375.11 0.65 243.8215
1 68.85 0.65 44.7525

2.0 CONCRETO SIMPLE


2.1 CIMIENTOS CONCRETO CICLOPEO 1:10+30% PG 207.51 M3
1 194.52 0.65 0.5 63.219
1 375.11 0.65 0.5 121.91075
1 68.85 0.65 0.5 22.37625
Descripción CANTIDAD LARGO ANCHO ALTO PARCIAL TOTAL Unidad

2.2 ACERO EN CIMIENTO CORRIDO Fy=4200 KG/CM2 1431.71 KG


ESTRIBOS DE 1/4" 1597.2 0.75 1197.9
PESO DE VARILLA DE 1/4" (KG/ML) 0.25 1197.9
299.475

ACERO DE 3/8" 3 638.48 1915.44


TRASLAPES DE 0.50 PARA ACERO DE 3/8" 3 0.5 70.942222 106.4133333333
PESO DE VARILLA DE 3/8" (KG/ML) 0.56 2021.853333333
1132.237866667

2.3 CONCRETO LIQUIDO EN SOBRECIMIENTO FC=175 KG/CM2 60.49 M3


1 630.08 0.12 0.8 60.48768

2.4 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO 630.08 M2


POR AMBOS LADOS 2 630.08 0.5 630.08

3.0 CONCRETO ARMADO


3.1 ACERO GRADO 60 EN SOBRECIMIENTO DE BLOQUE DE CONCRETO 1838.07 KG
ACERO VERTICAL CADA 0.60 M CON ACERO DE 12MM (H=3.40) 1015.933333 2.125 2158.858333333
ACERO VERTICAL CADA 0.60 M CON ACERO DE 12MM (H=5.00) 22.2 3.725 82.695

PESO DE VARILLA DE 12 mm (KG/ML) 0.82 2241.553333333


1838.073733333

3.2 ACERO GRADO 60 EN MURO DE BLOQUE DE CONCRETO 4195.92 KG


ACERO VERTICAL CADA 0.60 M CON ACERO DE 12MM (H=3.40) 1015.933333 3.17 3220.508666667
ACERO VERTICAL CADA 0.60 M CON ACERO DE 12MM (H=5.00) 22.2 4.77 105.894

PESO DE VARILLA DE 12 mm (KG/ML) 0.82 3326.402666667


2727.650186667

ACERO HORIZONTAL CADA 1.00 M CON ACERO DE 3/8" 4.25 608.96 2588.08
TRASLAPES DE 0.50 PARA ACERO DE 3/8" 67.66 0.5 33.83111111111

PESO DE VARILLA DE 3/8" mm (KG/ML) 0.56 2621.911111111


1468.270222222

Descripción CANTIDAD LARGO ANCHO ALTO PARCIAL TOTAL Unidad

3.3 MURO DE BLOQUE DE CONCRETO 14x39x19 2134.06 M2


muros de H=3.40M 608.96 3.4 2070.46
muros de H=5.00M 12.72 5 63.60

3.4 CONCRETO LIQUIDO EN MUROS, MEZC C:A:P 1:2 1/2: 1 1/2, SLUMP=10", F'C= 175 kg/cm2 53.56 M3
aberturas a llenar
muros de H=3.40M 1015.933333 0.156 0.09 3.4 48.50
muros de H=5.00M 22.2 0.156 0.09 5 1.56
%DESPERDICIO 1.07 50.06

3.5 CONCRETO PARA BASE DE PUERTA f´c= 175 Kg/cm2 2.10 M3


puerta 1 8.4 0.5 0.5 2.1

3.6 SOLAQUEO DE SOBRECIMIENTO 2134.06 M2


muros de H=3.40M 1 608.96 3.4 2070.464
muros de H=5.00M 1 12.72 5 63.6

3.7 COLUMNAS DE CONCRETO PARA PUERTA

3.7.1 CONCRETO EN COLUMNAS F´C=210 KG/CM2 2.20 M3


4 0.25 0.4 5.5 2.2

3.7.2 ACERO EN COLUMNAS FY=4200 KG/CM2 321.41 kg


acero de 1/2"
6 4 6 144

PESO DE VARILLA DE 3/8" (KG/ML) 1 144


144
estribos de 3/8"
36 4 1.3 187.2
36 4 0.9 129.6

PESO DE VARILLA DE 3/8" (KG/ML) 0.56 316.8


177.408
Descripción CANTIDAD LARGO ANCHO ALTO PARCIAL TOTAL Unidad

3.7.3 ENCOFRADO EN COLUMNAS 28.60 M2


4 1.3 5.5 28.6

3.7.4 TARRAJEO EN COLUMNAS 28.60 M2


4 1.3 5.5 28.6

5.0 PUERTA METALICA H=5.00m


5.1 PINTURA EN PUERTAS METALICAS 8.40 M2

5.2 DESMONTAJE DE PUERTA METALICA 1.00 GLB


INCLUYE: TRABAJO DE DESMONTAJE, TRASLADO DE PERSONAL IDA Y 1 1
VUELTA, VIATICOS, MOVILIZACION DE PUERTA

5.2 DESMONTAJE DE PUERTA METALICA 1.00 GLB


1 1