PIVOT PAD CONSTRUCTION C. Non-Towable High Profile Pivots L. The Pivot Pad should be formed directly over the steel stake marking the center of the field. 2. ‘The forms should be square with the field unless the well has already been dug The pad should then be formed to allow the pump discharge pipe to cross in the middle of one of the four sides. The Pivot Pad should be formed on the level. 3. Dig and form pad following the Figure below. The Anchor Bolts shonld extend 2" above the concrete. The Pivot Pad requires 8 to 8 1/4 yards of concrete. The concrete should be 2500 psi minimum strength A- Z(TYP)-4 Sa pe [ZS ee reene, i t fiat Wat 11-0" ) CTION A-A v7 3/e'| | RECONUENDED N UGH SOL, Syste. ef ad 9-7 3" —— ae