Mark C. Tyler
e
in
®
Craftsman Book Company
6058 Corte del Cedro / P.O. Box 6500 / Carlsbad, CA 92018
Acknowledgements
The author wishes to express his appreciation to the following companies and organizations for
furnishing materials used in the preparation of various portions of this book:
American Arbitration Association — 1633 Broadway, 10th Floor, New York, NY 10019
Appleton Electric Company — 9377 W. Higgins Road, Rosemont, IL 60018
Calculated Industries, Inc. — 4840 Hytech Drive, Carson City, NV 89706
Hubbell Lighting, Inc. (Formerly Marvin Electric Manufacturing Company) — 584 Derby
Milford Road, Orange, CT 06477
w
Leviton Manufacturing Company, Inc. — 201 North Service Road, Melville, NY 11747
Lithonia Lighting — P.O. Box A, Conyers, GA 30012
ie
Square D Company — 1415 South Roselle Road, Palatine, IL 60067
Trade Service Publications, Inc. — 15092 Avenue of Science, San Diego, CA 92128
ev
Westinghouse Electric Corporation — 1000 Westinghouse Drive, Cranberry Township, PA 16066
Craftsman has the books to fill your needs. Call toll-free 1-800-829-8123
in
or write to Craftsman Book Company, P.O. Box 6500, Carlsbad, CA 92018 for
a FREE CATALOG of over 100 books, including how-to manuals,
annual cost books, and estimating software.
nl
Tyler, Mark C.
Estimating electrical construction, revised / by Mark C. Tyler.
p. cm.
Rev. ed. of: Estimating electrical construction / by Edward J. Tyler. 1983.
Includes index.
ISBN 978-1-57218-253-0
1. Electrical engineering--Estimates. I. Tyler, Edward J. Estimating electrical
construction. II. Title.
TK435.T93 2011
621.319'24--dc22 2011005598
Contents
w
1 What Does It Take to Be 6 The Material Cost
ie
an Electrical Estimator?............. 5 Estimate............................................... 77
The.Design.Team.......................................... 7 Transfer.the.Takeoff.Data.......................... 77
ev
The.Construction.Team................................ 8 Calculate.Each.Item’s.Cost........................ 78
Key.Elements.of.a.Bid................................. 10
Material.Cost.Sources................................. 81
Pr
The.Estimate............................................... 11
Accurate.or.“Best”.Pricing......................... 84
2 Finding Work 7 Completing Your Estimate
& Submitting Bids......................... 13
e
Choosing.the.Right.Projects....................... 15
Manually (Labor, Equipment
in
Bid.Form.and.Submission.......................... 29 Cost.of.Equipment...................................... 98
Subcontract.Costs....................................... 99
O
w
Permits and Fees................................. 177
Bid Bonds............................................. 178 Learn About Your Competition......... 236
ie
Performance Bonds............................. 179 Selling Your Bid................................... 241
Insurance Coverage............................ 180 Scheduling............................................ 245
ev
Progress Payments.............................. 180
Retention.............................................. 181
Pr
12 Completing Your Estimates 17 Change Orders........................... 247
Why Changes Are Made..................... 249
& Bids Manually...................... 183
Finalizing Your Estimate and Bid..... 183 Get It (and Give It) in Writing........... 249
e
Finalizing Your Bid Summary Sheet 188 Processing a Change Order................ 254
Effects of Change Orders................... 256
13 Completing Your Estimates
nl
Chapter 1
What Does It Take to Be
an Electrical Estimator?
w
ie
ev
E
Pr
LECTRICAL CONTRACTING IS A relatively the work of electrical contractors and electrical
new business. Masonry, plumbing, framing, estimators more difficult. But they also make
e
roofing and most construction trades can trace for better, safer, and more durable electrical
in
of America didn’t begin until the 1880s when oped and matured, the role of professional
the first commercial power-generating station electrical estimators became more specialized.
O
was built in New York City. Anyone can quote prices for electrical work.
Most states require that both electricians and
In the early days of electrical contracting, electrical contractors be licensed; but electrical
there was no electrical code. Installation prac- estimators need no license at all. Under the law,
tice was poor by today’s standards. In one group company owners, managers, engineers, super-
of 65 mills where electric power was installed in visors, electricians and salespeople can quote
the 1890s, there were 23 serious fires — in the prices for electrical work. Technicians from
first six months! Still, the demand for electricity telephone companies, alarm system manufac-
increased rapidly. During the 1890s, trade asso- turers, and electrical equipment manufacturers
ciations, insurers and manufacturers developed often quote installation prices for their special-
standards that became the National Electrical ized electrical work.
Code®, first published in 1897.
But please don’t misunderstand. Estimating
The NEC® is revised every three years to bet- the cost of electrical work can be a very detailed,
ter protect people and property. Revisions are exacting discipline. It takes specialized skills
determined after studies by code committees and knowledge to create reliable estimates for
and have resulted in better electrical materials, electrical work. That’s why electrical estimating
more advanced designs and improved installa- is so important to the success of any electrical
tion procedures. Constant code changes make contracting company. Most work is awarded
through competitive bidding. The lowest quali- sized electrical contracting company. With
fied bidder usually gets the job. Profit margins additional experience and training, it’s common
can be thin, especially when work is scarce. The to transition to more complex, more technical
penalty for a haphazard estimate can be a major projects.
loss, and no electrical contracting company
needs more of those. Nearly every electrical Some electrical estimators begin a career
contracting company needs the best effort of at on the staff of a larger electrical contracting
least one qualified electrical estimator. company. A typical estimating department in a
large electrical contracting firm will have one
or two junior or trainee estimators along with
several more experienced estimators. When an
The Electrical Estimator electrical estimator has developed the skills and
w
contacts necessary to be successful, many begin
consulting, or even start electrical contracting
At one time, most electrical estimators were
ie
companies of their own. Some of the busiest and
also electricians, usually with at least six to eight
most successful electrical estimators I know are
years of experience in the field. Experienced
freelancers. Both the rewards and the risks are
ev
electricians tend to be good at reading drawings.
greater when working for yourself. But clearly
They understand contract specifications and
there are advantages to working at your own
are proficient at following the NEC — essential
pace and setting your own hours.
Pr
skills for every electrical estimator. Years ago,
master electricians commonly drafted electri- An electrical estimator’s primary task is
cal layouts, showing receptacles, switches and to develop a reliable estimate of job costs. In
fixtures. These drawings became supplements practice, it seldom stops there. Experienced
to the architectural drawings and were used by
e
and cost estimates were created from electrical identifying risks and opportunities in the job,
drawings prepared by a master electrician. That’s and maximizing value while minimizing costs. A
still true today on small, service-type projects.
nl
specialized today. Electrical estimators seldom On very large projects, there will often be a
draft electrical drawings and almost never chief estimator and several junior estimators. In
specify materials or equipment. Those tasks one of our practice examples, you’ll figure the cost
are typically done by trained specialists, usually of work planned by the electrical design group.
electrical engineers or Computer-Aided Design When done, you’ll hand the estimate over to the
and Drafting (CADD) professionals. Many larger senior estimator who will combine all estimates
projects are “design-build” jobs, where the con- to calculate the project cost. That total goes to
tractor is responsible for both the design and company managers who will set a percentage for
construction. There’s no competitive bidding, markup, turning the estimate into a bid.
but estimates are still required. On design-build
projects, the electrical estimator operates as a Electrical estimating can be either full- or part-
member of the design team, developing ROM time work. Most smaller electrical contracting
(rough order of magnitude) prices for budget companies don’t bid enough jobs to keep an
purposes. electrical estimator busy full-time. The company
owner may be the only qualified electrical
The electrical estimators I know come from estimator available. Some smaller electrical con-
varied backgrounds. Most worked as installers tractors don’t even have an estimator on staff.
before taking a desk job as a service estimator Instead, they call on a freelance estimator when
or residential estimator for a small- to medium- the need arises.
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
Many electrical contracting firms, both large with plans and specifications. The architect pre-
and small, put the electrical estimator to work pares the construction documents. These include
as project manager when a bid is accepted. an advertisement for bids, instructions to bid-
After winning the job, the electrical estimator ders, the contract, general and special conditions
puts on a hard hat and manages the project. to the contract, project specifications, project
That creates a tight feedback loop, making the drawings, and guidelines for administration of
project manager a better estimator (more aware the contract. On larger projects, the architectural
of costs) and the estimator a better project firm will usually retain consulting engineers to
manager (more aware of installation issues). advise on technical phases of the project. These
can include a structural engineer, a mechanical
The best electrical estimators have an instinct engineer and an electrical engineer.
for finding jobs with better-than-average profit
w
potential — and identifying jobs with more risk The structural engineer (SE) designs the
than potential reward. That’s why a skilled skeleton of the project, the foundation, and
ie
electrical estimator is a valuable asset to any supporting members. The SE plans equipment
electrical contracting company — possibly the bases, suspended members, seismic and wind
most valuable member of the team. Electrical resistance and other structural components.
ev
estimators are the first line of defense against
financial loss. The mechanical engineer (ME) designs the
Heating, Ventilating and Air Conditioning
Pr
No matter where you fit in the picture, I (HVAC) system, plumbing and drainage.
hope you’ve decided to build the qualifications
required to create a successful career in elec-
trical estimating. Opportunities are plentiful. Rewards
e
The Design Team paid estimators in the construction industry. Most larger
electrical contracting companies offer novice estimators
O
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
The electrical engineer (EE) designs the subcontractor can’t or won’t finish the work,
electrical system: power generation (either the bonding company hires another company
the primary or standby), primary and back-up to complete the job — and then tries to recover
lighting, a communications system (telephone against the defaulting contractor.
and voice mail), the computer network, a paging
system, a sound system, an employee-recognition The contractor must also provide insurance
security system, an intrusion system, and a fire coverage for casualty losses and other hazards.
alarm system. The electrical engineer must Most electrical contractors also take out the
work closely with the architect, the structural building permit for the electrical portion of
engineer and the mechanical engineer. Electrical the job. Chapter 11, Other Costs to Consider,
estimators have to estimate quantities and has more information on bonds, insurance,
costs for nearly anything an EE can design. licenses and taxes.
w
The design team’s work isn’t done until con- On most jobs, there will be a prime contrac-
tor (the prime) and subcontractors (the subs).
ie
struction is complete. The design team may be
responsible for on-site inspections as the project Sometimes there will be subs to the subs. A sub’s
progresses. The architect’s contract with a con- responsibilities are very similar to those of the
ev
sulting engineer usually requires inspections to prime — just on a smaller scale. An electrical sub
ensure that installation complies with the plans submits a bid to do electrical work described in
and specifications. Consultants check the shop the plans and specs. But that’s not all. Subs have
Pr
drawings (submittals) prepared by manufactur- to meet all requirements of the contract, includ-
ers and subcontractors to be sure the finished ing bonds, insurance, licenses and taxes.
product will meet the property owner’s and
architect’s expectations. The prime contractor is responsible for the
e
property owner and leads the construction team, payments once or twice a month, creating a
usually with the help of a few subcontractors. cascade of payments that go from prime to
The prime contractor receives direction from first-tier to second-tier, etc. If a contract doesn’t
the design team (plans and specs), instruction allow for progress payments, the prime and
from the property owner (the contract) and rules subs may have to take out loans to finance the
from the building codes (including the NEC). project. Interest on such a loan would then
become another cost on your estimate form.
The bid documents usually require the We’ll discuss progress payments in more detail
contractor to supply a bid bond. If the contrac- in Chapter 11.
tor’s bid is selected, the bid bond “binds” the
contractor to sign the construction contract at Subcontractors usually have little or no
the bid price. Most invitations to bid also require direct contact with either the architect or the
that the contractor supply a performance bond property owner. They deal with the contractor
guaranteeing that work will be completed as one tier above and, of course, the inspector.
shown in the plans. Bid bonds and performance
bonds are underwritten by licensed bonding On small jobs, like renovating the electrical
companies and are purchased at the expense system of an existing building, the electrical
of the contractor or subcontractor whose contractor may be the prime contractor, working
performance is guaranteed. If the contractor or directly with the property owner. Again, one or
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
more subs may be called on to do specialty work. alternatives that can save money or add value
The entire construction team may consist of the to the building. The company I currently work
property owner, the contractor, the estimator, for is a design-build firm. We do it all, using our
the foreman, and an office manager who checks own staff.
the estimates and keeps the company books.
Some very large companies have their own
Whether an electrical contractor is the prime construction division. If that’s the case, the prop-
or the sub, the duties will be similar: erty owner may wear all three hats — property
owner, designer and contractor. A builder who is
Finding a job that matches also the property owner will usually administer
company capabilities the contract and set the construction schedule.
Estimating the cost of the job
w
Most property owners don’t have the time or the
Submitting a bid to the property background to manage a complex construction
owner (if the electrical contractor project. It’s usually easier, faster, and cheaper to
ie
is the prime), or to the prime (if the assign the project to a dependable, experienced
electrical contractor is a sub) builder. In that case, the owner may prefer to
ev
have the builder take full charge of both project
Selling the bid — jobs don’t
design and construction (design-build).
usually just fall into your lap
Pr
Signing a contract if the bid is You’ll also hear construction professionals
selected talking about mechanical, electrical and
plumbing (MEP) or mechanical, electrical,
Planning the work (much of this data and plumbing (MEDP) teams. Either way,
happens in the estimating phase) it’s a team approach which combines design
e
Doing the work — following the and estimating for the largest project sub-
in
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
All electrical contractors, from the smallest Even on the contracts you win, you may have
residential firm to the largest multi-state to defend your work. One common criticism:
company, have an interest in avoiding waste of “Why was our bid so much lower than the next
electrical resources. They support restrictions lowest bid? You left too much money on the table.
on the use of incandescent lamps, promote We could have made thousands more.” So keep
fluorescent alternatives, solar generation for good records. Be ready to defend your estimates
homes, commercial and industrial applications, against someone else’s 20/20 hindsight.
better electrical management systems and
designs for large commercial installations. You bid a job to get the contract. Obviously,
it’s wise to bid as low as possible. But bid too
low too often and your company will eventually
go broke. A successful bid covers all costs: labor,
w
materials, equipment, overhead (managers,
Key Elements of a Bid office, taxes, insurance, etc.) and still has a little
left over — your profit. Being the low bidder
ie
The estimating process begins with the plans and getting the job isn’t always what you want.
and specs and ends with the presentation of the If you end up losing money on the job, you’d
ev
bid. Bidding electrical work can be a complex have been better off losing the bid and letting
process and may involve many hours of detailed the “winner” take the loss. A good bid is high
work. Leave out any step and your bid can go enough to earn a profit but low enough to get
Pr
from “first to worst.” the work.
Your job as an electrical estimator is to Finding the best bid price is a careful bal-
calculate the cost of completing the electrical ancing act. Most competitors will have similar
work on a project. That’s your estimated cost, labor, material and equipment costs. Overhead
e
your cost to the contractor for doing the work. costs can vary widely. Profit expectations also
in
Bid price is the figure quoted to the prime vary from contractor to contractor. As an
contractor or the property owner — what the electrical estimator, your primary concern will
property owner has to pay. The difference be the hard costs (labor, material, equipment)
nl
between cost and price is profit. We’ll discuss and overhead. Company management will
both overhead and profit in detail in Chapter decide how much to add for profit. In a small
O
10, Overhead and Profit. firm, the company owner will make decisions
on profit margin. In a larger company, the head
of the electrical contracting division may set
the profit margin.
A Successful Bid
There may only be a few companies in the
Winning a contract for electrical work area qualified to handle the job you’re bidding. If
is seldom easy. In fact, an estimator who’s you’re one of those companies, winning the job
successful 25 percent of the time is the happy may be easy. But if there’s a lot of competition
exception to the rule. As an electrical estimator, for the same job, bidding will be competitive.
assume you’ll have many more defeats than If all bids meet job requirements, the contract
victories. No lawyer, doctor, or baseball player will usually be awarded to the lowest bidder. If
would get by with a construction estimator’s it’s a government or public contract, the lowest
success ratio. An electrical estimator who wins qualified bidder will always get the work. But
as few as 10 percent of the jobs he bids belongs if it’s a private contract, anything can happen:
in the estimating hall of fame. A doctor buries The lowest bidder doesn’t automatically get
his losses; a lawyer visits his in jail. You’re lucky: the job. We’ll deal more with this topic in
The worst outcome is simply rejection. Chapter 15, Smart Bidding.
10
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
w
within that budget. It doesn’t always happen, program doesn’t make you an expert electrical
of course. Mistakes in material purchasing estimator. You have to understand the process
and poor use of field manpower can blow any
ie
from start to finish. Good tools just make it
estimate out of the water. But that should be easier. In the chapters that follow, we’ll do a
uncommon in a well-run electrical contracting couple of manual estimates with pencil and
ev
company. paper to help you understand the process and
There are three basic ways to estimate elec- develop experience.
Pr
trical work:
When you have electrical estimating with
Pure guesswork — which I certainly pencil and paper under your belt, and you’ve
don’t recommend! developed estimating habits that consistently
deliver an estimate you can rely on, it’s time to
e
Pencil, paper, and estimating forms advance into the world of computer estimating.
Computer software specifically Once you’ve done the takeoff, a computer will
in
designed for estimating make it easier to collect and organize material
costs, manhours, labor and equipment costs,
nl
Most electrical estimating is done with a and totals. Then I’ll introduce you to the
computer. Quantity takeoff is usually done by companion volume to this book: National
hand, either based on a site visit or construction
O
11
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
w
ie
ev
Pr
This page intentionally left blank
e
in
nl
O
Index
Actual costs, low ......................................179 contract requirements ......247 estimating with National
w
comparing jobs ......................216 market-based pricing ........235 cost breakdown ..................250 Estimator .........................146
Actual Job Costs opening ................................29 deductive ............................251 schedule, contract ...............21
summary ....................... 212-213 pre-bid conference ...............23 effect on labor costs ...........104 Construction Specifi cations
preparing with extending completion Institute ................................206
ie
fi nancial history ................214
Addenda ....................................23 Job Cost Wizard ........198-201 date ...................................264 CSI MasterFormat
Additive change orders ..........251 price .....................................10 get in writing .....................249 divisions ....................206-207
Adjustments, labor .................160 project specs ........................22 new contract for ................256 Construction team
ev
All Items count ................... 41-43 ROM .....................................13 processing ..........................254 contract obligations ........18-21
Allowance, contingency.. 174-175 rules .....................................21 reasons for .........................249 mechanical, electrical, data,
Altered bids ..............................29 selecting the right job ... 15-16 request for quote (RFQ)....250 plumbing (MEDP) ...............9
Alternative materials ...............51 selling .................................241 review meetings.................253 mechanical, electrical,
Aluminum conductors..............85 submission requirements ...29 subcontractor ....................254 plumbing (MEP) ..................9
Pr
American Arbitration Assoc. .260 tips .....................................244 taking a loss on ..................252
responsibilities .......... 8-9, 116
Ampacity requirements ...........86 trade package ......................32 Circuits, branch .......................71
Contingency ...........................185
Appleton Catalog ....................142 types ............................... 23-29 Claims ............................. 259-265
correct use of ............. 174-175
Appliance circuits, small ..........71 winning ..............................245 damaged materials
or equipment ...................263 defi ned................................173
Arbitration clause ..................260 Bid bond .....................................8
damaged work ...................263 materials percentage .........193
Architect estimate .............................178
preparing ...........................260 percentage ................. 174-175
design team ............................7 fee ............................... 178-179
using National Estimator
e
w
labor, sources for..................93 responsibilities.......................9 equipment takeoff................35 Project Selection
manhour override Electrical devices, catalogs.....142 Excel help tips....................140 Checklist.....................60, 114
percent..............................160 Electrical drawings finalizing bid manually Project Summary Sheet.....217
ie
materials, losing bid.........................................22 . ........................183-184, 191 Project Worksheet..............218
money on...........................252 estimating electrical finalizing bid, Quotation Comparison
quantities...................... 39-44 National Estimator..........193 Spreadsheet........................89
materials, sources for...........81
scale.......................................39 general expenses..................36 sample spreadsheet.... 120-126
National Electrical
ev
Electrical engineer (EE).............7 hand tools.............................99 Scope of Work...............61, 115
Estimator..........................145
manufacturers’ agents.........90 hard costs........................10, 31 Takeoff Worksheet
per item.................................78
Electrical equipment information sharing, . ................... 38, 42, 120-126
range check.........................100
EMA quality standards...........85 computer.............................44 Telephone Quotation Sheet
small tools.............................99
not fully assembled............101 insurance coverage.............180 . .........................................87
Pr
subcontractor.......................99
Electrical estimating keep takeoff secure........ 73-74 Formula
Counters....................................40
computerized......................113 labor costs....................... 34-35 extended costs......................79
Countertop receptacles....... 71-72 material cost sources............81 manhour override percent margin percentage..... 168-169
Counting electrical items... 41-43 National Estimator . .......................................160 markup percent.......... 167-168
Craftsman Book Company.....145 . ....................... 145, 148-156 market-based pricing.........235
Creating estimate, Freelance estimators..................6
using your costs..................214 material cost sources............81 Freight damage............... 263-264
National Estimator....... 148-156 Electrical estimators materials furnished
e
w
safety.....................................34 creating an estimate.. 148-156
adjustments to....................231 importance of........................52
safety/security estimating program............145
defined................................168 site inspection before...........45
considerations.....................48 estimating window.............147
determining percentage.....223 labor cost, percent change 192 topics discussed....................51
ie
supervision...........................34 optimum, charting......170-171 Precut feeder cable.................109
work obstructions.......... 47-48 materials, modifying costs
percentage, calculating . .......................................193 Prefabricated systems............109
Kitchen receptacles........... 71-72 . ............................... 167-168
risk adjustments.................215
menu and toolbars......146-147 Price quotes
electrical bids..........................6
ev
saving estimate...................197
Labor setting by instinct..............215 saving estimate to disk......156 last minute..........................184
cost adjustments................160 Master electricians......................6 ShowMe video.....................146 Pricing, market-based............235
estimate takeoff....................34 MasterFormat system.............206 software program.................11 Prime contractor
rates......................................35 Material takeoffs................. 53-75 splitting costbook backcharges........................264
Pr
Labor adjustment factor.........211 Materials window..............................150 change order process
Labor costs calculating costs...................78 subtotal.......................153, 155 . ............................... 254-255
adjusting manhours.............94 calculating interest on.......193 Negotiated bid...........................28 contract.................................17
change orders.....................251 completing manual takeoff Negotiating jobs........................16 contract obligations.........18-21
classifying...........................208 . ................................... 64-73 NEMA quality standards..........85 Miller Act............................261
estimating.......................93, 97 cost sources...........................81 Net margin..............................169 responsibilities...................116
factors that decrease... 107-110 costs per unit........................79 Nonproductive time.........104-107 subcontractor agreements....18
e
jobsite problems......... 101-103 factory test data...................85 Obstructions, underground...102 Printing estimate....................197
nonproductive time.....104-107 finalizing costs....................193 Office overhead.......................163 Pro forma income statement
overruns..............................220 Omissions, contract..................46 . .......................................230
introducing new.................111
overtime..............................104 Online pricing service.............184 Problems, add
nl
manufacturer specific..........85
scaffold work......................102 Optimum profit percentage....165 contingency for......................174
meeting code requirements
sources............................ 93-94 Ordering, materials................106 Production assets....................223
taking a loss on...................252 . .........................................86
request quotes for quality....84 Overhead.................................157 under utilization................224
Labor only bid...........................28 bid estimate..........................10 Productivity, setting goals......231
O
w
Sub-to-sub charges................263 Security, jobsite.........................48 Supports, conduit, estimating field personnel....................229
Purchasing agents.............. 85-86 Shortcut estimating............ 53-54 . ....................................70-71 management personnel......227
ShowMe video.........................146 supervisors..........................229
Q Symbols, electrical, sample list
ie
uality electrical contractors Signal plans, sample....... 133-134 Underground obstructions.....102
. ............................... 242-245 . .........................................63
Single line diagram, sample....137 Unit cost bid..............................25
Quantities
calculating............................79
Site Takeoff Unit costs...................................78
access....................................47 checking your work........ 74-75 Units
ev
counting...................... 138-143 conditions.............................46 color code........................57, 58 material................................78
QuickBooks Pro.................11, 146 inspection.............................45 detailed, importance of........54 of measure............................78
Quotation, bid preliminary checks...............16 equipment.............................35 Utilities
last minute..........................184 problems..................... 102-103 general expenses..................36 hookup and fees.............. 48-49
supplier request....................84 Site plan lack of..................................103
Pr
items to include....................56
telephone..............................86 electrical sample.................136 labor......................................34 project...................................19
written..................................86 reviewing..............................45
Quotation Comparison Small-appliance circuits...........71
materials...............................33
planning................................55
Value engineering....................51
Spreadsheet Soft wiring systems................109 Vendors
procedure..............................57
sample...................................89 Software, estimating.................44 cancellation charges...........252
sample............................. 58-73
using.....................................88 Sole source................................84 fair dealings..........................91
standard sequence...........56-57
material cost sources............81
Receptacles, kitchen......... 71-72 Special conditions, contract.....21
e
subcontractor costs..............36
Specifications request for quotation...........84
Recordkeeping, for claims......260 Takeoff Worksheet
resolving inconsistencies.....55 selecting..........................88, 90
Records, tracking costs...........204 All Items count.....................42
in
Residential Wiring to the NEC...71 . ........................ 64-65, 70-72 Craftsman Book Company
takeoff form........................118 transferring data
Resolving inconsistencies, . .......................................146
Takeoff Worksheet, to cost sheet........................77
rules for....................................55 Gexpro..................................90
filling in............. 127, 138-143 using............................... 37-39
Restocking charges.................252 Graybar Electric
Takeoff Worksheet, sample Task completion, tracking......208
Retainage...................................51 Company, Inc......................90
. ............................... 120-126 Taxable benefits........................97
Retention................. 181-182, 185 National Electrical
Square foot of floor estimate....54 Taxes
Review meetings.....................253 Contractors Assoc...............93
Standard sequence, takeoff labor costs.............................97
Revisions, NEC...........................5 Trade Service........................81
. ...................................56, 58 project...................................19
Risk analysis................... 215-222 Wire
Standards, energy................. 9-10 Team, construction................. 8-9
asset utilization..................223 boxes and covers,
Stop notice...............................261 Telephone Quotation Sheet
cost elements......................220 counting............................142
Storage, material sample...................................87
cost overruns......................216 calculating lengths..........70-71
and equipment.......................105 using...............................86, 88
job size.........................220-221 estimating........................70-71
Strategic pricing.....................235 Temporary utilities...................48
Rough order of magnitude installing soft wiring
Structural engineer (SE)............7 Tenant improvement (TI)........25
(ROM)........................................6 systems..............................109
Sub-to-sub charges......... 262-263 Test data, manufacturer...........85
bids........................................13 insulation requirements......86
Subcontract Provisions Testing
pricing.....................................6 measuring lengths..............142
for Change Order..................248
Rules, bid...................................21 contract.................................21 sizing.....................................71
Subcontractor
field.....................................112 Wiring devices, counting.........139
Safety change order
Time and materials bid.......25, 28 Work schedules, phased..........103
jobsite....................................48 process....................... 254-255
Time slips Work, finding....................... 14-15
labor cost..............................34 change order requirements
effect on productivity.........211 Working conditions.........107, 111
meetings......................106-107 . ............................... 247-248
w
208 pages, 8½ x 11, $29.75 apprentices and journeymen electricians in the State of California who
must now meet requirements of the new California Electrical Licensing
Law that requires journeymen electricians pass a test. It’s designed with
National Electrical Estimator sample questions and answers, definitions, illustrations, and study tips to
ie
help you pass the exam on the first try. Although written for the California
This year’s prices for installation of all common elec- exam, it can be used as a study guide for any state electrician’s exam that’s
trical work: conduit, wire, boxes, fixtures, switches, based on the 2002 NEC. 96 pages, 8½ x 11, $26.00
outlets, loadcenters, panelboards, raceway, duct,
ev
signal systems, and more. Provides material costs,
manhours per unit, and total installed cost. Explains Construction Forms for Contractors
what you should know to estimate each part of an This practical guide contains 78 practical forms, let-
electrical system. Includes a CD-ROM with an elec- ters and checklists, guaranteed to help you stream-
tronic version of the book with National Estimator, a
Pr
line your office, organize your jobsites, gather and
stand-alone WindowsTM estimating program, plus organize records and documents, keep a handle on
an interactive multimedia video that shows how to your subs, reduce estimating errors, administer
use the disk to compile construction cost estimates. change orders and lien issues, monitor crew produc-
552 pages, 8½ x 11, $62.75. Revised annually tivity, track your equipment use, and more. Includes
accounting forms, change order forms, forms for
National Construction Estimator customers, estimating forms, field work forms, HR
e
hours, recommended crew, and gives the labor cost for installation. on your computer, and as PDFs. 360 pages, 8½ x 11, $48.50
Includes a CD-ROM with an electronic version of the book with National
Estimator, a stand-alone WindowsTM estimating program, plus an interac-
tive multimedia video that shows how to use the disk to compile con- ElectriCalc Pro Calculator
nl
struction cost estimates. 664 pages, 8½ x 11, $62.50. Revised annually This unique calculator, based on the 2002 National Electrical Code and
updateable to future NEC codes, solves electrical problems in seconds:
Calculates wire sizes, gives you integrated voltage drop solutions, conduit
Residential Wiring to the 2008 NEC sizing for 12 types of conduit, and finds motor full-load amps per the cur-
O
This completely revised manual explains in sim- rent NEC. Also offers one-button parallel and de-rated wire sizing, com-
ple terms how to install rough and finish wiring in putes fuse and breaker sizes, sizes overload protection, calculates service
new construction, alterations, and additions. It and equipment grounding conductor sizes, finds NEMA starter sizes, works
takes you from basic electrical theory to current in volts, volt-amps, watts, kVA, kW, PF%, and DC resistance, and even oper-
wiring methods that comply with the 2008 ates as a math calculator. 3½ x 7, $99.95
National Electrical Code. You’ll find complete
instructions on troubleshooting and repairs of Estimating Home Building Costs, Revised
existing wiring, and how to extend service into
additions and remodels. Hundreds of drawings Estimate every phase of residential construction from site costs to the
and photos show you the tools and gauges you profit margin you include in your bid. Shows how to keep track of man-
need, and how to plan and install the wiring. hours and make accurate labor cost estimates for site clearing and exca-
Includes demand factors, circuit loads, the formulas you need, and over 20 vation, footings, foundations, framing and sheathing finishes, electrical,
pages of the most-needed 2008 NEC tables to help your wiring pass plumbing, and more. Provides and explains sample cost estimate work-
inspection the first time. Includes a CD-ROM with an Interactive Study sheets with complete instructions for each job phase. This practical guide
Center that helps you retain what you’ve learned, and study for the elec- to estimating home construction costs has been updated with digital Excel
trician’s exam. Also on the CD is the entire book in PDF format, with easy estimating forms and worksheets that ensure accurate and complete esti-
search features so you can quickly find answers to your residential wiring mates for your residential projects. Enter your project information on the
questions. 248 pages, 8½ x 11, $42.00 worksheets and Excel automatically totals each material and labor cost
from every stage of construction to a final cost estimate worksheet. Load
Building Code Compliance for Contractors & Inspectors the enclosed CD-ROM into your computer and create your own estimate
as you follow along with the step-by-step techniques in this book.
Have you ever failed a construction inspection? Have 336 pages, 8½ x 11, $38.00
you ever dealt with an inspector who has his own
interpretation of the Code and forces you to comply Basics of Household Wiring Extended Edition DVD
with it? This new book explains what it takes to pass
inspections under the 2009 International Residential An excellent training DVD designed to get new hires, trainees or beginners
Code. It includes a Code checklist — with explana- in the electrical field up to speed with the complexities of household
tions and the Code section number — for every wiring. While it won’t help you pass the electrician’s exam, this DVD will
trade, covering some of the most common reasons show you, using illustrated examples, how to correctly wire a three and
why inspectors reject residential work. The author four-ways switch, install GFCIs for single and multi-location protection,
uses his 30 years’ experience as a building code offi- wire switch loops, half receptacles, two-gang receptacles and much more.
cial to provide you with little-known information on You’ll also learn to understand the difference in amps, volts, and watts, arc-
what code officials look for during inspections. fault circuit interrupters, electricity flow and service panels, just to name a
232 pages, 8½ x 11, $32.50 few. 1 hour and 27 minutes, $19.95
Buy similar Craftsman Book Co. titles here: https://www.Craftsman-Book.com
Buy this complete title here: https://goo.gl/A70Eh1
w
house is properly grounded, and install receptacles, GFCIs, switches, fix- ers, capacitors, distribution equipment, branch circuits, feeders, calcula-
tures and appliances per NEC requirements. Dozens of diagrams and full- tions, measuring and testing, and more. It gives you the correct answer, an
color illustrations show you exactly how the work goes together. explanation, and where to find it in the latest NEC. Also tells how to apply
for the test, how best to study, and what to expect on examination day.
ie
248 pages, 8½ x 11, $24.95
Includes a FREE CD-ROM with all the questions in the book in interactive
Illustrated Guide to the 1999 National Electrical Code test-yourself software that makes studying for the exam almost fun!
Updated to the 2011 NEC. 352 pages, 8½ x 11, $54.50
ev
This fully-illustrated guide offers a quick and easy visual reference for
installing electrical systems. Whether you’re installing a new system or Also available: Electrician’s Exam Preparation Guide 2008, $49.50
repairing an old one, you’ll appreciate the simple explanations written by
a code expert, and the detailed, intricately-drawn and labeled diagrams. A
real time-saver when it comes to deciphering the 1999 NEC. National Repair & Remodeling Estimator
Pr
360 pages, 8½ x 11, $38.75
The complete pricing guide for dwelling reconstruction costs. Reliable,
specific data you can apply on every repair and remodeling job. Up-to-
DeWalt Wiring Quick Check date material costs and labor figures based on thousands of jobs across
Understanding complex electrical formulas is one of the most important the country. Provides recommended crew sizes; average production rates;
tasks facing today’s electricians. Accurate calculations make for proper exact material, equipment, and labor costs; a total unit cost and a total
code compliance and safe installations.This easy-to-use flipchart compiles price including overhead and profit. Separate listings for high- and low-
the most commonly-used electrical formulas and simplifies them, using a volume builders, so prices shown are specific for any size business.
e
step-by-step approach and practical, real-world examples. Topics range Estimating tips specific to repair and remodeling work to make your bids
from Ohm’s Law and power formulas to areas of conduit and conduit fill, complete, realistic, and profitable. Includes a CD-ROM with an electronic
in
minimum burial depth, clear working space and optional service load cal- version of the book with National Estimator, a stand-alone WindowsTM esti-
culations. With easy-reference tabs and a sturdy design, this is a beneficial mating program, plus an interactive multimedia video that shows how to
tool that will stand the test of time, weather, and a variety of jobsite and use the disk to compile construction cost estimates.
toolbox conditions. 40 pages, 4 x 8½, $14.95 504 pages, 8½ x 11, $63.50. Revised annually
nl
Download all of Craftsman's most popular costbooks for one low price with the
Craftsman Site License. http://www.craftsmansitelicense.com
O