Project Contoh Untuk Latihan Pekerjaan Sipil
Project Contoh Untuk Latihan Pekerjaan Sipil
February 2019 March 2019 April 2019 May 2019 June 2019 July 2019
Mode 16 21 26 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11
1
2 PEKERJAAN PENDAHULUAN 3 days Mon 3/4/19 Wed 3/6/19
3 Pembersihan Lokasi 3 days Mon 3/4/19 Wed 3/6/19
4 Pengukuran dan Pasangan Bouwplank 3 days Thu 3/7/19 Mon 3/11/193
5
6 PEKERJAAN TANAH 9 days Tue 3/12/19 Fri 3/22/19
7 Galian Tanah 7 days Tue 3/12/19 Wed 3/20/194
8 Urugan Tanah Kembali 2 days Thu 3/21/19 Fri 3/22/19 7
9 Buangan Tanah Galian 7 days Tue 3/12/19 Wed 3/20/197FF
10
11 PEKERJAAN DINDING 40 days Thu 5/2/19 Wed 6/26/19
12 Pasang Dinding Bata 1:3 1/2 Bata 30 days Thu 5/2/19 Wed 6/12/1924
13 Plesteran Tebal 15 mm Campuran 1:3 10 days Thu 6/13/19 Wed 6/26/1912
14 Benangan Sudut 1:2 3 days Mon 6/24/19Wed 6/26/1913FF
15 Acian 4 days Fri 6/21/19 Wed 6/26/1913FF
16
17 PEKERJAAN STRUKTUR 60 days Thu 3/21/19 Wed 6/12/19
18 Pondasi Tapak P1 (1200x1200x150) 4 days Thu 3/21/19 Tue 3/26/19 9
19 Pondasi Tapak P2 (500x500x150) 2 days Mon 3/25/19Tue 3/26/19 18FF
20 Sloof (300x200) 5 days Wed 3/27/19Tue 4/2/19 18,19
21 Kolom K1 (400x150) 7 days Wed 4/3/19 Thu 4/11/19 20
22 Kolom K2 (300x150) 7 days Thu 5/2/19 Fri 5/10/19 27
23 Kolom Praktis KP (120x120) 7 days Tue 6/4/19 Wed 6/12/1912FF
24 Balok B1 (400x200) 14 days Fri 4/12/19 Wed 5/1/19 21
25 Balok B2 (300x200) 14 days Mon 5/13/19Thu 5/30/19 22
26 Balok Praktis BP (150x120) 14 days Mon 5/13/19Thu 5/30/19 25FF
27 Lantai S1 (Thick 100 mm) 2 days Tue 4/30/19 Wed 5/1/19 20FF
28 Lantai S2 (Thick 120 mm) 3 days Mon 4/29/19Wed 5/1/19 24FF
29 Kanopi Beton S3 (Thick 100 mm) 2 days Thu 5/2/19 Fri 5/3/19 12SS
30 Tangga Beton 5 days Fri 4/12/19 Thu 4/18/19 24SS
31
32 PEKERJAAN ATAP 6 days Fri 5/31/19 Fri 6/7/19
33 Pemasangan Usuk Galvalum 2 days Fri 5/31/19 Mon 6/3/19 25
34 Pemasangan Reng Galvalum 2 days Tue 6/4/19 Wed 6/5/19 33
35 Pemasangan Atap Spandek 1 day Thu 6/6/19 Thu 6/6/19 34
36 Pekerjaan Talang 1 day Fri 6/7/19 Fri 6/7/19 35
37
38 PEKERJAAN PENUTUP LANTAI DAN DINDING 14 days Thu 5/2/19 Tue 5/21/19
39 Keramik Lantai 60x60 12 days Thu 5/2/19 Fri 5/17/19 28
40 Keramik Lantai Kamar Mandi & Teras 30x30 2 days Mon 5/20/19Tue 5/21/19 39
Page 1
ID Task Task Name Duration Start Finish Predecessors
February 2019 March 2019 April 2019 May 2019 June 2019 July 2019
Mode 16 21 26 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11
41 Keramik Dinding Kamar Mandi dan Dapur 4 days Thu 5/16/19 Tue 5/21/19 40FF
30x40
42 Keramik Tangga 60x60 2 days Thu 5/2/19 Fri 5/3/19 39SS
43 Pemasangan Step Noshing Tangga 2 days Mon 5/6/19 Tue 5/7/19 42
44
45 PEKERJAAN KUSEN PINTU DAN JENDELA 3 days Tue 6/4/19 Thu 6/6/19
46 Pintu dan Jendela Utama P1 1 day Tue 6/4/19 Tue 6/4/19 23SS
47 Pintu dan Jendela Balkon P2 1 day Wed 6/5/19 Wed 6/5/19 23SS
48 Pintu Kamar P3 1 day Thu 6/6/19 Thu 6/6/19 23SS
49 Pintu Kamar Mandi P4 1 day Tue 6/4/19 Tue 6/4/19 23SS
50 Jendela Kamar J1 1 day Wed 6/5/19 Wed 6/5/19 49
51 Bouven BV 1 day Wed 6/5/19 Wed 6/5/19 50SS
52 Jendela Kapel dan Perpustakaan 1 day Wed 6/5/19 Wed 6/5/19 50SS
53 Glass Block Tangga dan Balkon 1 day Thu 6/6/19 Thu 6/6/19 52
54
55 PEKERJAAN RAILLING 12 days Wed 5/22/19Thu 6/6/19
56 Pekerjaan Railling Tangga 7 days Wed 5/22/19Thu 5/30/19 38
57 Pekerjaan Railling Balkon 5 days Fri 5/31/19 Thu 6/6/19 56
58
59 PEKERJAAN PLAFOND 8 days Mon 2/25/19Wed 3/6/19
60 Plafond GypsumBoard 9 mm 8 days
61 Plafond GRC Board 9 mm 2 days
62 Pemasangan List Gypsum 1 day
63
64 PEKERJAAN PENGECATAN 6 days Mon 2/25/19Mon 3/4/19
65 Pekerjaan Cat Dinding Interior 6 days
66 Pekerjaan Cat Dinding Exterior 4 days
67 Pekerjaan Cat Besi 1 day
68 Pekerjaan Waterproofing 1 day
69
70 PEKERJAAN ELEKTRIKAL 7 days Fri 6/7/19 Mon 6/17/19
71 Instalasi Penerangan 3 days Fri 6/7/19 Tue 6/11/19 45
72 Instalasi Stop Kontak 3 days Fri 6/7/19 Tue 6/11/19 71SS
73 Instalasi Saklar Tunggal 3 days Wed 6/12/19Fri 6/14/19 72
74 Instalasi Saklar Ganda 3 days Wed 6/12/19Fri 6/14/19 73SS
75 MCB Box 1 day Mon 6/17/19Mon 6/17/1974
76 MCB 6 A 1 day Mon 6/17/19Mon 6/17/1975SS
77 MCB 10 A 1 day Mon 6/17/19Mon 6/17/1975SS
78
79 PEKERJAAN MEKANIKAL 50 days Mon 4/29/19Fri 7/5/19
80 Pipa PVC 4" 14 days Mon 4/29/19Thu 5/16/19 28SS
Page 2
ID Task Task Name Duration Start Finish Predecessors
February 2019 March 2019 April 2019 May 2019 June 2019 July 2019
Mode 16 21 26 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11
81 Pipa PVC 3" 14 days Thu 5/2/19 Tue 5/21/19 12SS
82 Pipa PVC 1,5" 14 days Thu 5/2/19 Tue 5/21/19 12SS
83 Pipa PVC 1/2" 14 days Thu 6/13/19 Tue 7/2/19 12
84 Pemasangan Kitchen Zink 1 day Wed 7/3/19 Wed 7/3/19 83
85 Pemasangan Kran 1 day Wed 7/3/19 Wed 7/3/19 83
86 Pemasangan Closet Duduk 2 days Thu 7/4/19 Fri 7/5/19 85
Page 3